`In the United States Court of Federal Claims
`No. 19-859
` (Filed: 13 May 2022)
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`***************************************
`E-NUMERATE SOLUTIONS, INC., and
`*
`E-NUMERATE, LLC,
`*
`
`
`*
`
`Plaintiffs,
`*
`
`
`*
`v.
`
`*
`
`
`*
`THE UNITED STATES,
`*
`
`
`*
`
`Defendant
`*
`
`
`*
`***************************************
`
`
`ORDER
`
`
`On 10 May 2022, plaintiffs filed an unopposed motion to amend the Court’s previous
`
`scheduling order, ECF No. 77. See Pl.’s Unopposed Mot. to Amend the Scheduling Order, ECF
`No. 84. Plaintiffs’ counsel describes several scheduling conflicts and states the government does
`not oppose its motion. Id. at 1–2.
`
`
`For good cause shown, the Court GRANTS plaintiffs’ motion to amend the current
`scheduling order and ADOPTS the following modified claim construction briefing schedule:
`
`
`Event
`Plaintiffs file their reply
`claim construction briefs
`The government files its
`surreply claim construction
`briefs
`Plaintiffs file their surreply
`claim construction brief
`regarding indefiniteness
`terms
`The parties submit the joint
`claim construction statement
`and propose dates for the
`Markman hearing
`If desired, parties may submit
`joint technical tutorial to the
`Court
`
`Prior Deadline
`13 May 2022
`
`New Deadline
`27 May 2022
`
`27 May 2022
`
`24 June 2022
`
`10 June 2022
`
`8 July 2022
`
`17 June 2022
`
`15 July 2022
`
`24 June 2022
`
`22 July 2022
`
`
`
`Case 1:19-cv-00859-RTH Document 85 Filed 05/13/22 Page 2 of 2
`
`To be scheduled
`8 July 2022
`
`To be scheduled
`29 July 2022
`
`Markman hearing
`Deadline for the government
`to produce technical
`documents for additional
`agencies named in the second
`amended complaint
`
`IT IS SO ORDERED.
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`s/ Ryan T. Holte
`RYAN T. HOLTE
`Judge
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`- 2 -
`
`