throbber

`
`
`
`Date
`
`Project
`
`
`Personnel
`
`
`
`FEDERAL ENERGY REGULATORY COMMISSION
`FIELD INSPECTION REPORT
`
`
`April 30, 2021
`
`
`
`Adelphia Gateway, LLC
`Adelphia Gateway Project
`Delaware, Chester, Montgomery, Bucks, and Northampton Counties,
`Pennsylvania; New Castle County, Delaware
`Docket Nos.: CP18-46-000 and CP18-46-001
`Authority: Section 7(c)
`
`FERC Contractor:
`FERC Contractor Staff:
`Company Staff:
`
`Tetra Tech, Inc.
`David Wertz
`Edward Bova (Environmental Inspector), Jeff
`Smith (Environmental Compliance
`Coordinator)
`
`Inspection Summary
`
`0
`
`0
`
`No
`
`No
`
`Problem Areas
`
`Noncompliances
`
`Follow-Up Letter Required
`
`Refer to Enforcement
`
`Introduction
`
`On April 30, 2021, David Wertz of Tetra Tech, performed a construction inspection of the Adelphia
`Gateway, LLC (Adelphia) Adelphia Gateway Project (Project) under contract to the Federal Energy
`Regulatory Commission (FERC or Commission) and per the request of the FERC Project Manager,
`Kylee Ferrara.
`
`The Project consists of the construction and operation of a total of about 4.7 miles of new 16-inch-
`diameter pipeline, two new compressor stations (CSs) that together provide a total of 11,250 horsepower
`(hp) of compression, and appurtenant facilities in Delaware and Pennsylvania; the Project also involves
`the purchase, repurpose, and operation of Interstate Energy Company, LLC’s (Interstate Energy) existing
`non-National Gas Act jurisdictional system in Pennsylvania. More specifically, the Project includes the
`following new facilities:
`
`
`
`

`

`
`
`
`
`• construction of an approximately 4.4-mile-long, 16-inch-diameter lateral in Delaware County,
`Pennsylvania extending from the proposed Marcus Hook CS to interconnections with
`Transcontinental Gas Pipe Line Company (Transco) and the Philadelphia Electric Company
`(PECO1; Tilghman Lateral2);
`
`• construction of an approximately 0.3-mile-long, 16-inch-diameter lateral extending from the
`proposed Marcus Hook CS to an existing meter station owned by Delmarva Power and Light
`Company (Delmarva)3 in New Castle County, Delaware (Parkway Lateral);4
`
`• construction of a new 5,625 hp CS in Delaware County consisting of three 1,875 hp natural gas-
`fired reciprocating compressor units (Marcus Hook CS);
`
`• construction of a new 5,625 hp CS in Bucks County, Pennsylvania consisting of three 1,875 hp
`natural gas-fired reciprocating compressor units (Quakertown CS); and
`
`• construction of five new meter stations and other appurtenant facilities.
`
`In addition, Adelphia plans to purchase and repurpose Interstate Energy’s existing oil and natural gas
`pipeline facilities (with minor modifications), including:
`
`• an approximately 84.2-mile-long, 18-inch-diameter mainline pipeline, which is capable of
`transporting either oil or natural gas and which extends from the Marcus Hook Industrial
`Complex to the Martins Creek Terminal in Northampton County, Pennsylvania; 5
`
`• an approximately 4.4-mile-long, 20-inch-diameter mainline, which transports only natural gas,
`which originates in Northampton County and terminates at the Martins Creek Terminal;
`
`•
`
`four meter stations; and
`
`• other appurtenant facilities.
`
`Adelphia proposes to operate the Project in three zones: Zone North A, Zone North B, and Zone South.
`The Project would enable Adelphia to provide up to 250,000 dekatherms per day (Dth/day) of
`bidirectional firm natural gas transportation service in Zone North A; up to 350,000 Dth/day of firm
`transportation service in Zone North B; and up to 250,000 Dth/day of firm tran sportation service in Zone
`South.
`
`Adelphia states that the facilities will be placed into service in two phases . The Zone North facilities
`were placed into service on January 13, 2020. The Zone South facilities will be placed in service
`following the conversion of those facilities. The anticipated in-service timing for the Project is
`November 2021.
`
`
`1 PECO is a public utility owned by Exelon Corporation providing natural ga s a nd electricity to customers in Pennsylvania .
`2 The Tilghma n La teral will a lso interconnect with the Monroe Refinery.
`3 Delma rva is a public utility owned by Exelon Corporation (Exelon) providing na tural ga s a nd electricity to customers in
`Dela wa re a nd Maryland.
`4 The Pa rkway La teral will a lso interconnect with two interstate natural ga s pipelines owned by Columbia Ga s
`Tra nsmission a nd Texas Eastern Tra nsmission Company, LP.
`5 The northern 34.8-mile-long segment is ca pable of transporting either oil or na tural ga s, a nd the southern 49.4-mile-long
`segment was previously used to transport oil only. Adelphia states that, since 2014, the northern segment has transported
`only na tural ga s a nd the southern segment has been inactive.
`
`
`
`

`

`
`
`
`The purpose of the inspection was to determine Adelphia’s compliance with the environmental
`conditions of the Commission’s December 20, 2019 Order Issuing Certificates for the Project and to
`inspect the construction conditions of the Project facilities and rights-of-way (ROWs).
`
`The findings of the inspection were that no instances of noncompliance or problem areas were identified.
`
`A site map and photographic record are presented in this report.
`
`Inspection
`
`On April 30, 2021, weather conditions were clear, with temperatures ranging from the high-50s (°F) to
`high-60s (°F) in the Project area. A total of approximately 1.8 inches of precipitation was recorded in
`nearby Philadelphia during the two weeks before the inspection. Soil conditions were generally wet.
`
`The inspection included the Quakertown CS (Photo Numbers [Nos.] 1 to 3), Paoli Pike Blowdown
`Assembly Valve (BAV; Photo Nos. 4 to 6), Transco Meter Station (Photo Nos. 7 and 8), and Tilghman
`Lateral (Photo Nos. 9 and 10).
`
`Adelphia reported that construction activity at Marcus Hook CS, Quakertown CS, and Transco Meter
`Station had not progressed during previous weeks because a new contractor was being onboarded to
`complete remaining construction. The previous contractor completed removal of its equipment and
`materials from these sites. The new contractor began mobilizing materials and personnel, and was
`already maintaining erosion control devices (ECDs). Construction was active along the Tilghman
`Lateral Phase I, the connecting pipeline between the Tilghman Lateral and Transco Meter Station, and
`the Paoli Pike BAV.
`
`Quakertown CS
`
`Adelphia reported that construction had not yet resumed at the Quakertown CS site. On the western side
`of the Quakertown CS site, additional temporary workspace (ATWS) QCS-01.1 was set up for use
`(Photo No. 1). Equipment mats were placed on top of geotextile fabric. The workspace was clearly
`marked with stakes, and “wetland buffer” and “no refueling” areas were properly identified with signage.
`ECDs were installed along the perimeter of the workspace. “No parking” and “wetland buffer” signage
`was clearly posted along the edge of Permanent Access Road AR-QCS-01, which leads to the office
`trailers, to help prevent unallowed or inadvertent use of this area during construction (Photo No. 2).
`Within the CS yard, construction activity had not yet resumed. Equipment from the previous contractor
`was removed, and some Project materials were staged (Photo No. 3). Site soils from excavation of the
`detention pond were stockpiled and stabilized. No environmental concerns were identified.
`
`Paoli Pike BAV
`
`At the Paoli Pike BAV site, the workspace was clearly marked with stakes and all construction activity
`was within the approved workspace limits. ECDs included chain-link fence reinforced “super” silt fence
`and compost filter sock, which were installed along the perimeter of the workspace (Photo No. 4). The
`reinforced silt fence also functioned as an exclusion fence to keep bog turtle out of the construction
`workspace (bog turtle may be present in the surrounding wetland). Additionally, a bog turtle specialist
`was on-site for bog turtle surveillance during construction and to ensure that the barrier fencing was
`effective. Within the workspace boundaries, equipment mats were overlain on geotextile fabric to
`protect the wetland soils and to provide a stable workspace. The workspace was tidy and well-
`maintained. An excavation around the mainline pipe was stabilized with a trench box, and a section of
`the existing mainline was cut out for the planned installation of the BAV (Photo No. 5). Groundwater
`seeping into the excavation was pumped temporarily into a nearby portable water storage tank that was
`staged within the workspace for later offsite disposal at a treatment facility, according to Adelphia.
`
`
`
`

