DOCKET NO.: HHD-CV-23-6165724-S
`
`SUPERIOR COURT
`
`SHAFFER BEACON MECHANICAL LLC
`
`VS.
`
`SRK MANAGEMENTLLC ET AL
`
`JUDICIAL DISTRICT OF
`HARTFORD
`
`AT HARTFORD
`
`APRIL 10, 2024
`
`SECOND AMENDED COMPLAINT
`
`FIRST COUNT; ( as to SRK Management LLC)
`
`1.
`
`On or about October 18, 2021, the plaintiff, Shaffer Beacon
`
`Mechanical LLC, and the defendant, SRK Management LLC duly authorized by
`
`Castle Ventures, LLC d/b/a Castle Apartments, entered into an agreement whereby
`
`the plaintiff agreed to provide the defendant, SRK Management LLC, with new
`
`efficiency boilers, gas piping for a new boiler, services and laborfor apartment
`
`buildings located in Waterbury, Connecticut and Plainville, Connecticut at the
`
`defendant's request. A copy of the agreementis attached hereto as Exhibit A.
`
`2.
`
`The plaintiff performedofall of its obligations to the defendant, SRK
`
`Management, LLC, in connection with said agreement.
`
`3:
`
`The defendant, SRK Management LLC, has defaulted in that it has
`
`failed to pay the plaintiff for said efficiency boilers, services and labor and the
`
`plaintiff is exercising its right to declare the entire balance due and owing.
`
`

`

`4,
`
`There is presently due and owing from the defendant, SRK
`
`ManagementLLC, to the plaintiff the sum of $19,588.99 [$7,092.89 principal plus
`
`finance charges in the amount of $12,496.10], accruing finance charges andall
`
`
`
`
`
`CtsofCollectionincludingreasonableattorneyfees.
`
`
`
`
`
`5.
`
`Demand has been madebut the defendant, SRK Management LLC,
`
`has refused and/or neglected to payplaintiff said sum.
`
`(as to Middlebury-Piping Ventures LLC and Middlebury-
`SECOND COUNT:
`Piping Ventures II LLC)
`
`1.
`
`On or before March 11, 2022, the defendants, Middlebury-Piping
`
`Ventures LLC and Middlebury-Piping Ventures II LLC, through its agent, the
`
`defendant, SRK ManagementLLC, entered into an agreementfor gas piping for a
`
`new motor along with materials, services and labor for apartment buildings known
`
`as Piping Rock Apartments, 1579 Hamilton Avenue, Waterbury, Connecticut at the
`
`defendant’s request.
`
`Zz
`
`The defendants, Middlebury-Piping Ventures LLC and Middlebury-
`
`Piping Ventures II LLC, are the record owners of the premises.
`
`Se
`
`The plaintiff performedof all of its obligations to the defendant, SRK
`
`Management LLC,
`
`in connection with said agreement.
`
`

`

`4.
`
`The defendant, SRK Management LLC, has defaulted in that they
`
`havefailed to pay the plaintiff for gas piping for a new motor along with materials,
`
`services and labor.
`
`5.
`
`There
`
`i
`
`l
`
`=
`
`Piping Ventures LLC and Middlebury-Piping VenturesI| LLC, to theplaintiff the sum
`
`of $9,566.58 [$7,092.89 principal plus interest in the amount of $2,473.69
`
`at the statutory rate of 10 percent per annum in accordance with C.G.S.
`
`37-3a. See Exhibit B attached hereto].
`
`_( Unjust Enrichmentas to Middlebury-Piping Ventures LLC
`THIRD COUNT:
`and Middlebury-Piping VenturesIi LLC)
`
`qs
`
`On or before March 11, 2022, the plaintiff, Shaffer Beacon
`
`Mechanical LLC, and the defendant, SRK Management LLC, entered into an
`
`agreement wherebytheplaintiff agreed to provide the defendant, SRK Management
`
`LLC, with gas piping for a new motor along with materials, services and labor for
`
`apartment buildings known as Piping Rock Apartments, 1579 Hamilton Avenue,
`
`Waterbury, Connecticut at the defendant's request.
`
`oe
`
`The defendants, Middlebury-Piping Ventures LLC and Middlebury-
`
`Piping Ventures Il LLC, are the record owners of the premises.
`
`

`

`&
`
`The plaintiff performed of all of its obligations to the defendant, SRK
`
`ManagementLLC, in connection with said agreement.
`
`4.
`
`The defendant, SRK Management LLC, has defaulted in that they
`
`
`
`savefailedtopaytheplaintiffforsaidgaspipingforanewmotoralongwith
`
`
`
`
`
`materials, services and labor.
`
`5.
`
`The defendants, Middlebury-Piping Ventures LLC and Middlebury-
`
`Piping Ventures Il LLC have been unjustly enriched thereby, to plaintiffs detriment.
`
`6.
`
`There is presently due and owing from the defendants, Middlebury-
`
`Piping Ventures LLC and Middlebury-Piping VenturesII LLC, to theplaintiff the sum
`
`of $9,566.58 [$7,092.89 principal plus interest in the amount of $2,473.69 at the
`
`statutory rate of 10 percent per annum in accordance with C.G.S. 37-3a].
`
`FOURTH COUNT:
`
`( as to Castle Ventures LLC)
`
`1.
`
`On or about October 13, 2021, the defendant, Castle Ventures LLC,
`
`entered into an agreement, through its agent, the defendant, SRK Management
`
`LLC, for new efficiency gas boilers along with materials, services and labor for
`
`apartmentbuildings known as Castle Apartments, 100 Norton Park Road, Plainville,
`
`Connecticut. A copy of the agreementis attached hereto as Exhibit A.
`
`2
`
`The defendant, Castle Ventures, LLC, is the record owner of the
`
`premises.
`
`

`

`3.
`
`The plaintiff performedofall of its obligations to the defendant, SRK
`
`Management LLC, in connection with said agreement.
`
`4.
`
`The defendant, SRK Management LLC, has defaulted in that they
`
`failed
`
`he
`
`plaintiff f
`
`ici
`
`boil
`
`;
`
`materials, services and labor.
`
`5
`
`There is presently due and owing from the defendant, Castle
`
`Ventures, LLC, to the plaintiff the sum of $7,593.31 finance charges andall costs of
`
`collection, including reasonable attorney fees.
`
`FIFTH COUNT: (Unjust enrichmentas to Castle Ventures LLC)
`
`Ts
`
`On or about October 13, 2021, the defendant, Castle Ventures LLC,
`
`entered into an agreement, through its agent, the defendant, SRK Management
`
`LLC, for new efficiency gas boilers along with materials, services and laborfor
`
`apartmentbuildings knownas Castle Apartments, 100 Norton Park Road, Plainville,
`
`Connecticut. A copy of the agreementis attached hereto as Exhibit A.
`
`2
`
`The defendant, Castle Ventures, LLC, is the record owner of the
`
`premises.
`
`a
`
`The plaintiff performedofall ofits obligations to the defendant, SRK
`
`Management LLC, in connection with said agreement.
`
`

`

`4.
`
`The defendant, SRK ManagementLLC, has defaultedin that they
`
`havefailed to paythe plaintiff for said new efficiency gas boilers along with
`
`materials, services and labor.
`
`5.
`
`The defendant, Castle Ventures, LLC, has been unjustly enriched
`
`thereby,to plaintiffs detriment
`
`6.
`
`There is presently due and owing from the defendant, Castle
`
`Ventures, LLC, to theplaintiff the sum of $7,593.31 finance charges andall costs of
`
`collection.
`
`PLAINTIFF,
`
`By:
`Eric Hard, Esq.
`Cohen, Burns, Hard & Paul
`81 South Main Street
`West Hartford, CT 06107
`Tel:
`(860) 561-1036; Fax: (860) 247-2126
`JURIS NO. 402625
`Its Attorneys
`Email: ehard@cbhplaw.com
`
`

`

`WHEREFORE, PLAINTIFF CLAIMS.
`
`io"=
`
`Money damages;
`
`Attorney fees;
`
`Interest at the statutory rate of 10 percent pursuant to C.G.S. 37-3a
`
`Such otherrelief as the court deems just.
`
`PLAINTIFF,
`SHAFFER BEACON MECHANICAL LLC
`
`Aterr
`Eric Hard, Esq.
`Cohen, Burns, Hard & Paul
`81 South Main Street
`West Hartford, CT 06107
`Tel:
`(860) 561-1036
`Fax: (860) 247-2126
`JURIS NO. 402625
`Its Attorneys
`
`

`

`CERTIFICATION
`
`| certify that a copy of this document wasor will immediately be mailed or
`
`andself-represented parties of record and that written consent for electronic
`
`delivery was received from all counsel and self-represented parties of record who
`
`were or will immediately be electronically served. Name and address of each
`
`party and attorney that copy wasor will immediately be mailed or delivered to:
`
`COUNSEL FOR THE DEFENDANT:
`SRK MANAGEMENTLLC
`
`Slavin, Stauffacher & Scott LLC
`P.O. Box 9
`Watertown, CT 06795
`Email: dbraunstein@sssattorneys.com
`
`PLAINTIFF,
`
`By:
`Esq.
`Eric Hard,
`Cohen, Burns, Hard & Paul
`81 South Main Street
`West Hartford, CT 06107
`Tel:
`(860) 561-1036; Fax: (860) 247-2126
`JURIS NO. 402625
`Its Attorneys
`
`

`

`EXHIBIT A
`
`

`

`
`
`1
`
`|| |
`
`EVERSSURCE
`
`October 13, 2021
`
`Ms, Rebecca Ruiz
`
`Property Manager
`
`279 Oakville Ave.
`Waterbury, CT 06708
`
`LETTER OF ADDENDUM
`
`Reference:
`
`Dear Ms. Ruiz,
`
`Castle Ventures (100 Norton Park) — Letter ofAddendumNo. 1
`
`This is Addendum number | to the Letter ofAgreement dated April 21, 2021 between Castle Ventures, LLC and
`iversource Inergy. We have reviewed the Beacon Mechanical Services proposalfor additional measuresat this site, and
`new Central Boilers and ECM Pumps have qualified for programincentives. These (2) new measures have generated
`$18,546.63 in direct program incentives, and the bonus comprehensive incentive has increased to $15,281.63 fora total of
`$33,828.26 that potentially could be available for the original LOAiterns,ifthese measures are installed exactly as stated
`inside the Exhibit A documents,
`
`The overall total Multifamily program incentive for all measures in this property (including the original LOA Direct Install |
`Weatherization, Insulation, Dwelling Unit and Common and Exterior LED Lighting.) h1aincreasedfromthe original
`$75,403.54 LOA combined incentive value to $77,887.00. The LOA expiration date has been extended to January 30, 202
`The Addendum incentives for measure 7 and 8, plus the Comprehensive Incentive will be paid to Castle Ventures, LLC
`uponverification ofthe installation ofall energy savings measures, If you are in agreement withthis Addendum,please
`acknowledge by signing and dating this agreement below and returning to us within 30 days to execute,
`Sincerely,
`
`
`
`reenterperenneelaEU
`
`|
`
`
`
`Cat 2. Watts
`
`Carl R. Watts
`Eversource Energy
`PO Box 270
`Hartford, CT 06141-0270
`
`EA Boe—
`
`Signature ofEverSource Official
`Enoch Lenge
`.
`-
`
`Name (Print)
`
`om
`
`Supervisor — Energy Efficiency.
`Title of Eversource Official
`
`10/13/21
`
`Date
`
`a|"7
`
`}
`
`cr
`
`1G
`
`ta
`
`4
`
`_
`
`Sighature ofthe Participant Official \
`es
`a
`-
`seoceitg. RDeeVir Ake
`Name (Print)
`> MA
`TilicofParticipantOfficial
`Loe (a
`Toe tsar tnasnncapo is
`
`

`

` MECHANICAL SERVICE. 1c.
`
`BEACON
`
`PO BOX 868 - GRANBY, CT 06035
`TEL 860-844-0111 / FAX 860-653-4767
`
`CT Lic # S1-0397089, P1-203890, HOD-0000787, MA Lic # 062090
`
`www, BeaconMechanical.com
`
`STPULTERIORTTTSeaymy
`
`
`
`
`
`October 18, 2021
`
`Castle Apartments
`100 Norton Park Rd.
`Plainville, CT 06062
` ev
`Dear Rebecca,
`
`QT # 2021-1 0-06-11
`
`Building 1 Boiler Replacement
`
`Bidg.# 1: We shall drain, disconnect, remove and properly dispose ofthe existing three (3) gas boilers. Wewill then
`furnish labor and materials required to install, three (3) new Lochinvar Energy Knight condensing gas boiler, model
`KHB285N. Eachboiler has a heating capacity of 264,000 BTU/h whenfired on natural gas with an operating efficiency
`of 95%. The Energy Knight features direct spark ignition, modulating burner with a 10:1 turndown, an ASME stainless
`steel heat exchangerfor durability and longlife, and an ECM variable speed primary circulator. The boiler includes the
`SMART SYSTEM™ which is an advanced integrated boiler contro! offering outdoor reset, night setback, domestic hot
`waterpriority, and additional features designed to maximize the potential energy savings. The boilers will be connected
`togetherin a lead / lag system to maximize energy efficiency and to accommodate the various heating and hot water
`demandsof the building. This new system will be piped as a primary secondary system with a new Grundfos Magna3
`circulator for the building loop. This boiler is a high efficiency modulating unit and will be directly vented through the
`side wall of the building utilizing PVC with combustion air ducted directly into the bailer by the same method. The
`|
`domestic hot water will be generaled by the existing indirect water heater. As part of the installation, we will replace the
`existing domestic circulation pump with a new Grundfos ECM pump
`i
`High Efficiency Equipment:
`i
`-
`Lochinvar KHB285N Gas-Fired Boilers (x3)
`-
`Grundfos Magna3 40-120F ECM Circulators (x1)
`-
`Grundfos Alpha 26-99 ECM Circulators (x1)
`
`Included in the price is labor to completely install these new boilers, supply andreturn piping. Also includes: circulator
`pumps, ball valves, purge station, low water cut-offs, automatic water feeders, anti-backflow preventers, coppertubing,
`copperfittings, black pipe, blackfittings, gas piping, PVC pipe, condensate pumps, acid neutralizers, vinyl tubing,
`|
`miscellaneous installation materials, and contro! wiring. Our price includes start-up, permit and one (1) year warranty
`on Beacon Mechanical installed components.
`x
`a $ 41,056.34 + $ 2,607.08 CTTax = § 43,663.42 Total93 S2G,. DL
`‘Rebates / incentives will be determined by an LOA from the utility company following their review,
`% Gb ast ;
`Beacon Mechanical Service, LLC is a licensed and fully insured company. BMSis also a Better Business
`ley
`i =
`Bureau Accredited Business.
`
`This Quotation is valid for 30 days.
`
`Terms:

`2
`*
`
`2
`
`j
`LOA will be assigned to BMS
`Payment terms on owner portion of contract will be paid by equal payments for 6 months with 2%interest on remaining
`balance per monthafter thirty days
`Delivery: 2-6 weeks from receiptof signed order and deposit (based on unit availability from factory/distributor), BMS lis
`not responsible for extended delays due to equipment shortages from manufacturer's & distributors. This also
`depends on COVID-19 guidelines as outlined by the Slate & Federal Government
`|
`Finance charges of 1.5% per month / annual Rate of 185 on all amounts past due and we will add ali costs of collection
`including a reasonable attorney'sfee.
`;
`
`

`

`PO BOX 868 - GRANBY, CT 06035
`TEL 860-844-0111 / FAX 860-653-4767
`CT Lic # $1-0397099, P1-203890, HOD-0000787, MA Lic # 062090
`
`www.BeaconMechanical.com
`
`QT # 2021-10-06-11
`
`se
`~—
`
`
`BEACON
`
`MECHANIEAL SERVICE, uc,
`CySTEPGiil(Perocolau [stentsealuisdinirene)aay
`
`
`
`October 18, 2021
`
`Castle Apartments
`100 Norton Park Rd.
`Plainville
`CT 08062
`Rev 4
`Dear Rebecca,
`
`Building 1 Boiler Replacement
`
`Bidg.# 1; We shall drain, disconnect, remove and properly dispose of the existing three (3) gas boilers. We will then
`furnish labor and materials required to install, three (3) new Lochinvar Energy Knight condensing gas boiler, model
`KHB285N, Eachboiler has a heating capacity of 264,000 BTU/h when fired on natural gas with an operating efficiency
`of 95%. The Energy Knight features direct spark ignition, modulating burner with a 10:1 turndown, an ASME stainless
`steel heat exchangerfor durability and long life, and an ECM variable speed primary circulator. The boiler includes the
`SMART SYSTEM™which is an advanced integrated boiler contro! offering outdoor reset, night setback, domestic hot
`water priority, and additional features designed to maximize the potential energy savings. The boilers will be connected
`together in a lead / lag system to maximize energy efficiency and to accommodate the various healing and hot water
`demands of the building. This new system will be piped as a primary secondary system with a new Grundfos Magna3
`circulator for the building loop. This boiler is a high efficiency modulating unit and will be directly vented through the
`side wall of the building utilizing PVC with combustion air ducted directly into the boiler by the same method. The
`domestic hot water will be generated by the existing indirect water heater. As part of the Installation, we will replace the
`existing domestic circulation pump with a new Grundfos ECM pump.
`
`High Efficiency Equipment:
`-
`Lochinvar KHB285N Gas-Fired Boilers (x3)
`-
`Grundfos Magna3 40-120F ECM Circulators (x1)
`-
`Grundfos Alpha 26-99 ECM Circulators (x1)
`
`Included in the price is labor to completely install these new boilers, supply and return piping. Also includes; circulator
`pumps, ball valves, purge station, low water cut-offs, automatic water feeders, anti-backflow preventers, copper tubing,
`copperfittings, black pipe, blackfittings, gas piping, PVC pipe, condensate pumps, acid neutralizers, vinyl tubing,
`miscellaneous installation materials, and control wiring. Our price includes start-up, permit and one (1) year warranty
`on Beacon Mechanicalinstalled components.
`
`PHCO. wevsccrrvsieeveavnesas $ 41,056.34 + £ 2,607.08 CT Tax = $ 43,663.42" Total
`
`‘Rebates / incentives will be determined by an LOA from the utility company following their review.
`
`Beacon Mechanical Service, LLC is a licensed and fully insured company. BMS is aiso a Better Business Le|
`F
`I
`ACCREDITED:
`Bureau Accredited Business.
`| ok erie
`AL
`BBB.
`This Quotation is valid for 30 days.
`
`Terms:
`
`@
`e
`

`
`a
`
`LOA will be assigned to BMS
`Payment terms on ownerportion of contract will be paid by equal payments for 6 months with 2%interest on remaining
`balance per month after thirty days
`Delivery: 2-6 weeks from receipt of signed order and deposit (based onunit availability from factory/distributor). BMSis
`not responsible for extended defays due to equipment shortages from manufacturer's & distributors. This also
`depends on COVID-19 guidelines as outlined by the State & Federal Government
`Finance charges of 7.5%per month / annual Rate of 18%on all amounts past due and we will add all costs of collection
`including a reasenabie attorney's fee,
`
`

`

`e
`
`a
`

`a
`
`BMSis not responsible for any tax liability that may be impased on the customer as a result of any payments from rebate
`incentives.
`BMS one (1) year warranty is on labor and materials as stated in equipment manufacturer's warranty and begins on
`completion of installation.
`Warranties are not in effect until job is paid in full. Warranties are not prorated,
`Customer needs to call for a final inspection with the Building Department following completion of the jab. Final payment
`is NOTrelated to inspection. BMS will address any issues (if needed) related to the installation following inspection,
`
`
`
`Nick Riggott
`
`Please sign and return one (1) copy of this entire proposal,
`
`| have read and accept the terms and conditionslisted above and select the following:
`
`Total: pate:MEK
`
`Accepted By:
`
`(Signature)
`
`
`
`
`
`(Print Name)
`
`You the buyer may cancel tis wansactionat any timeprior ta midnight oa thethird business dayafterthe date ofthix wansaction, See the attached notice of
`cancellation for an explanation ofthis right
`
`

`

`Statement
`
`Date: 1/18/2024
`
`[exo
`
`Shaffer Beacon
`MECHANICAL
`
`ib PLUMBING +» ON
`Quality & integrity Since 4890
`12 Mechanicsville Road
`P.O. Box 868
`Granby, CT 06035
`(860) 653-4767 (fax)
`(860) 844-0111
`Lic. #. S1-0393852, P1-0289777, HOD-000128
`
`Account: SRK Management
`
`POBEBFrm
`Waterbury, CT 06704
`
`Customer/invoice
`
`Date
`
`Description
`
`Invoice Amount
`
`Payments
`
`Balance
`
`Castle Apartments
`266548
`277152
`277153
`277154
`277155
`277156
`
`277158
`
`277159
`
`277491
`
`277895
`280333
`
`12/29/2021 Work Order 223748 Installation Bore:
`1/31/2022 January 2022 interest
`2/28/2022 February2022 Interest
`3/31/2022 March 2022 Interest
`4/30/2022 April2022 Interest
`5/31/2022 May 2022 Interest
`6/6/2022 CK #443 DATED 5/31/22
`6/30/2022 June 2022 Interest
`7/9/2022 CK #467 DATED 6/13/22
`7/30/2022 July 2022 Interest
`8/15/2022 CK #296 DATED8/3/22
`8/31/2023 August 2022 Interest
`9/2/2022 CK #1527050 DATED 6/30/22 EVERSOURCE
`9/6/2022 CK #304 DATED 9/1/22
`9/30/2022 September Interest
`10/31/2022 October Interest
`10/31/2022 CK #331 DATED 10/25/2022
`
`$43,683.42
`$E72.67
`$890.12
`$907.92
`$926.08
`$944.60
`
`$963.50
`
`$982.77
`
`368.55
`
`368.55
`368.55
`
`$2,066.44)
`
`($2,167.08)
`
`($16,546.63)
`
`
`
`$5,116.70)
`
`$43,663.42
`$44,536.09
`$45,426.21
`$46,334.13
`$47,260.21
`$48,204.81
`$46,138.40
`$47,101.90
`$44,934.82
`$45,917.59
`$27,370.96
`$27,739.51
`$13,972.91
`$11,972.91
`$12,341.46
`$12,710.01
`$7,593.31
`
`

`

`EXHIBIT B
`
`

`

`|
`Statement
`
`Date: 1/18/2024
`
`a
`
`*# Shaffer Beacon
`Bo
`MECHANICAL
`uatity & tetegetes enstM .
`12 Mechanicsville Road
`P.O. Box 868
`Granby, CT 06035
`(860) 653-4767 (fax)
`(860) 844-0111
`Lic. # S1-0393852, P1-0289777, HOD-000128
`
`277493
`
`8/31/2022 Finance Charge - August
`
`$42.38
`
`$0.00
`
`$42.38
`
`Hilltop Towers
`277492
`
`8/31/2022 Finance Charge - August
`
`$26.55
`
`$0.00
`
`Hilltop Towers Balance Due:
`
`SRK - Middie Street Apts
`277496
`8/31/2022 Finance Charge - August
`
`$26.62
`
`$0.00
`
`SRK - Middle Street Apts Balance Due:
`
`Piping Rock Apartments
`273044
`3/11/2022 Work Order 229190 No Heat
`273045
`3/11/2022 Work Order 229558 No Heat
`273046
`3/11/2022 Work Order 230092 No Heat
`273047
`3/11/2022 Work Order 231497 No Heat
`273048
`3/11/2022 Work Order 232606 No Heat
`274705
`3/6/2022 Work Order 233502 No Heat
`274783
`3/8/2022 Work Order 233357 No Heat
`277054
`3/7/2022 Work Order 233279 Service
`277495
`8/31/2022 Finance Charge - August
`277896
`9/30/2022 Finance Charge - September
`279877
`11/30/2022 Finance Charge
`280654
`12/31/2022 Finance Charge
`289666
`1/31/2023 Finance Charge
`289667
`2/28/2023 Finance Charge
`289668
`3/31/2023 Finance Charge
`289669
`4/30/2023 Finance Charge
`289670
`6/31/2023 Finance Charge
`289671
`6/30/2023 Finance Charge
`289672
`7/31/2023 Finance Charge
`289673
`8/31/2023 Finance Charge
`289674
`9/30/2023 Finance Charge
`289675
`10/31/2023 Finance Charge
`289676
`11/30/2023 Finance Charge
`289677
`12/31/2023 Finance Charge
`
`Piping Rock Apartments Balance Due:
`
`$2,246.87
`$3,332.04
`$744,45
`$372.23
`$670.04
`$664.69
`$1,187.14
`$2,143.13
`$247.15
`$240.50
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`
`$1,673.15
`$1,943.09
`$0.00
`$0.00
`$0.00
`$0.00
`$276.23
`$475.17
`$0.00
`$0.00
`$0.00
`$0.00
`$0.00
`$0.00
`$0.00
`$0.00
`$0.00
`$0.00
`$0.00
`$0.00
`$0.00
`$0.00
`$0.00
`$0.00
`
`$26.55
`
`$26.55
`
`$26.62
`
`$26.62
`
`$673.72
`$1,388.95
`$744.45
`$372.23
`$670.01
`$664.69
`$910.88
`$1,667.96
`$247.15
`$240.50
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`$141.86
`
`$9,566.58
`
`

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket