`RE: Port Arthur LNG, LLC, Docket No. CP17-20-000
`Supplement No. 4 to Implementation Plan No. 268
`Supplement No. 2 to Implementation Plan No. 276
`Supplement No. 3 to Implementation Plan No. 292
`Condition 84
`
`Dear Ms. Reese:
`
`On April 18, 2019, the Federal Energy Regulatory Commission (“Commission”) issued its “Order
`Granting Authorization under Section 3 of the Natural Gas Act” in the above-referenced docket
`(the “Order”). The Order authorizes Port Arthur LNG, LLC (“Port Arthur LNG” or “PALNG”) to
`construct and operate its Liquefaction Project (“Project”) subject to the conditions listed in
`Appendix A of the Order. Construction of the project began in November 2019 and is ongoing.
`
`In today’s submittal, Port Arthur LNG is providing documentation to install the balance of the
`ISBL and OSBL electrical lighting design not previously approved via FERC Accession No.
`20250606-3059. PALNG is providing a response to the Conditions relevant to the scope of this
`request as further described below.
`
`PALNG respectfully requests FERC to review this package and issue approval to install the
`balance of the ISBL and OSBL electrical lighting design on or before September 19, 2025, in order
`to facilitate PALNG’s construction scheduling efforts.
`
`Attachment 1 — Document Index
`Attachment 2 — Narrative to Install the ISBL and OSBL Electrical Lighting Design Balance
`Attachment 3 — Supporting Documentation
`
`Please note that some of the material filed herein contains Privileged and/or Critical Energy
`Infrastructure Information (“CEII”). Attachments 1, 2 and 3 include documents that contain
`proprietary information and/or CEIl. Pursuant to Section 388.112 of the Commission’s
`
`
`
`
`
`
`
`
`Port Arthur Liquefaction Project Public
`Docket No. CP17-20-000
`
`regulations, Port Arthur LNG requests that the Commission treat this information as privileged
`material. The information included in these attachments meets the Commission’s definition of
`privileged material and treatment of this information as privileged is therefore warranted. Port
`Arthur LNG is submitting a public version of this filing, with the privileged material redacted. The
`privileged material has been labeled accordingly and is not to be released. Port Arthur LNG
`previously filed a proposed form of Protective Order and Non-Disclosure Certificate in this
`proceeding on November 29, 2016.
`
`Port Arthur LNG acknowledges that the Director of OEP, or the Director’s designee, has delegated
`authority to address any requests for approvals or authorizations necessary to carry out the
`conditions of the Order, and take whatever steps are necessary to ensure the protection of life,
`health, property, and the environment during construction and operation of the project.
`
`Please contact me if you have any questions related to this filing. Thank you for your attention to
`these matters.
`
`Respectfully submitted,
`
`/s/Jim Thompson
`
`Jim Thompson
`Manager, Permitting & Compliance
`Port Arthur LNG, LLC
`
`cc: Michael Taylor
`Jerrod Harrison
`Bill Lansinger
`Danielle Gordon
`
`
`
`
`
`
`
`
`Port Arthur Liquefaction Project Public
`Docket No. CP17-20-000
`
`Attachment 1
`
`Document Index
`(CEII)
`Port Arthur Liquefaction Project
`
`Note — This attachment includes Critical Energy Infrastructure Information (CEII) and has been
`removed from the Public version.
`
`
`
`
`
`
`
`
`Port Arthur Liquefaction Project Public
`Docket No. CP17-20-000
`
`Attachment 2
`
`Narrative to Install the
`ISBL and OSBL Electrical Lighting Design Balance
`(CEII)
`Port Arthur Liquefaction Project
`
`Note — This attachment includes Critical Energy Infrastructure Information (CEII) and has been
`removed from the Public version.
`
`
`
`
`
`
`
`
`Port Arthur Liquefaction Project Public
`Docket No. CP17-20-000
`
`Attachment 3
`
`Supporting Documentation
`(CEII)
`Port Arthur Liquefaction Project
`
`Note — This attachment includes Critical Energy Infrastructure Information (CEII) and has been
`removed from the Public version.
`
`
`
`
`
`
`
`
`Public
`
`CERTIFICATE OF SERVICE
`
`I hereby certify that I have this day served the foregoing document upon each
`person designated on the official service list compiled by the Secretary in this proceeding.
`
`Dated at Houston, TX this 22" day of August 2025.
`
`/s/ Brittany Khandoga
`
`Brittany Khandoga
`
`1500 Post Oak Blvd., Suite 1000
`Houston, TX 77056
`bkhandoga@SempraGlobal.com
`
`
`
`
`
`
`
`
`
`