`

`
`
`
`Adelphia stated that the contractor was currently determining a suitable foundation design for the
`proposed BAV, considering the existing subsoil conditions, and that installation of the BAV was
`expected to be completed in the coming weeks. In general, the workspace and adjacent roadway were
`clean and free of mud and construction debris (Photo No. 6). No environmental concerns were
`identified.
`
`Transco Meter Station
`
`Construction had not yet resumed at the Transco Meter Station site. Exposed soils were temporarily
`stabilized with straw mulch and seed. Meanwhile, stockpiled subsoil was temporarily stabilized with
`erosion control blanket and seed. ECDs were maintained around the perimeter of the site, and there was
`no evidence of sediment transport offsite (Photo No. 7). Construction of the connecting pipeline between
`the Tilghman Lateral and Transco Meter Station was mostly complete . The pipeline was installed
`underneath the roadway tied-in to the Tilghman Lateral and capped near the southern boundary of the
`Transco Meter Station (Photo No. 8). Adelphia reported that the connecting pipeline segment and the
`Tilghman Lateral were hydrotested, cleaned, tested for deformity, and being dried with pressurized air.
`Once dry, the installed pipeline would be filled with nitrogen in the coming days (to prevent corrosion)
`because this portion of the pipeline was expected to be idle while other Project components are
`constructed.
`
`Tilghman Lateral
`
`At the Tilghman Lateral Horizontal Directional Drill (HDD)-1 exit site near Station Number (Sta. No.)
`20+16, pressurized air was being pushed through the pipeline installed along HDD-1 crossing to dry the
`pipeline. According to Adelphia, once drying is complete, the piping will be pressurized with nitrogen
`to prevent corrosion (Photo No. 9). To the east of the completed HDD-1 crossing, within ATWS-TL-
`03a, water used for hydrostatic testing was temporarily stored in a portable water tank. Further to the
`east, spoils excavated from the Paoli Pike BAV site were temporarily stored in roll-off containers. All
`activity was within the approved workspace limits, and no environmental concerns were identified
`(Photo No. 10).
`
`Conclusions and Recommendations
`
`A follow-up letter is not required at this time because no instances of noncompliance were identified.
`Overall, construction was progressing satisfactorily, environmental conditions were acceptable, and no
`environmental concerns were identified. Another inspection is tentatively scheduled for the week of
`May 24, 2021.
`
`
`
`

`

`SITE MAP
`SITE MAP
`
`=
`x
`MONROECOUNTY
`CARBON COUNTY eae -
`
`NORTHAMPTON
`COUNTY
`
`Existing aK
`Columbia Gas
`Meter Station \_
`
`LEHIGH COUNTY
`
`Existing Martins
`Creek Station
`
`Existing 20-Inch-Diameter
`Pipeline
`
`Existing
`Transco Meter
`Station
`
`New Jersey
`
`SJPenns WATE
`A
`y
`
`\
`
`oN
`New Quakertown
`MeterStation ~
`and Tap Valve
`~
`
`,
`
`Esn China, Esti Thailand, Tom Tom, 2013
`
`/
`
`Existing Quakertown
`Station
`
`BUCKS COUNTY
`
`schwenksville
`
`New Skippack
`Tap Valve
`
`MONTGOMERY
`COUNTY
`
`BERKS COUNTY
`
`2
`PHILADELPHIA7
`COUNTY
`
`CHESTER
`COUNTY
`
`DELAWARE
`COUNTY
`
`Milepost
`Existing Facility
`) Proposed Facility
`Proposed Blowdown Assembly Valve
`Proposed Mainline Valve
`eee Existing 18-Inch-Diameter Mainline
`———~ Existing 20-Inch-Diameter Pipeline
`“=== Proposed Parkway Lateral
`me Proposed Tilghman Lateral
`
`Adelphia Gateway
`Project
`
`Scale: 1:575,000
`
`Project Overview
`
`Basemap Source: Esr, DeLeLorme, NAVTEO
`USGS.
`Imermap, IPC, NRCAN, Es*i Japan, MET!
`
`
`
`
`
`
`
`
`
`

`

`FEDERAL ENERGY REGULATORY COMMISSION
`PHOTOGRAPHIC RECORD
`
`
`Company: Adelphia Ga teway, LLC
`
`Docket Nos.: CP18-46-000 and 18-46-001
`
`Project: Adelphia Ga teway
`
`Facility: Qua kertown CS
`
`Photo No.: 1
`
`Facility: Qua kertown CS
`
`Direction: South
`
`Assessment: Acceptable
`
`Comments: Open ROW, ATWS-
`QCS-01.1. The ATWS wa s set up
`for use. Equipment mats were placed
`on top of geotextile fabric. The
`workspace was clearly marked with
`sta kes, and “wetland buffer” a nd “no
`refueling” a reas were properly
`identified with signa ge. ECDs were
`insta lled a long the boundary of the
`workspace. No environmental
`concerns were identified.
`
`Photo No.: 2
`
`Facility: Qua kertown CS
`
`Direction: Ea st
`
`Assessment: Acceptable
`
`Comments: The view looking east
`towa rd office trailers a long
`Perma nent Access Road AR-QCS-
`01. “No pa rking” and “wetland
`resource” signage wa s posted along
`the edge of the road to help prevent
`una llowed or ina dvertent use of this
`a rea during construction.
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`

`

`FEDERAL ENERGY REGULATORY COMMISSION
`PHOTOGRAPHIC RECORD
`
`
`Company: Adelphia Ga teway, LLC
`
`Docket Nos.: CP18-46-000 and 18-46-001
`
`Project: Adelphia Ga teway
`
`Facilities: Quakertown CS/Paoli Pike BAV
`
`Photo No.: 3
`
`Facility: Qua kertown CS
`
`Direction: North
`
`Assessment: Acceptable
`
`Comments: Industrial ROW. View
`of the CS ya rd looking south from
`the northern end of the site.
`Construction activity had not yet
`resumed. Some materials were
`sta ged within the yard. Site soils
`from excavation of the detention
`pond were stockpiled a nd stabilized.
`No environmental concerns were
`identified.
`
`
`
`
`
`Photo No.: 4
`
`Facility: Pa oli Pike BAV
`
`Direction: North
`
`Assessment: Acceptable
`
`Comments: Wetla nd ROW. The
`workspace was clearly marked with
`sta kes and all construction a ctivity
`wa s within the a pproved workspace
`limits. ECDs included chain-link
`fence reinforced “super” silt fence
`a nd compost filter sock, which were
`insta lled a long the perimeter of the
`workspace. The reinforced silt fence
`a lso functioned as a n exclusion fence
`to keep bog turtle out of the
`construction workspace. Equipment
`ma ts were overlain on geotextile
`fa bric to protect the wetland a nd to
`provide a stable workspace. The
`workspace was tidy and well-
`ma intained.
`
`
`
`
`
`
`
`
`
`
`

`

`FEDERAL ENERGY REGULATORY COMMISSION
`PHOTOGRAPHIC RECORD
`
`
`Company: Adelphia Ga teway, LLC
`
`Docket Nos.: CP18-46-000 and 18-46-001
`
`Project: Adelphia Ga teway
`
`Facility: Pa oli Pike BAV
`
`Photo No.: 5
`
`Facility: Pa oli Pike BAV
`
`Direction: Northwest
`
`Assessment: Acceptable
`
`Comments: Wetla nd ROW. A
`section of the existing mainline wa s
`cut out for the planned installation of
`the BAV. Groundwater seeping into
`the excavation was pumped into the
`porta ble wa ter storage tank during
`construction, which was pumped to a
`ta nker truck (visible in the
`ba ckground) for offsite disposal a t a
`trea tment facility, a ccording to
`Adelphia . Adelphia stated that the
`contractor was currently determining
`a suita ble foundation design for the
`BAV, considering the existing
`subsoil conditions. Installa tion of the
`BAV wa s expected to be completed
`in the coming weeks.
`
`Photo No.: 6
`
`Facility: Pa oli Pike BAV
`
`Direction: Southeast
`
`Assessment: Acceptable
`
`Comments: Wetla nd ROW. A
`genera l view of the excavation for
`the BAV, the workspace, a nd
`a djacent roadway. The workspace
`a nd roadway were clea n a nd free of
`mud a nd construction debris. No
`environmental concerns were
`identified.
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`

`

`FEDERAL ENERGY REGULATORY COMMISSION
`PHOTOGRAPHIC RECORD
`
`
`Company: Adelphia Ga teway, LLC
`
`Docket Nos.: CP18-46-000 and 18-46-001
`
`Project: Adelphia Ga teway
`
`Facility: Tra nsco Meter Station
`
`Photo No.: 7
`
`Facility: Tra nsco Meter Station
`
`Direction: South
`
`Assessment: Acceptable
`
`Comments: Forested ROW.
`Exposed soils were temporarily
`sta bilized with straw mulch and seed.
`Stockpiled subsoil wa s temporarily
`sta bilized with erosion control
`bla nket and seed. According to
`Adelphia , construction is expected to
`resume in the coming weeks. No
`environmental concerns were
`identified.
`
`
`
`
`
`Photo No.: 8
`
`Facility: Tra nsco Meter Station
`
`Direction: South
`
`Assessment: Acceptable
`
`Comments: Industrial ROW,
`Tilghma n Lateral. Construction of
`the connecting pipeline between the
`Tilghma n Lateral a nd Tra nsco Meter
`Sta tion was mostly complete. The
`pipeline wa s insta lled underneath the
`roa dway a nd wa s tied-in to the
`Tilghma n Lateral. The pipeline wa s
`hydrotested, clea ned, tested for
`deformity, a nd was being dried,
`a ccording to Adelphia. Adelphia
`sta ted that the pipe would be filled
`with nitrogen in the coming days (to
`prevent corrosion).
`
`
`
`
`
`
`
`
`
`
`
`
`

`

`FEDERAL ENERGY REGULATORY COMMISSION
`PHOTOGRAPHIC RECORD
`
`
`Company: Adelphia Ga teway, LLC
`
`Docket Nos.: CP18-46-000 and 18-46-001
`
`Project: Adelphia Ga teway
`
`Spread: Tilghma n La teral
`
`Photo No.: 9
`
`Sta. No.: 20+16
`
`Direction: West
`
`Assessment: Acceptable
`
`Comments: Industrial ROW,
`Tilghma n Lateral. The pipeline
`insta lled a long the HDD-1 crossing
`wa s hydrotested, cleaned, checked
`for deformities, and wa s being dried
`with a ir, a ccording to Adelphia. The
`connecting pipeline from the
`Tilghma n Lateral to the Tra nsco
`Meter Sta tion (underneath the
`roa dway) wa s partially backfilled.
`Adelphia stated that the pipeline
`would be pressurized with nitrogen
`to prevent corrosion once drying wa s
`complete. No environmental
`concerns were identified.
`
`Photo No.: 10
`
`Sta. No.: 22+00
`
`Direction: Ea st
`
`Assessment: Acceptable
`
`Comments: Industrial ROW,
`Tilghma n Lateral, ATWS-TL-03a.
`Wa ter used for hydrostatic testing
`wa s temporarily stored in a portable
`wa ter ta nk. Further to the east, spoils
`exca vated from the Paoli Pike BAV
`site were temporarily stored in roll-
`off containers (background). All
`a ctivity was within the approved
`workspace limits, a nd no
`environmental concerns were
`identified.
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket