`
`IN THE UNITED STATES DISTRICT COURT
`FOR THE WESTERN DISTRICT OF WISCONSIN
`
`
`NATIONAL WILDLIFE REFUGE ASSOCIATION,
`DRIFTLESS AREA LAND CONSERVANCY, WISCONSIN
`WILDLIFE FEDERATION, and DEFENDERS OF WILDLIFE,
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`v.
`
`
`
`
`
`
`
`
`
`Plaintiffs,
`
`
`
`
`
`
`
`
`
`
`
`OPINION AND ORDER
`
`21-cv-096-wmc &
`21-cv-306,
`Consolidated
`
`RURAL UTITLITIES SERVICE,
`CHRISTOPHER MCLEAN, Acting Administrator,
`Rural Utilities Service,
`UNITED STATES FISH AND WILDLIFE SERVICE,
`CHARLES WOOLEY, Midwest Regional Director, and
`SABRINA CHANDLER, Manager, Upper Mississippi River
`National Wildlife and Fish Refuge,
`UNITED STATES ARMY CORPS OF ENGINEERS,
`LIEUTENANT GENERAL SCOTT A. SPELLMON, Chief of
`Engineers and Commanding General, U.S. Army Corps of
`Engineers, COLONEL STEVEN SATTINGER, Commander
`And District Engineer, Rock Island District, U.S. Army Corps of
`Engineers, and COLONEL KARL JANSEN, Commander and
`District Engineer, St. Paul District, U.S. Army Corps of Engineers,
`
`
`
`
`
`AMERICAN TRANSMISSION COMPANY, LLC,
`DAIRYLAND POWER COOPERATIVE, & ITC
`MIDWEST LLC,
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`Defendants,
`
`
`
` and
`
`Intervenor-Defendants.
`
`In this lawsuit, plaintiffs National Wildlife Refuge Association, Driftless Area Land
`
`Conservancy, Wisconsin Wildlife Federation, and Defenders of Wildlife challenge the
`
`actions of various federal agencies permitting the Cardinal-Hickory Creek (“CHC”)
`
`Transmission Line Project, which would run from the Hickory Creek substation west of
`
`
`
`Case: 3:21-cv-00306-wmc Document #: 149 Filed: 01/14/22 Page 2 of 45
`
`Dubuque, Iowa, through far Southwest Wisconsin near Cassville and the Mississippi River
`
`to Middleton in the center of Southern Wisconsin, all through what is known as “the
`
`Driftless Area.”1 The utility companies charged with building and operating the CHC --
`
`American Transmission Company, LLC (“ATC”), Dairyland Power Cooperative
`
`(“Dairyland”) and ITC Midwest LLC (“ITC”) (the “Utilities”) -- later joined the suit as
`
`intervenor-defendants. Now at the merits stage, the court finds that defendants fail to
`
`meet legal requirements for the Environmental Impact Statement, Compatibility
`
`Determination, and Land Transfer.
`
`BACKGROUND2
`
`As proposed, the CHC project would create a 345-kilovolt electricity transmission
`
`line between 100 and 125 miles long. (ROD004933-34.) As part of the project, a new
`
`electricity substation would also be constructed in Montfort, Wisconsin. (Id.) Intervenor-
`
`defendants Dairyland, ATC, and ITC intend to construct, own and operate the CHC line
`
`jointly. (ROD004940.) Several areas of the proposed CHC project cover existing rights-
`
`
`1 The Driftless area is a region in Iowa, Wisconsin, and Minnesota. This region was not flattened
`by glaciers like many other areas of the Upper Midwest, leading to a unique geographic region with
`hills, bluffs and valleys. Many species of plant and animal call this region home, such as the Timber
`Rattlesnake, the Northern Monkshood, and the Brook Trout. “Defining the Driftless,”
`https://driftlesswisconsin.com/defining-the-driftless/ (last visited December 30, 2021).
`
`2 Intervenor-defendants moved to strike plaintiffs’ proposed findings of fact (dkt. #113) from
`consideration, as the parties agreed in their preliminary pretrial conference report that proposed
`findings would be unnecessary. (Report (dkt. #40) 13.) Because the court did not rely on any
`parties’ proposed findings of fact for summary judgment, but instead relied directly on the
`administrative record, that motion will be denied as moot, along with plaintiffs’ related motion for
`leave to reply (dkt. #165).
`
`
`
`2
`
`
`
`Case: 3:21-cv-00306-wmc Document #: 149 Filed: 01/14/22 Page 3 of 45
`
`of-way owned by the Utilities and would also involve replacing or upgrading existing
`
`facilities. (Id.)
`
`Midcontinent Independent System Operator, Inc. (“MISO”), an independent not-
`
`for-profit group which manages the power grid in 15 states, worked with various state
`
`regulators and utility industry stakeholders from 2008 to 2011 to identify projects that
`
`would increase energy transmission and usage of renewable energy. (ROD004981.) One
`
`identified project was to connect Dubuque, Iowa, to southwest Wisconsin, which would
`
`provide cheaper wind power to Milwaukee and Chicago, as well as reduce overloaded power
`
`lines. (ROD031340-41.) This in turn developed into the proposed CHC transmission line
`
`project. (ROD004981.)
`
`Because Dairyland expressed an intent to request funding for its 9% stake in the
`
`CHC project from the U.S. Department of Agriculture Rural Utilities Service (“RUS”),
`
`that government entity led the effort to prepare an Environmental Impact Statement
`
`(“EIS”) in cooperation with U.S. Fish and Wildlife Service (“Fish and Wildlife”), the U.S.
`
`Army Corps of Engineers (“Corps”) and the U.S. Environmental Protection Agency
`
`(“EPA”). (ROD004941.) The Utilities also asked (1) Fish and Wildlife for a right of way
`
`easement and special use permit to cross the Upper Mississippi River National Wildlife
`
`and Fish Refuge (“the Refuge”), and (2) the Corps for permits to build in navigable waters
`
`of the United States. (ROD004942.)
`
`Before granting a right of way through the Refuge, Fish and Wildlife must confirm
`
`that the proposed project comports with the purposes of the Refuge under 16 U.S.C.A.
`
`§ 668dd. Fish and Wildlife originally finalized its “Compatibility Determination for the
`
`
`
`3
`
`
`
`Case: 3:21-cv-00306-wmc Document #: 149 Filed: 01/14/22 Page 4 of 45
`
`CHC” on December 20, 2019. (ROD007584.) Because the Utilities already had a prior
`
`right of way through the Refuge, where a 161 and 69kv transmission line had been
`
`previously installed (ROD17047) and the Utilities had agreed to transfer back that right
`
`of way (ROD007574), Fish and Wildlife found the proposed CHC line was compatible
`
`with the purposes of the Refuge as “a minor realignment of an existing right-of-way” and
`
`granted a permit to the Utilities. (ROD007574.)
`
`On March 1, 2021, however, the Utilities contacted Fish and Wildlife and asked
`
`for a slightly amended right of way through the Refuge, ostensibly to avoid Ho-Chunk
`
`burial grounds. (Zoppo Decl., Ex. A (dkt. #53-1) 2-3.) Then, before Fish and Wildlife
`
`could issue a decision on the proposed amendment, the Utilities again contacted Fish and
`
`Wildlife on July 29, 2021, this time asking for an expedited land exchange instead of an
`
`amended right of way, ostensibly because approval for a new right of way would take too
`
`long. (Zoppo Decl. (dkt. #53-2) 1.) Specifically, in exchange for a land exchange in the
`
`Refuge, the Utilities were now proposing to transfer a 30-acre parcel to Fish and Wildlife.
`
`(Id.) On August 3, 2021, Fish and Wildlife confirmed receipt of the Utilities’ latest
`
`proposal, indicating that its response to such a land exchange “may” be “favorable.”
`
`(Zoppo Decl. (dkt. #53-3) 1.)
`
`Then, on August 27, 2021, less than a month after Fish and Wildlife responded
`
`favorably to a proposed land transfer, and less than a week before summary judgment
`
`motions were due in this case, Fish and Wildlife “withdrew” its entire original
`
`Compatibility Determination, stating it “learned that an error had previously been made
`
`regarding the 2019 Compatibility Determination when identifying the existing rights-of-
`
`
`
`4
`
`
`
`Case: 3:21-cv-00306-wmc Document #: 149 Filed: 01/14/22 Page 5 of 45
`
`way proposed for re-alignment.” (Not. by Def. (dkt. #69-1) 1.) As a result, any approved
`
`right of way through the Refuge was rescinded, along with the compatibility determination.
`
`(Id.) However, in its letter of withdrawal to the Utilities, Fish and Wildlife did note that
`
`the agency “is committed to working with you toward timely review of the land exchange
`
`you have proposed in lieu of your March 2021 application for an amended right-of-way
`
`permit . . . [and] concurs that a land exchange is a potentially favorable alternative to a
`
`right-of-way permit.” (Id.)
`
`As for the Corps’ involvement, both its Rock Island and Saint Paul district offices
`
`issued permits, as each office covers a different area of the CHC line. (USACE000094;
`
`USACE000679.) Specifically, the Corps’ Rock Island office is responsible for those
`
`sections of the CHC project running through Iowa and authorized the project under
`
`Nationwide Permit 12 (“NWP 12”). Generally, such nationwide permits (“NWPs”) are
`
`used as a means to expedite permissions to build without needing to go through the more
`
`demanding, individual permitting process. (USACE001200.) Instead, proposed projects
`
`permitted by an NWP only require that the Corps do a project-specific “verification” to
`
`ensure that it meets the requirements of the nationwide permit. (USACE001199.) The
`
`CHC was verified in November of 2019. (USACE001199.) However, NWP 12 was later
`
`revoked by the Corps in part, and now only covers oil and gas pipelines, meaning that
`
`companies building utility lines like the CHC project will need to be permitted under NWP
`
`57. To date, the Utilities have not yet reapplied for an NWP 57 permit. See “Regulatory
`
`Program
`
`&
`
`Permits,”
`
`U.S.
`
`Army
`
`Corps
`
`of
`
`Engineers,
`
`
`
`5
`
`
`
`Case: 3:21-cv-00306-wmc Document #: 149 Filed: 01/14/22 Page 6 of 45
`
`https://www.usace.army.mil/Missions/Civil-Works/Regulatory-Program-and-Permits/
`
`Nationwide-Permits/ (last visited Jan. 14, 2022).
`
`In contrast, the Saint Paul district Corps never relied on NWP 12; instead, it issued
`
`a separate permit. (USACE013001.) Specifically, the Saint Paul office issued a Regional
`
`Utility General Permit (“RUGP”), which mirrors NWP 12 for the most part, while applying
`
`to operations in the Saint Paul District that includes the relevant portions of Southwest
`
`Wisconsin. (USACE000730.) The Corps verified the proposed CHC project under the
`
`RUGP in December of 2019 (USACE000679), which is active. (USACE000679.) Various
`
`other state permits have been issued for the CHC project as well, although none of those
`
`are challenged in this case. (USACE000012.)
`
`I. Mootness
`
`OPINION
`
`The Administrative Procedure Act (“APA”) grants judicial review of agency action
`
`to persons “suffering legal wrong because of agency action, or adversely affected or
`
`aggrieved by agency action within the meaning of the relevant statute.” 5 U.S.C. § 702.
`
`More specifically, APA § 704 provides that “final agency action for which there is no other
`
`adequate remedy in a court [is] subject to judicial review.” 5 U.S.C. § 704. Finally, APA
`
`§ 706 grants courts the power to set aside agency actions that are “arbitrary, capricious, or
`
`otherwise not in accordance with law,” 5 U.S.C.§706(2)(A), while affording appropriate
`
`deference to administrative decisions.
`
`
`
`6
`
`
`
`Case: 3:21-cv-00306-wmc Document #: 149 Filed: 01/14/22 Page 7 of 45
`
`Both governmental and intervenor-defendants argue that many of the challenged
`
`actions here are now moot. Specifically, defendants point to the fact that the Fish and
`
`Wildlife’s original Compatibility Determination and issuance of a right of way through the
`
`Refuge have been revoked, while the proposed land transfers have not yet been finalized.
`
`Yet none of these arguments hold up to scrutiny, as the specific facts of this case compel
`
`the court to rule on the challenged permits, as they are certain to have to be revisited by
`
`this court in similar form, except under even more pressing and difficult circumstances.
`
`While this court’s jurisdiction “is limited by Article III to live cases and
`
`controversies,” the doctrine of mootness generally weighs against relinquishing jurisdiction.
`
`Ozinga v. Price, 855 F.3d 730, 734 (7th Cir. 2017). This is particularly true when a party
`
`voluntarily ceases the disputed conduct, rather than face a lawsuit forcing the conduct to
`
`stop. Friends of the Earth, Inc. v. Laidlaw Env’t Servs. (TOC), Inc., 528 U.S. 167, 189 (2000).
`
`Thus, the Supreme Court has adopted a “strict” standard in cases of voluntary cessation,
`
`as “[i]t is well settled that ‘a defendant’s voluntary cessation of a challenged practice does
`
`not deprive a federal court of its power to determine the legality of the practice.’” Friends
`
`of the Earth, Inc. 528 U.S. at 189 (citing City of Mesquite v. Aladdin’s Castle, Inc., 455 U.S.
`
`283, 289 (1982)). In such cases, the court may only find mootness if “subsequent events
`
`make it absolutely clear that the allegedly wrongful behavior could not reasonably be
`
`expected to recur.” Id. (citing United States v. Concentrated Phosphate Export Assn., 393 U.S.
`
`199, 203 (1968)). This burden shifts slightly if: (1) the party voluntarily ceasing an action
`
`is the government; and (2) “a government actor sincerely self-corrects the practice at issue.”
`
`Freedom From Religion Found., Inc. v. Concord Cmty. Sch., 885 F.3d 1038, 1051 (7th Cir.
`
`
`
`7
`
`
`
`Case: 3:21-cv-00306-wmc Document #: 149 Filed: 01/14/22 Page 8 of 45
`
`2018). In that case, “a court will give this effort weight in its mootness determination,”
`
`although a case may still be “live” if it “cannot give definitive weight to the [government’s]
`
`statements.” Id.
`
`Under the circumstances here, the court cannot help but conclude that any
`
`mootness determination would require a finding of absolute clarity that a return to a
`
`request for a right of way could not reasonably be expected, especially because the Utilities
`
`offer only 30 days’ notice from its reissuance to begin building through the heart of the
`
`Refuge. Even assuming a slightly lower standard applied because Fish and Wildlife is a
`
`governmental body -- albeit one seemingly working hand-in-glove with the Utilities up to
`
`and including suddenly withdrawing the right of way through the Refuge just weeks before
`
`plaintiffs’ challenge was to become ripe for summary judgment consideration by this court
`
`-- the only other alternative is a nearly identical crossing through land transfers approved
`
`by Fish and Wildlife, which will be subject to the same or very similar challenges. Indeed,
`
`there remains no reasonable doubt on this record that both the Utilities and Fish and
`
`Wildlife remain committed to a path through the Refuge (whether by land transfer or a
`
`reissued right of way). Nevertheless, the court will address mootness and standing issues
`
`as to plaintiffs’ principal claims in more detail before turning to the merits of those claims.
`
`A. Compatibility Determination
`
`Plaintiffs’ strongest claim is their challenge to the Fish and Wildlife’s original
`
`Compatibility Determination, which granted the Utilities the original right of way through
`
`the Refuge. However, defendants argue that the withdrawal of the right of way by Fish
`
`and Wildlife renders that claim moot, especially since the Utilities are now planning to
`
`
`
`8
`
`
`
`Case: 3:21-cv-00306-wmc Document #: 149 Filed: 01/14/22 Page 9 of 45
`
`seek land transfers with Fish and Wildlife to run through the Refuge instead. (Defs.’ Mot.
`
`(dkt. #93) 45; Not. by Def. (dkt. #69-1) 1.)
`
`As previously explained, the history of the Compatibility Determination and
`
`issuance of the original right of way is a convoluted one, with the Utilities later requesting
`
`an amended right of way and now a land transfer, then Fish and Wildlife withdrawing its
`
`determination altogether, and with it, the existing right of way. Suspiciously, all of these
`
`actions took place in the months after this case was filed. Moreover, in weighing the
`
`likelihood of reoccurrence against Fish and Wildlife’s voluntary cessation, the court finds
`
`that a very similar compatibility determination is not only likely but nearly certain to
`
`reoccur.
`
`In response, defendants contend that the original right of way permit issued in 2020
`
`will never be reissued given the Utilities request for a planned land transfer instead of a
`
`permit. (Defs.’ Mot. (dkt. #93) 46.) That response is thin porridge indeed. While the
`
`Utilities have waffled between seeking another right of way or land transfers, at no point
`
`has Fish and Wildlife or the Utilities suggested that the CHC would not cross the Refuge,
`
`which mean the Utilities’ request for another Compatibility Determination is a near
`
`certainty and its outcome is at least “potentially favorable” for the Utilities. Indeed, the
`
`government’s Final EIS itself acknowledges as much: “[a]ll action alternatives would cross
`
`the Refuge,” and the EIS did not even consider any routes not crossing the Refuge.
`
`(ROD004950.) Instead, the government relied on “the Utilities’ investigation and
`
`assessment of potential Mississippi River crossing locations for the proposed C-HC Project”
`
`
`
`9
`
`
`
`Case: 3:21-cv-00306-wmc Document #: 149 Filed: 01/14/22 Page 10 of 45
`
`and accepted the Utilities’ own analysis that the CHC must cross the Refuge.
`
`(ROD005006.)
`
`Without even a cursory analysis of non-Refuge crossings beyond the Utilities’ self-
`
`funded research, both defendants and intervenor-defendants have already made their
`
`choice and the CHC transmission line will, by right of way or land transfer, still cross the
`
`Refuge. In fact, the Utilities continue to clear land on both the Iowa and Wisconsin sides
`
`of the Refuge as though its crossing were inevitable. (11/1/21 Op. & Order (dkt. #16) 3.)
`
`Thus, the Utilities must gain access to the Refuge under either of two ways: receive a right
`
`of way through a renewed compatibility determination process or acquire a fee simple title
`
`through land transfers with Fish and Wildlife, which as discussed below raises all the same
`
`concerns as a compatibility study.
`
`Moreover, the fact that Fish and Wildlife is now expecting to review a land transfer
`
`favorably does not mean that a renewed right of way request is in the offing, and as
`
`discussed above, a controversy is not moot unless “it is absolutely clear [that] the allegedly
`
`wrongful behavior could not reasonably be expected to recur,” which the Supreme Court
`
`has interpreted as an extremely high bar. Friends of the Earth, Inc., 528 U.S. at 189 (citing
`
`United States v. Concentrated Phosphate Export Assn., 393 U.S. 199, 203 (1968)) (emphasis
`
`added). For example, when the Governor of Missouri announced that the state was
`
`revoking a challenged policy about grants for religious organizations, the Supreme Court
`
`found that the State still had “not carried the ‘heavy burden’ of making ‘absolutely clear’
`
`that it could not revert to its policy.” Trinity Lutheran Church of Columbia, Inc. v. Comer, 137
`
`S. Ct. 2012, 2019 n.1 (2017). Similarly, while the Utilities may proceed by land transfer
`
`
`
`10
`
`
`
`Case: 3:21-cv-00306-wmc Document #: 149 Filed: 01/14/22 Page 11 of 45
`
`through the Refuge, it is equally as likely that they will have to revert to seeking a right of
`
`way. As such, defendants have not met the heavy burden required to moot plaintiffs’
`
`challenge to the Compatibility Determination.
`
`If the land transfer were to fall through, the government defendants alternatively
`
`contend that the Utilities would be requesting an amended right of way permit, which will
`
`be different than the original request. (Defs.’ Mot. (dkt. #93) 46.) However, an amended
`
`right of way request will not be so different as to moot plaintiffs’ challenge. Indeed, such
`
`a request would have to cover nearly the same acreage within the Refuge, something that
`
`the Utilities are all but assuring as they continue to clear the path for the CHC line up to
`
`the Refuge from both the Iowa and Wisconsin sides even as this lawsuit pends. (Zoppo
`
`Decl., Ex. B (dkt. #53-2) 5.)
`
`In a case involving preferential treatment for city contracts, the Supreme Court held
`
`that similar, minor changes to the repealed conduct cannot moot a case:
`
`There is no mere risk that [the city] will repeat its allegedly
`wrongful conduct; it has already done so. Nor does it matter
`that the new ordinance differs in certain respects from the old
`one. City of Mesquite does not stand for the proposition that it
`is only the possibility that the selfsame statute will be enacted
`that prevents a case from being moot; if that were the rule, a
`defendant could moot a case by repealing the challenged
`statute and replacing it with one that differs only in some
`insignificant respect . . . The new ordinance may disadvantage
`[plaintiffs] to a lesser degree than the old one, but insofar as it
`accords preferential treatment . . . it disadvantages them in the
`same fundamental way.
`
`Ne. Fla. Chapter of Associated Gen. Contractors of Am. v. City of Jacksonville, Fla., 508 U.S. 656,
`
`662 (1993). Thus, the fact that Fish and Wildlife may grant land transfers or issue a
`
`slightly amended right of way that require less acreage does not change plaintiffs’ main
`
`
`
`11
`
`
`
`Case: 3:21-cv-00306-wmc Document #: 149 Filed: 01/14/22 Page 12 of 45
`
`complaint that placement of the CHC line through the Refuge is not compatible with its
`
`purposes.
`
`Finally, while intervenor-defendants assert they are acting in good faith, there is
`
`substantial, contrary evidence in this record. As noted, the Utilities did not ask to amend
`
`their right-of-way permit until after this litigation commenced (Zoppo Decl., Ex. A (dkt.
`
`#53-1) (letter dated March 1, 2021)), and Fish and Wildlife suddenly “discovered” errors
`
`in the Compatibility Determination that warranted withdrawal, which defendants argue
`
`conveniently moots any pending challenges to a Refuge crossing, just a week before opening
`
`briefs on summary judgment were due in this case. (Not. of Withdrawal (dkt. #69).)
`
`Shortly before this, the Utilities suggested a land transfer, which they maintain was only
`
`because it would allow construction to begin faster (Zoppo Decl., Ex. B (dkt. #53-3)), an
`
`option that Fish and Wildlife promptly indicated may be a good option (id., Ex. C).
`
`At the same time, the Utilities have continued construction on the Iowa side of the
`
`line and started construction on the Wisconsin side in October 2021, even as they
`
`maintained passage through the Refuge was uncertain, ignoring that the obvious connector
`
`between the two portions of the line under construction runs straight through the Refuge.
`
`(ROD005063.) In particular, on August 11, 2021, the Utilities requested a stay from the
`
`court pending a possible land transfer, stating that they would not begin work in the Refuge
`
`until October 2022, while offering to give plaintiffs all of “30 days’ notice” before starting
`
`actual construction in the Refuge. (Intervenor-Defs.’ Mot. (dkt. #50) 3.) Then, on
`
`September 24, 2021, the Utilities notified the court that they would start construction in
`
`Wisconsin on October 25, 2021, leaving the Refuge and a few, federal wetlands as the only
`
`
`
`12
`
`
`
`Case: 3:21-cv-00306-wmc Document #: 149 Filed: 01/14/22 Page 13 of 45
`
`portion of the line not under construction. (Not. (dkt. #96) 1.) This, despite the fact that
`
`the summary judgment motions in this case would have otherwise been due on November
`
`1, 2021, and the Utilities still did not have a valid right of way or approved land transfer
`
`through the Refuge. (Not. (dkt. #96) 1.)3
`
`Given these facts, plaintiffs contend, and the court finds credible, that the Utilities
`
`are pushing forward with construction on either side of the Refuge, even without an
`
`approved path through the Refuge, in order to make any subsequent challenge to a Refuge
`
`crossing extremely prejudicial to their sunk investment, which will fall on their ratepayers
`
`regardless of completion of the CHC project, along with a guaranteed return on the
`
`Utilities’ investment in the project. Thus, if the court does not treat consideration of the
`
`essentially inevitable re-proposal for a Refuge crossing as ripe for consideration now, the
`
`Utilities will have built up to either side of the Refuge, making entry of a permanent
`
`injunction later all the more costly, not just to the Utilities and their ratepayers, but to the
`
`environment they are altering on an ongoing basis.
`
`B. Land Transfer
`
`Even if the original challenge to the Compatibility Determination were not ripe, a
`
`challenge to land transfer, as the only alternative for crossing the Refuge, would be. Of
`
`course, the intervenor defendants similarly argue that the court cannot yet review the Fish
`
`
`3 Plaintiffs filed a preliminary injunction to halt construction, and the Utilities again emphasized
`at a court hearing, that they had always planned to begin Wisconsin construction in October 2021.
`(11/22/21 Hr’g Tr. (dkt. #173) 8-14.) Construction is already underway in Iowa, with clearing
`occurring in Wisconsin subject to the court’s preliminary injunction order protecting a few
`designated wetlands. (Id. 9-12.)
`
`
`
`13
`
`
`
`Case: 3:21-cv-00306-wmc Document #: 149 Filed: 01/14/22 Page 14 of 45
`
`and Wildlife’s approval of land transfers, as there is no final decision or record to review.
`
`(Intervenor-Defs.’ Opp’n (dkt. #112) 8.) However, the defendants’ argument is premised
`
`on the likely mistaken assumption that Fish and Wildlife may apply different decision
`
`criteria to the land transfer than the right of way, necessarily leading to the need for the
`
`creation of a new administrative record. In fact, the proposed land exchange would very
`
`likely have to meet the same compatibility requirements of the Refuge Act, making any
`
`analysis done by Fish and Wildlife for the land exchange and the right of way practicably
`
`identical.
`
`Thus, the possible, minor change to the proposed Refuge crossing does not
`
`constitute a sufficient change to moot the agency’s original compatibility analysis, and the
`
`difference between the CHC’s crossing the Refuge by right of way or fee simple title
`
`transfers are negligible where the underlying effect of allowing the crossing is the same. See
`
`Ne. Fla. Chapter of Associated Gen. Contractors of Am. v. City of Jacksonville, Fla., 508 U.S. 656,
`
`662 (1993) (holding it does not “matter that the new ordinance differs in certain respects
`
`from the old one”). As such, the issue of compatibility -- whether by exchange or by right
`
`of way -- is not only ripe, but the only way to ensure an orderly review of the project under
`
`the National Environmental Protection Act (“NEPA”).
`
`Finally, the Supreme Court has held that the question of whether an agency decision
`
`is “final” depends upon “the fitness of the issues for judicial decision and the hardship to
`
`the parties of withholding court consideration.” Abbott Lab’ys v. Gardner, 387 U.S. 136,
`
`149 (1967), abrogated on other grounds by Califano v. Sanders, 430 U.S. 99 (1977). Thus,
`
`“[t]he cases dealing with judicial review of administrative actions have interpreted the
`
`
`
`14
`
`
`
`Case: 3:21-cv-00306-wmc Document #: 149 Filed: 01/14/22 Page 15 of 45
`
`‘finality’ element in a pragmatic way,” with the Supreme Court finding a statement by the
`
`Federal Communications Commission as reviewable even though “the FCC regulation
`
`could properly be characterized as a statement only of its intentions.” Abbott, 387 U.S.
`
`136 at 149.
`
`Even if Fish and Wildlife does not have to follow the Refuge Act’s compatibility
`
`requirements for a land exchange, Fish and Wildlife’s own, anticipated approval of a land
`
`exchange to proceed with a Refuge crossing and the hardship that a delay in consideration
`
`would cause plaintiffs compels the court to review the proposed crossing now. Specifically,
`
`the letter from Fish and Wildlife stating its concurrence “that a land exchange is a
`
`potentially favorable alternative to a right-of-way permit,” as well as its subsequent
`
`revocation of the original right of way to avoid orderly review, are statements of intent.
`
`(Notice (dkt. #69-1) 1.) In fact, as previously discussed, Fish and Wildlife has created a
`
`situation where a land exchange or similar right of way are the only options left to
`
`defendants, making its statement of intent all but a guarantee, while they continue to
`
`attempt to evade judicial review until any route, other than through the Refuge, would be
`
`so prejudicial that a court would have little choice but to approve the crossing -- creating
`
`the very hardship that the Supreme Court warned against in Abbot. If anything, both the
`
`government defendants and Utilities appear to be playing a shell game, cavalierly revoking
`
`applications for and grants of permits, all as a Refuge crossing becomes a near certainty,
`
`while telling this court that nothing is yet reviewable.
`
`Defendants also fail on public policy grounds. In Abbott, the Supreme Court was
`
`being asked to review a drug labeling regulation where the government similarly argued
`
`
`
`15
`
`
`
`Case: 3:21-cv-00306-wmc Document #: 149 Filed: 01/14/22 Page 16 of 45
`
`that reviewing the regulation and halting its enforcement would be harmful to the public
`
`given the importance of proper pharmaceutical labeling. 387 U.S. 136 at 154. In rejecting
`
`this argument, the Supreme Court found that pre-enforcement review would actually speed
`
`up enforcement, as the regulation would either be fully upheld or struck down at once,
`
`despite recognizing that pharmaceutical labeling can have drastic negative effects on
`
`patient health. Id. Here, there is no similar, adverse public safety concern should the court
`
`act now; if anything, pre-enforcement review of the right of way or land transfer only affects
`
`the proposed crossing through the Refuge sought by the Utilities. As such, the government
`
`and Utilities have an even weaker argument for delay than in Abbott.
`
`If this were simply a case of a land transfer, the court may be more inclined to wait
`
`for Fish and Wildlife’s further review. Given the history of this litigation, however,
`
`common sense counsels in favor of proceeding. As previously noted, if the issuance of a
`
`right of way or land transfer is not reviewed at this stage, there is a strong possibility that
`
`the CHC line will be nearly completed in all areas except the Refuge despite its legality
`
`being in substantial question. Defendants tout the land transfer as the reason why
`
`reissuance of the right of way will not occur, but acknowledge that the contemplated land
`
`transfers are uncertain to shield a crossing through the Refuge from review.
`
`Defendants cannot use a possible land exchange as both sword and shield in this
`
`litigation, while the public interest and plaintiffs may suffer substantial hardship by further
`
`delaying judgment day. Even without questioning the governmental defendants’ or the
`
`Utilities’ motives, their proposed “wait and see” method of proceeding amounts to little
`
`more than an orchestrated trainwreck at some later point in this lawsuit. See City of Mesquite
`
`
`
`16
`
`
`
`Case: 3:21-cv-00306-wmc Document #: 149 Filed: 01/14/22 Page 17 of 45
`
`v. Aladdin’s Castle, Inc., 455 U.S. 283, 289 (“In this case the city’s repeal of the
`
`objectionable language would not preclude it from reenacting precisely the same provision
`
`if the District Court’s judgment were vacated.”) (citations omitted); Wis. Right to Life, Inc.
`
`v. Barland, 751 F.3d 804, 831 (7th Cir. 2017) (quoting Friend of the Earth, Inc. v. Laidlaw
`
`Envtl. Servs., Inc. 528 U.S. 167, 190) (“[A] case does not become moot merely because the
`
`defendants have stopped engaging in unlawful activity. ‘[A] defendant claiming that its
`
`voluntary compliance moots a case bears the formidable burden of showing that it is
`
`absolutely clear the allegedly wrongful behavior could not reasonably be expected to
`
`recur.’”). Given all of the above factors, therefore, the court finds the Compatibility
`
`Determination ripe for review.4
`
`II. Standing
`
`Defendants further contend that plaintiffs have no standing to bring this action. In
`
`order to establish standing, there are three requirements: “First, the plaintiff must have
`
`suffered an injury in fact . . . Second, there must be a causal connection between the injury
`
`and the conduct complained of . . . Third, it must be [redressable].” Lujan v. Defs. of
`
`Wildlife, 504 U.S. 555, 560–61 (1992) (internal citations omitted). Moreover, to
`
`
`4 Plaintiffs also seek to challenge the Corps’ NWP 12 permit, which defendants note is no longer
`operational and has been replaced by NWP 57, altho