throbber
FILED
`
`#152
`l/ 05; __
`GTE-5M COCHRAN-WILSON, CLERK
`BY’ngHng—D'C'
`
`IN THE CIRCUIT COURT OF UNION COUNTY, ARKANSAS
`CIVIL DIVISION
`
`GLOBAL INDUSTRIAL, INC. d/b/a
`GLOBAL TURNAROUND
`
`PLAINTIFF
`
`v.
`
`CASE NO. 70CV—16-76-6
`
`LEIDOS CONSTRUCTORS, L.L.C. et a].
`
`DEFENDANTS
`
`and
`
`EL DORADO AMMONIA, LLC
`
`EL DORADO CHEMICAL COMPANY; and
`
`LSB INDUSTRIES, INC.
`
`V.
`
`CROSS-CLAIMANTS
`COUNTER CROSS-DEFENDANTS
`
`LEIDOS CONSTRUCTORS, LLC;
`LEIDOS ENGINEERING, L.L.C.; and
`LEIDOS, INC.
`
`CROSS-DEFENDANTS
`COUNTER CROSS-CLAIMANTS
`
`Benham’s Reply in Support of its Motion for Leave to Change Party Name
`
`This should be a noncontroversial motion to change the case caption so that it accurately
`
`reflects the parties’ names and is consistent with the pleadings. See Ark. R. Civ. P. 10(a)
`
`(providing that the title of an action must include “the names of all the parties”). The name Leidos
`
`Constructors, LLC no longer exists and that company has not operated since April 2016, which is
`
`when The Haskell Company (“Haskell”) purchased Leidos Constructors, LLC and changed its
`
`name to Benham Constructors, LLC (“Benham” or “Benham Constructors”).
`
`It was Benham
`
`Constructors that in May 2016 completed the projects that form the basis of the present action.
`
`“Leidos Constructors, LLC” should therefore be replaced with “Benham Constructors, LLC” in
`
`the case caption and style.
`
`UNION COUNTY CIRCUIT CLERK DOCUMENT# CTX—OOOOOO185792 PAGE 1 OF 20
`
`1
`
`

`

`Plaintiffs LSB Industries, El Dorado Chemical Company, and El Dorado Ammonia, L.L.C.
`
`(collectively, “LSB”) have long recognized that Benham Constructors is the proper party. LSB’s
`
`original demand letter is based on alleged “material breaches by Benham Constructors, LLC,” and
`
`LSB’s amended cross-complaint, filed on August 8, 2018, provides on page 1 that LSB is asserting
`
`claims “against (1) Benham Constructors, L.L.C., formerly known as Leidos Constructors, L.L.C.,
`
`formerly known as SAIC Constructors, L.L.C.” LSB nevertheless objects to properly naming
`
`Benham Constructors in the case style and caption and argues that Benham’s motion is a tactic of
`
`delay and confusion. However, using the correct party names cannot possibly delay the trial, and
`
`Benham will not argue that it should. Moreover, referring to the parties by their proper names
`
`eliminates (rather than creates) confusion at trial: when Benham’s witnesses testify about their
`
`work for Benham Constructors, the jury will know which party those witnesses represent.
`
`The Court should grant Benham’s motion because (1) Benham Constructors is the correct
`
`party name, (2) forcing Benham to proceed under the wrong name will create confusion, and
`
`(3) granting this motion will not cause any delay.
`
`1.
`
`Leidos Constructors, LLC is now Benham Constructors, LLC
`
`There is no real dispute that Leidos Constructors is now Benham Constructors. LSB does
`
`not seriously contend otherwise; instead, LSB’s principal argument is apparently that Benham
`
`must prove this by affidavit. However, the Arkansas Rules of Civil Procedure do not impose this
`
`requirement—and,
`
`in any event, Benham has now mooted this argument by providing the
`
`superfluous affidavit. See Declaration of Michael B. Gwyn (“Gwyn Decl.”).
`
`Arkansas Rule of Civil Procedure 7(b)(2) provides that a motion “shall include a brief
`7
`supporting statement of the factual and legal basis for the motion.’ Benham did exactly that.
`
`Paragraphs 1-4 of Benham’s motion explain, among other things, that:
`
`o
`
`o
`
`Benham Constructors is the successor-in-interest to Leidos Constructors; and
`
`Leidos Constructors no longer exists.
`
`That is reason enough to grant the motion.
`
`UNION COUNTY CIRCUIT CLERK DOCUMENT# CTX—OOOOOO185792 PAGE 2 OF 20
`
`2
`
`

`

`LSB’s argument that Benham also was required to provide a sworn statement is wrong.
`
`LSB does not cite any authority from Arkansas for this point, and instead quotes out—of-context an
`
`unpublished Delaware Superior Court opinion construing Delaware Civil Rules 10 and 15(a) and
`
`certain Delaware statutes. See Delaware Dep’t of Transp. v. Mactec Eng ’g & Consulting, Inc,
`
`No. CIV.A. SllC0103l RES, 2011 WL 6400285, at *1 (Del. Super. Ct. Dec. 14, 2011). That
`
`Delaware case has nothing at all to do with Arkansas law or whether a party has the right to litigate
`
`under its proper name.1
`
`Regardless, Benham has now attached a sworn statement from Michael Gwyn, former
`
`President of Benham Constructors, LLC, and former President of Haskell’s Federal, Healthcare &
`
`Energy Group, to this reply. Mr. Gwyn’s sworn statement provides:
`
`0 On April 16, 2016, Haskell acquired Leidos Constructors, LLC. But Haskell did not
`purchase either Leidos Engineering, LLC or Leidos, Inc. Gwyn Decl. ll 3.
`
`o Haskell changed Leidos Constructors’ name to Benham Constructors, LLC, and Benham
`Constructors has used that name exclusively since April 2016. Id. W 4—5.
`
`0 Leidos Constructors, LLC no longer exists.
`
`Id. $1 6.
`
`o Benham Constructors is not affiliated with Leidos, Inc. or Leidos Engineering, LLC.
`117.
`
`Id.
`
`2.
`
`LSB’S apparent plan to confuse the jury by calling several different entities “Leidos”
`is not a reason to deny Benham’s motion
`
`Benham filed this motion in part to “aid the factfinder and the Court in distinguishing
`
`between the parties during Phase II of the litigation.” Mot.
`
`11 4. LSB argues that granting
`
`Benham’s motion and updating the caption to reflect Benham’s real name will “cause significant
`
`and unjustifiable confusion” for the jury. Opp. at l 1. The opposite is true. Nothing could confuse
`
`I LSB’S other cases are equally irrelevant. They stand for the uncontroversial proposition that
`evidence outweighs argument. In Stan v. Vences, for example, the court dismissed a claim for lack
`of subject-matter jurisdiction because the uncontroverted evidence demonstrated that the plaintiff
`was covered by worker’s compensation and this evidence outweighed contrary attorney argument.
`571 S.W.3d 24, 31 (2019), ren ’g denied (Mar. 6, 2019). Likewise, McCoy v. Robinson held that
`an attorney’s word could not substitute for the requirement to file a proof of service, see 550
`S.W.3d 33, 40 (2018), and Flentje v. First Nat. Bank of Wynne held that arguments of counsel are
`not evidence for purposes of summary judgment, see 11 S.W.3d 531, 539 (2000).
`
`"3
`
`UNION COUNTY CIRCUIT CLERK DOCUMENT# CTX—OOOOOO185792 PAGE 3 OF 20
`
`

`

`the jury more amid a sea of corporate names than having the wrong entity listed on the jury form
`
`and having LSB call Benham by the wrong name throughout trial.
`
`To sharpen the point, LSB spends seven pages of its opposition canvassing the trial record
`
`and discovery for every mention of Leidos, Leidos Engineering, Leidos Constructors, Benham,
`
`Haskell, or Merrick. See Opp. at 4-10. The fact that all of those names appear in the record
`
`underscores that the case style should reflect the correct names of the parties, rather than incorrect
`
`names. LSB’s expressed desire to try to confuse the jury by telling it that all of the defendants are
`
`one collective entity known as “Leidos” is not a reason to deny the motion, but
`
`instead a
`
`compelling reason to grant it so that the jury will not be confused. Nor does it undermine
`
`Benham’s right to be called by its correct name. See Ark. R. Civ. P. 10(a) (providing that the title
`
`of an action must include “the names of all the parties”).2
`
`3. Granting Benham’s motion will not cause delay
`
`Finally, LSB argues that Benham’s motion is a “transparent ploy to further delay the trial
`
`of this case.” Opp. at 12. That is pure fiction. Benham’s motion nowhere suggested (and Benham
`
`does not argue) that changing the case caption has any bearing on the trial date. Rather, this is a
`
`simple administrative request that the case caption reflect Benham’s accurate legal
`
`identity.
`
`Moreover, the Court will recall that this matter does not currently have a date scheduled for trial,
`
`as the Court struck the previous trial setting of September 21, 2020, due to the difficulties of
`
`conducting such a complicated trial in compliance with then-existing COVID-19 restrictions.
`
`While the parties await the sitting of a new Circuit Judge, and the scheduling of the trial of this
`
`matter by the new Judge in 2021, now is the most appropriate time to allow the administrative fix
`to the current case caption. By doing so, the Court will assist any new Judge by transferring the
`
`case with all the correct party names properly included in the case caption.
`
`2 LSB’s suggestion that Benham has refused to present a 30(b)(6) corporate representative witness
`on Topic 1 dealing with corporate structure, Opp at 10, is undermined by the evidence LSB cites,
`which shows that Benham has not objected to offering a witness on that topic See Opp. at 10, Ex
`S (listing the topics objected to by the defendants, beginning with Topic 2).
`
`4
`
`UNION COUNTY CIRCUIT CLERK DOCUMENT# CTX-OOOOOO185792 PAGE 4 OF 20
`
`

`

`Conclusion
`
`Benham respectfully requests that this Court amend the case style and caption to refer to
`
`Benham Constructors by its correct name.
`
`Respectfully submitted,
`
`SUSMAN GODFREY L.L.P
`
`/S/ M
`
`. She herd
`
`Matt ew .Shepherd
`LAW OFFICES SHEPHERD & SHEPHERD, PA.
`
`200 N. Jefferson, Suite 600
`
`El Dorado, AR 71730
`
`(870) 862-2087 Telephone
`(870) 862-2747 Facsimile
`mshepherd@shepfirm.com
`
`Neal S. Manne
`
`State Bar No.: 2017083
`
`Chanler A. Langham (Pending PHVAdmission)
`Adam Carlis (Pending PHVAdmission)
`1000 Louisiana St, Suite 5100
`
`Houston, Texas 77002
`
`(713) 651-9366 Telephone
`(713) 654-6666 Facsimile
`nmanne@susmang0dfrey.com
`c1angham@susmangodfrey.com
`acarlis@susmang0dfrey.com
`
`Drew D. Hansen (Pending PHVAdmiSSion)
`SUSMAN GODFREY L.L.P.
`
`1201 3rd Ave., Suite 3800
`
`‘
`
`Seattle, WA 98101
`
`(206) 516-3880 Telephone
`(206) 516-3883 Facsimile
`dhansen@susmang0dfrey.com
`
`Brittany Fowler (Pending PHI/Admission)
`SUSMAN GODFREY L.L.P.
`
`1900 Avenue ofthe Stars, Suite 1400
`
`Los Angeles, CA 90067-6029
`(310) 789—3 100 Telephone
`(310) 789-3150 Facsimile
`bfowler@susmangodfrey.com
`
`UNION COUNTY CIRCUIT CLERK DOCUMENT# CTX—OOOOOO185792 PAGE 5 OF 20
`
`5
`
`

`

`Patrick D. Wilson (99073)
`Jessica Pruitt Koehler (2015226)
`WRIGHT, LINDSEY & JENNINGS LLP
`
`200 West Capitol Avenue. Suite 2300
`Little Rock, AR 72201
`
`(501) 371—0808 Telephone
`(501) 376-9442 Facsimile
`
`ATTORNEYS FOR DEFENDANT
`
`BENHAM CONSTRUCTORS, LLC
`
`CERTIFICATE OF SERVICE
`
`I hereby certify that on November 5, 2020, I electronically served a true and correct copy
`of foregoing on the following counsel of record:
`
`David E. Jones
`Todd E. Kolczun
`LOGAN & LOWRY LLP
`102 East Third Street
`PO. Box 452469
`
`Grove, OK 74345—2469
`djones@loganlowry.com
`tkolczun@1oganlowry.com
`
`R. Jeffery Sawyer
`STONE & SAWYER PLLC
`
`315 East Main
`
`El Dorado, Arkansas 71730
`Counselfor Global Industrial, Inc.,
`d/b/a Global Turnaround
`
`James R. Leahy (pro hac vice)
`Stephen Edmundson (pro hac vice)
`Katie Tipper-McWhorter (pro hac vice)
`Aimee Housinger (pro hac vice)
`GREENBERG TRAURIG, LLP
`
`1000 Louisiana Street, Suite 1700
`Houston, Texas 77002
`leahyj@gtlaw.com
`tipperk@gtlaw.com
`housingera@gtlaw.com
`
`F. Mattison Thomas, III
`
`103 East Main, Suite D
`El Dorado, AR 71730
`matt@southarklegal.com
`
`Joseph R. Falasco
`QUATTLEBAUM, GROOMS & TULL PLLC
`
`111 Center Street, Suite 1900
`
`Little Rock, Arkansas 72201
`Jfalasco@qgtlaw.com
`Attorneys for El Dorado Ammonia, LLC
`El Dorado Chemical Company
`
`
`
`UNION COUNTY CIRCUIT CLERK DOCUMENT# CTX—OOOOOO185792 PAGE 6 OF 20
`
`

`

`IN THE CIRCUIT COURT OF UNION COUNTY, ARKANSAS
`CIVIL DIVISION
`
`GLOBAL INDUSTRIAL, INC. d/b/a
`GLOBAL TURNAROUND
`
`PLAINTIFF
`
`v.
`
`CASE NO. 70CV—16-76-6
`
`LEIDOS CONSTRUCTORS, LLC et al
`
`DEFENDANTS
`
`and
`
`EL DORADO AMMONIA, LLC
`
`EL DORADO CHEMICAL COMPANY; and
`LSB INDUSTRIES, INC.
`
`V.
`
`CROSS-CLAIMANTS
`COUNTER CROSS—DEFENDANTS
`
`LEIDOS CONSTRUCTORS, LLC;
`LEIDOS ENGINEERING, LLC; and
`LEIDOS, INC.
`
`CROSS-DEFENDANTS
`COUNTER CROSS-CLAIMANTS
`
`Declaration of Michael B. Gwvn inSUQQOi‘l‘ of Reply
`In Support of Motion for Leave toChangePartv Name
`
`1.
`
`My name is Michael B. Gwyn, and I am the tonner President of the Federal,
`
`Healthcare & Energy Group at The Haskell Company (“Haskell”), as well as the former President
`
`of Benham Constructors, LLC (“Benham”). Haskell is the sole Member of Benham Constructors,
`
`LLC. >
`
`2.
`
`I submit this declaration in support of the Benham’s Motion for Leave to Change
`
`Party Name.
`
`I have personal knowledge of the facts contained in this declaration.
`
`3.
`
`On April 16, 2016, Haskell acquired Leidos Constructors, LLC. Haskell did not
`
`acquire Leidos Engineering, LLC or Leidos, Inc.
`
`4.
`
`In connection with its purchase of Leidos Constructors, LLC, Haskell changed the
`
`name of Leidos Constructors, LLC from Leidos Constructors, LLC to Benham Constructors, LLC.
`
`5.
`
`Since April 2016, Benham Constructors, LLC has been known exclusively as
`
`Benham Constructors, LLC.
`
`UNION COUNTY CIRCUIT CLERK DOCUMENT# CTX-000000185792 PAGE 7 OF 20
`
`

`

`6.
`
`7.
`
`Leidos Constructors, LLC no longer exists.
`
`Benham Constructors, LLC is not affiliated with Leidos,
`
`Inc. or Leidos
`
`Engineering, LLC.
`
`8.
`
`In May 2016, Benham Constructors, LLC completed the projects which form the
`
`basis of the above-styled litigation.
`
`9.
`
`On April 11, 2017, counsel for El Dorado Ammonia, LLC sent a demand letter
`
`referencing “material breaches by Benham Constructors L.L.C.” Attached as Exhibit 1 is a true
`
`and correct copy of that letter.
`
`1, Michael B. Gwyn, solemnly affirm and declare under penalty of perjury, that the
`
`foregoing declaration is true and correct to the best of my personal knowledge, information, and
`
`belief.
`
`
`
`UNION COUNTY CIRCUIT CLERK DOCUMENT# CTX—OOOOOO185792 PAGE 8 OF 20
`
`

`

`Exhibit 1
`
`UNION COUNTY CIRCUIT CLERK DOCUMENT# CTX—OOOOOO185792 PAGE 9 OF 20
`
`

`

` EGreenbergTraurig
`
`James R. Leahy
`Tel 713.374.3534
`Fax 713.374.3505
`Ieahyj©gtlaw.com
`
`April 11. 2017
`
`Via cerli zed mail return recei r ret nested re ular mail and e-mail
`
`
`
`
`
`Mr. Michael Smith
`Vice President
`
`SAIC Constructors. L.L.C.
`9400 N. Broadway, Ste. 300
`Oklahoma City. OK 73114
`
`Mr. William J. Cople IlT
`Counsel for Leidos Constructors. L.L.C.
`
`Hollingsworth LLP
`1350 I Street, NW
`Washington, DC 20005
`wco1;1e@Iiolliugsworthllp.com
`
`Mr. Jeffrey W. Miller
`Associate Counsel, SAIC Constructors, L.L.C. and
`Registered Agent, Benlram Constructors, L.L.C.
`9400 N. Broadway, Ste. 300
`Oklahoma City, OK 73114
`Jeff. rrufler'ga2,berrlrarrr. com
`
`Mr. Richard M. Mitchell
`Executive Vice—President, Construction
`Benham Constructors, L.L.C.
`8845 Red Oak Boulevard
`Charlotte. NC 28217
`r‘ichardinitchelltthb enha 111.com
`
`Mr. James R. Moos
`SVP and Deputy Group President, Civil
`Leidos Engineering
`622 Emerson Rd Ste 600
`Saint Louis. Missouri 63141-6728
`
`Mr. Michael B. Gwyn
`President
`Leidos Constructors. L.L.C.
`9400 N. Broadway. Ste. 300
`Oklahoma City. OK 73114
`MICHAEL.B.GYWN@leidos.corn
`
`Leidos, Inc, f/k/a Science Applications
`International Corporation
`c/o The Corporation Trust Company.
`Registered Agent
`Corporation Trust Center
`. 1209 Orange Street
`Wilmington, DE 19801
`
`Re:
`
`Engineering, Procurement, and Construction Agreement between El Dorado
`Ammonia, L.L.C., and SAIC Constructors, L.L.C., and, Guaranty
`
`Dear Sirs:
`
`This firm has been retained to represent. El Dorado Ammonia, L.L.C., (“EDA”) in a legal
`matter regarding the material breaches by Benham Constructors L.L.C., formerly known as
`Leidos
`Constructors,
`L.L.C.,
`formerly
`known
`as
`SAIC
`Constructors,
`L.L.C.
`(“Benham/Leidos/SAIC”) of its Engineering, Procurement, and Construction Agreement
`(“Ammonia EPC Contract”), dated August 12, 2013, and its breaches of other legal duties owed
`to EDA.
`The subject matter of the Ammonia EPC Contract concerned the design and
`reconstruction of the 531—NH3 ammonia plant in El Dorado, Arkansas (“Project”). At all times
`relevant herein, Benham/Leidos/SAIC was the design engineer and general contractor engineer
`responsible for the timely completion of the Project. Contemporaneously with the execution of
`
`GREENBERG TRAURIG, LLP l ATTORNEYS AT LAW l WWW.GTLAW.COM
`1000 Louisiana Street, Suite 1700, Houston. Texas 77002 lTol 713.374.3500 l Fax 713.374.3505
`
`UNION COUNTY CIRCUIT CLERK DOCUMENT# CTX-000000185792 PAGE 10 OF 20
`
`

`

`April 11,2017
`PageZ
`
`the Ammonia EPC Contract, a Guaranty agreement was executed by Leidos, Inc, formerly
`known as Science Applications International Corporation (“Guarantor”) in favor of EDA in
`which the Guarantor unconditionally, absolutely, and irrevocably guaranteed to EDA the full and
`timely performance of Benham/Leidos/SAIC of the Ammonia EPC Contract as primary obligor,
`not merely as surety.
`
`Pursuant to Article 13 of the Ammonia EPC Contract, EDA engaged FTI Consulting
`(“FTI”) to audit the costs and management of the work by Benham/Leidos/SAIC. The audit has
`been completed, and its results are disturbing. Although the mismanagement and delays that
`repeatedly occurred during the course of the Project are well known to both parties,
`the
`quantification of the costs that have been incurred by EDA as a result of Benham/Leidos/SAIC’S
`poor engineering and mismanagement of the Project are
`significant and will
`require
`reimbursement by Benham/Leidos/SAIC. A copy of the audit report
`is attached hereto as
`Exhibit A.
`
`The Ammonia EPC Contract provided a fixed price for engineering and general
`conditions (Article 5.1), and the contractor, Benham/Leidos/SAIC, was to invoice variable
`construction costs at actual cost plus a 4.5% fee (Article 5.2). Under the terms and conditions of
`the Ammonia EPC Contract, Benham/Leidos/SAIC was contractually obligated to manage the
`Project in accordance with Article 2 ofthe contract, which required Benham/Leidos/SAIC inter
`alia to:
`
`0
`
`Perform the work as appropriate to complete the Project in accordance with the
`estimated contract price ($233,821,044);
`
`- Maintain a competent full time staff at the Project site;
`0
`Secure, monitor, and coordinate subcontractor activities;
`
`0
`0
`
`0
`
`0
`
`Provide all engineering in a timely manner;
`Provide, update, and maintain the Project schedule;
`
`the work for defects, and confirm that work
`inspect
`Provide quality control,
`complied with plans, specifications, and other requirements ofthe contract; and
`Provide accurate progress reports ofthe Project.
`
`Additionally, Benham/Leidos/SAIC was fully responsible for the adequate, conforming, and
`timely performance of the work by its subcontractors and fully responsible to EDA for all acts
`and omissions of its subcontractors (Article 8.3).
`
`1. Liquidated damages for delay
`
`As an additional consequence of Benham/Leidos/SAIC’S breaches of its contractual
`duties, mechanical completion of the Project was delayed for 273 calendar days. Discrete
`periods ofincremental delay have been identified as follows:
`
`0
`
`90 calendar days of delay to start of piping installation on November 17, 2014,
`was caused by Benham/Leidos/SAIC’S mismanagement of its subcontractor
`procurement process. Benham/Leidos/SAIC waited until July 25, 2014, to issue
`its invitation to bid, and took over a month after receipt of proposals to execute a
`
`GREENBERG TRAURIG,'LLP I: ATTORNEYS AT LAW I www.GTLAw.COM
`1000 Louisiana Street, Suite 1700, Houston, Texas 77002 ITel 713.374.3500 I Fax 713.374.3505
`
`UNION COUNTY CIRCUIT CLERK DOCUMENT# CTX—OOOOOO185792 PAGE 11 OF 20
`
`

`

`April 11,2017
`Page 3
`
`subcontract on October 17, 2014, with the selected piping subcontractor, Global
`Industrial, Inc. (“Global”), Critical piping activities, planned to begin on July I,
`2014,I did not actually start until November 17,2014.
`
`105 calendar days of delay to complete the piping installation for the Project was
`due
`to Benham/Leidos/SAIC’S mismanagement
`of
`the
`initial
`piping
`subcontractor, Global. During Global’s time on the Project, Benham/Leidos/SAIC
`did not consistently provide EDA with information concerning percent complete,
`physical progress, or other
`earned value metrics
`that
`tracked GIobaI’s
`productivity, even though Global was being paid on a time and materials basis.
`Notwithstanding such failures to manage Global’s productivity, cost, and
`schedule, Benham/Leidos/SAIC represented to EDA on May 30, 2015, that piping
`installation would be complete by September 26, 2015 — before terminating
`Global approximately one month later on July 1, 2015. After the replacement
`piping subcontractor, Performance Contractors,
`Inc. (“Performance”) assumed
`responsibility for the completion of the piping work for the Project, the revised
`schedule projected that piping installation would not be complete until January
`28, 2016.
`
`78 calendar days of additional delay due to impacts on Performance’s work
`caused by Benham/Leidos/SAIC, specifically:
`
`0
`
`0 Engineering revisions — Piping engineering was far from complete at the
`start of piping installation, and Benham/Leidos/SAIC continued to
`sporadically issue piping isometrics and revisions well into 2016;
`Existing isometric errors;
`0 Global—related backcharges — Rework of defective piping installed by
`Global was belatedly discovered by Benham/Leidos/SAIC and required
`correction;
`
`o
`
`other
`by
`Interference
`Benham/Leidos/SAIC —
`
`subcontractors
`Performance
`
`not
`and
`
`by
`properly managed
`other
`subcontractors
`
`experienced inefficiencies due to acceleration and overcrowding and
`congestion of work areas in the later stages of Project work.
`
`As set
`
`forth above, Benham/Leidos/SAIC was responsible for 273 days of inexcusable
`delay in completing the Project. Amendment No.
`1
`to the Ammonia EPC Contract granted
`Benham/Leidos/SAIC an additional 131 calendar days to achieve mechanical completion of the
`Project, but included an important reservation of rights:
`
`Nothing in this Amendment shall act as a release, settlement, waiver, or otherwise
`limit or reduce the Parties’
`rights, obligations, or responsibilities under the
`Contracts including in relation to the Work performed to date, delays, and the
`Parties’
`responsibility for
`same.
`In all other
`respects,
`the terms of the
`Amendment or Contracts shall remain in full force and effect and unchanged.
`
`1 Delay of 49
`calendar days caused by delay in issuance of air permit has not been not charged to
`Benham/Leidos/SAIC.
`
`GREENBERG TRAURIG,
`1000 Louisiana Street,
`
`LLP I ATTORNEYS AT LAW I WWW,GTLAW.COM
`Suite 1700, Houston, Texas 77002 ITet 713.374.3500 I Fax 713.374.3505
`
`UNION COUNTY CIRCUIT CLERK DOCUMENT# CTX—OOOOOO185792 PAGE 12 OF 20
`
`

`

`April 11, 2017
`Page4
`
`Accordingly, EDA is entitled to recover for delays that occurred prior to the execution of the
`Amendment No. 1 on October 20, 2015, which amount to 142 calendar days (273 calendar days
`minus 131 days).
`
`Article 4.3 of the Ammonia EPC Contract provides for liquidated damages of $5,000 per
`day for each full day of delay if mechanical completion was not achieved by the agreed
`completion date due to Benham/Leidos/SAIC’S failure to prosecute the work with diligence
`and/or its negligence or the negligence of its subcontractors. Liquidated damages in the amount
`of $710,000 would be owed to EDA for 142 calendar days of delay, but for the limit set by
`Article 4.3, which reduces the liquidated damages owed by Benham/Leidos/SAIC to $500,000.
`
`2. Other costs proximately caused by Benliam/Leidos/SAIC’S breach of contractual
`duties, negligence, gross negligence, and/or fraud
`
`in some cases,
`As a result of Benham/Leidos/SAIC’S negligence, gross negligence, and,
`actionable fraud, EDA sustained additional costs and damages in the amounts set forth below:
`
`(1. Costs incurred in overpayment to Global due to Ben/mm/Leidos/SAIC’S
`mismanagement of engineering, material, and subcontractor
`
`As set forth above, not only did Benham/Leidos/SAIC have a contractual obligation
`under Article 2 of the Ammonia EPC Contract
`to supervise, manage, and inspect work
`performed by subcontractor Global
`for compliance with plans and specifications, but
`Benham/Leidos/SAIC agreed to assume full responsibility for the negligent acts and omissions
`of Global under Article 8. Global’s defective work and negligence caused EDA to incur
`excessive costs currently calculated in the amount of $3,886,290, which represents Global’s
`overbilling of overtime in the amount of$l,774,763 (including Benham/Leidos/SAIC’S 4.5% fee
`to be reimbursed) and Global’s inefficiencies associated with its overtime hours in the amount of
`82,1 1 1,527 (including Benham/Leidos/SAIC’S 4.5% fee to be reimbursed).
`
`Due to the initial delays in the piping installation work, on March 3, 2015, Global was
`allowed to amend its work schedule to six days per week and 12 hours per day. EDA agreed to
`this change on the basis of representations made by Benham/Leidos/SAIC’S project manager that
`Global’s
`revised work schedule was
`not
`expected
`to
`have
`any
`cost
`implications.
`Benham/Leidos/SAIC was required to manage Global to ensure that Global did not abuse the
`new work schedule by charging excessive overtime hours with little or no productivity resulting
`from the extra hours.
`Instead, Benham/Leidos/SAIC allowed Global to use the revised work
`schedule as a blank check to be written on EDA’s account.
`
`EDA reasonably expected the revised work schedule would allow critical piping
`activities to accelerate and advance the Project schedule; instead, after Global’s overtime charges
`were approved in March 2015, the mechanical completion date continued to slip even further
`behind schedule. Benham/Leidos/SAIC’S monthly report for April 2015 showed that
`the
`mechanical completion date had slipped from July 28, 2015, to August 25, 2015, and the piping
`completion had slipped from June 29, 2015,
`to August 27, 2015 (a delay of two additional
`months). Global’s poor performance and inefficiencies were attributable — and allowed to
`
`GREENBERG TRAURIG, LLP I ATTORNEYS AT LAW I www.cTLAWLOM
`1000 Louisiana Street, Suite 1700, Houston, Texas 77002 ITel 713.3743500 I Fax 713.374.3505
`
`UNION COUNTY CIRCUIT CLERK DOCUMENT# CTX—OOOOOO‘185792 PAGE 13 OF 20
`
`

`

`April 11,2017
`Page 5
`
`for months — due
`continue
`Benham/Leidos/SAIC.
`
`to
`
`negligent management
`
`and
`
`lack of oversight
`
`by
`
`Global billed for 72,062 overtime hours between March 1, 2015, and its termination date
`of July 2, 2015. Global’s subcontract with Leidos defined overtime as all hours in excess of 40
`hours Monday through Friday, as well as all hours on Saturdays, Sundays, and company
`observed holidays.
`The inefficiency of Global’s overtime work became evident with the
`schedule slippages set forth above, but FTI used a 201]
`industry study, Change Orders,
`Productivity, Overtime: A Primer for the Construction Industry,
`issued by the Mechanical
`Contractors Association of America (“MCAA”) to determine the loss of productivity due to
`Global’s excessive overtime hours.
`‘
`
`MCAA methodology measures the decrease in productivity of an employee with each
`consecutive week of scheduled overtime. Applying the MCAA methodology, Global worked
`5,567 inefficient manhours between March 1, 2015, and April 22, 2015, and another 20,472
`inefficient hours between April 22, 2015, and July 2, 2015, due to the excessive and ineffective
`overtime scheduled by Benham/Leidos/SAIC. The inefficient hours were multiplied by the
`applicable blended rate of straight time rate and overtime being charged at the time, which shows
`resulting costs incurred in the amount of $2,020,600. When Benham/Leidos/SAIC’S 4.5% fee
`($90,927) is added to Global’s excessive overtime costs,
`the cost of Benham/Leidos/SAIC
`allowing excessive and inefficient overtime to be invoiced by Global amounts to $2,111,527.
`
`b.
`
`Additional costs due to negligent materials management and supervision
`
`Benham/Leidos/SAIC is also responsible for other costs attributable to its negligent
`materials management and supervision.
`The parties’ agreed Project schedule (Exhibit E to
`Ammonia EPC Contract)
`required Benham/Leidos/SAIC to complete design work and
`engineering prior to the start of piping installation. Not only was the engineering incomplete
`when Benham/Leidos/SAIC directed Global to start piping installation in November 2014, but
`only a small percentage of the piping isometric drawings were completed.
`in fact, 90% of the
`piping isometrics had still not been issued by February 2015.
`
`Benham/Leidos/SAIC was also responsible for the management of materials needed for
`the Project. Article 2.1.6 of the Ammonia EPC Project provided that Benham/Leidos/SAIC was
`required to perform all necessary preparation for laydown areas, storage areas, or areas needed
`for access of materials and equipment. While Global performed work on the Project, materials
`were spread across six different laydown yards, which made it difficult and time consuming to
`identify required materials and deliver proper materials for installation.2 Benham/Leidos/SAIC
`was either directly responsible or inexcusably negligent in tolerating such obvious inefficiencies
`in material handling at the Project site.
`
`These failures on the part of Benham/Leidos/SAIC directly impacted the productivity of
`its subcontractor, Global. To calculate these specific inefficiencies, EDA again utilized the 2011
`MCAA industry study, which provides a method of quantifying inefficient hours using factors
`based on industry research. According to the MCAA methodology, mismanagement of materials
`
`2 One ofthe first actions taken by the replacement piping subcontractor, Performance, was to move all materials to a
`single laydown yard to increase efficiency.
`
`GREENBERG TRAURIG, LLP I ATTORNEYS AT LAW I WWW.GTLAW.COM
`1000 Louisiana Street, Suite 1700, Houston, Texas 77002 ITel 713.374.3500 l Fax 713.374.3505
`
`UNION COUNTY CIRCUIT CLERK DOCUMENT# CTX—OOOOOO185792 PAGE 14 OF 20
`
`

`

`April 11,2017
`Page 6
`
`(as occurred at the Project site) is considered a logistics factor, which has been determined to
`have a relatively minor impact (although quite significant in the context of this Project) of 10%.
`Similarly, according to MCAA methodology, negligent supervision has also been determined to
`have a relatively minor (but significant) impact of 10%.
`
`After adjustment for overtime inefficiencies (see above), Global’s remaining man hours
`amounted to 232,321 man hours. When the MCAA methodology is applied to include both
`mismanagement of materials
`and negligent
`supervision of a
`subcontractor
`(20%),
`a
`determination can be made that at least 38,720 man hours billed by GlObal were wasted time.
`Applying Global’s average hourly rate to the hours of productive work lost due to
`Benham/Leidos/SAIC’S mismanagement and negligence, the costs incurred by EDA amount to
`$2,885,717. When Benham/LeidOS/SAIC’S 4.5% fee ($129,857) is added to this amount, the
`excessive costs due to negligent management of materials and negligent supervision amount to
`$3,015,574.
`
`c.
`
`Costs to It ire another engineering firm to perform scheduling work
`
`EDA also incurred additional costs when forced to transfer the scheduling responsibilities
`for the Project from Benham/Leidos/SAIC to another engineering firm, Hatch, Ltd. (“Hatch”).
`The Ammonia EPC Contract required Benham/Leidos/SAIC to provide sufficient management
`of the wOrk to achieve Project completion in accordance with the estimated contract price and
`the
`agreed Project
`schedule.
`By May 2015, when
`it had become obvious
`that
`Benham/Leidos/SAIC had failed to manage and adequately supervise its subcontractor, Global,
`and had repeatedly caused the Project schedule to slip, EDA had no alternative but to transfer the
`scheduling responsibility for the Project to Hatch pursuant to Article 16 of the Ammonia EPC
`Contract.
`'
`
`to retain the services of a replacement engineering firm to take over
`EDA’S cost
`scheduling responsibilities for the Project amounted to $1,868,431. These were duplicative costs
`incurred by EDA, as such services were part of Benham/Leidos/SAIC’S scope ofwork under the
`Ammonia EPC Contract. Accordingly, EDA is entitled to recover such additional costs from
`Benham/Leidos/SAIC.
`
`(I.
`
`Transition costs fol/0 wing Global ’5 termination
`
`The effective date of Global’s termination was July 2, 2015, which left the Project site
`without a piping subcontractor for approximately one month. During that period oftime, EDA
`incurred additional costs and sustained further delay to the Project as transitional tasks had to be
`performed before a replacement subcontractor was hired to complete the piping work (and to
`remedy defective piping work performed by Global). These transitional tasks included inter alia
`identification the scope of work remaining to be completed, developing a more effective
`management of the materials on site, determining staffing needed to complete the work, and to
`calculate costs to complete the work.
`
`2015,
`
`The transition costs incurred during the period from July 12, 2015, through August 2,
`amounted to $2,229,842.3
`Such
`costs would
`not
`have
`been
`incurred
`had
`
`3 A portion of such costs invoiced by Performance appear to include work invoiced to the OSBL pro

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket