`January 16, 2020
`
`
`Kimberly D. Bose, Secretary
`Federal Energy Regulatory Commission
`888 First Street, NE
`Room 1A
`Washington, DC 20426
`
`Re: Elba Liquefaction Company, L.L.C. and
`
`Southern LNG Company, L.L.C.
`Docket No. CP14-103-000
`Elba Liquefaction Project
`Updated Request to Place Facilities In-Service
`
`
`
`Dear Ms. Bose:
`
`
`
`
`
`
`On June 1, 2016, the Federal Energy Regulatory Commission (“Commission”) issued in the
`captioned proceeding, its Order Granting Section 3 and Section 7 Authorizations (“June 1 Order”),
`in which authorization was granted to Elba Liquefaction Company, L.L.C. and Southern LNG
`Company, L.L.C. (together referred to as “Companies”) to construct and operate new natural gas
`liquefaction and export facilities and to abandon its LNG Truck Loading Facilities (“Elba
`Liquefaction Project”). On June 27, 2016, Companies filed their Implementation Plan pursuant to
`Condition 8 of Appendix B to the June 1 Order.
`
`
`By letter order dated October 17, 2016, Companies received Commission authorization to
`
`commence initial site preparation of the Elba Liquefaction Project. In compliance with
`Environmental Condition 10 of Appendix B to the June 1 Order, Companies have filed monthly
`status reports (“Reports”) showing construction and restoration progress of the Elba Liquefaction
`Project. The Movable Modular Liquefaction System No. 2 (“MMLS #2) facilities will be ready to
`place in-service on January 16, 2020. This will be the fourth MMLS system to be placed in-service.
`
`On January 13, 2020, Companies requested written authorization to place the MMLS #2
`
`facilities associated with the Elba Liquefaction Project In-Service in compliance with Environmental
`Condition 13 of Appendix B to the June 1 Order. Companies herewith update the January 13 filing
`and respectfully request written authorization from the Director of the Office of Energy Projects to
`place the MMLS #2 facilities associated with the Elba Liquefaction Project In-Service on January
`16, 2020. Condition 13 states that such authorization will only be granted following a determination
`that the facilities have been constructed in accordance with FERC approval and applicable standards,
`can be expected to operate safely as designed, and the rehabilitation and restoration of the right-of-
`way and other areas affected by the Project are proceeding satisfactorily.
`
`Companies state that the commissioning tests confirm that the MMLS #2 facilities have been
`
`constructed in accordance with FERC approval and applicable standards and can be operated safely
`in accordance with the FERC Conditions in the June 1 Order. Additionally, Companies confirm that
`
` 569 Brookwood Village, Suite 749 Birmingham, Alabama 35209 205-325-3668
`
`
`
`Ms. Kimberly D. Bose
`January16, 2020
`Page 2
`the rehabilitation and restoration of the right-of-way and other areas affected by the Project are
`proceeding satisfactorily and that no environmental problem areas or non-compliance issues were
`identified by the Commission Staff during their inspection in September.
`
`Further, Companies provide in Appendix A the executed in-service test Certification showing
`
`that the in-service test has been completed.
`
`With this submittal, Companies believe they have filed all documentation required by FERC
`
`staff demonstrating readiness for the Elba Liquefaction Project to be placed into service. Companies
`are herein requesting authorization to place the MMLS #2 facilities in service on January 16, 2020
`as authorized by the June 1 Order.
`
`
`
`
`
`
` A Certificate of Service is attached.
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`/s/ Tina S. Hardy
`Tina S. Hardy
`Manager - Regulatory
`Elba Liquefaction Company, L.L.C. and
`Southern LNG Company, L.L.C.
`Post Office Box 2563
`Birmingham, Alabama 35202-2563
`(205) 325-3668
`tina_hardy@kindermorgan.com
`
`
`
`
`
`CERTIFICATE OF SERVICE
`
`I hereby certify that I have served the foregoing public documents by electronic
`
`mail upon each person designated on the official service list compiled by the Secretary in
`
`this proceeding.
`
`Dated at Birmingham, Alabama this 16th day of January 2020.
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`/s/ Tina S. Hardy
`Tina S. Hardy
`Manager - Regulatory
`Elba Liquefaction Company, L.L.C. and
`Southern LNG Company, L.L.C.
`Post Office Box 2563
`Birmingham, Alabama 35202-2563
`(205) 325-3668
`tina_hardy@kindermorgan.com
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`CERTIFICATION STATEMENT
`
`Appendix A
`Appendix A
`
`The signature parties below representing Shell U.S. Gas’ & Power LLC
`
`and Elba Liquefaction Company, L.L.C. hereby certify that the in-service test for
`
`the MMLS Unit 2 associated with the Elba Liquefaction Project (“Project”)
`
`authorized in Docket No. CP14-103 has been completed. The in-service test was
`
`completed in an 8-day period and consisted of a full capacity test, as defined by
`
`the environmental conditions, but in no case less than 90% of the LDQ.
`
`AbeHecrel
`Elba Liquefaction Company, L.L.C.
`
`Sworn to and subscribed
`before me this | day of
`yo
`oP
`y
`fe
`wie
`
`
`
`=
`
`|
`NotaryPublic
`My Commission expires: V
`
`“AEORGAR
`
`OM V9 %& 3
`OyUBe
`AM couse
`
`any
`
`