throbber
ENVIRONMENTAL ASSESSMENT REPORT
`
`
`Cost: $4,600,000.
`
`
`
`Federal Energy Regulatory Commission
` Office of Energy Projects, Division of Gas-Environment & Engineering
`
`
`
`
`Name of Applicant: Adelphia Gateway, LLC (Adelphia)
`
`
`Date Filed: 12/7/20
`Docket No: CP21-14-000
`
`Supplemental Filings: 1/15/21
`
`
`Type: Sections 157.205, 157.208 – Prior Notice under Blanket Certificate
`Authority
`
`Facilities
`
` Adelphia Gateway, LLC (Adelphia) requests under its blanket certificate authority granted in Docket
`No. CP82-487-000 et al., to install and operate an electric motor-driven 3,000-horsepower (HP)
`compressor unit at its Marcus Hook Compressor Station in Delaware County, Pennsylvania (Marcus Hook
`Electric Compression Project or Project). The Marcus Hook Electric Compression Project is designed to
`increase the discharge pressure and reduce the gas heat temperature level at the outlet of the Marcus Hook
`Compressor Station to provide firm service to a new shipper that will transport gas on Adelphia’s system
`to the interconnection with Columbia Gas Transmission, LLC (Columbia Gas). The certificated capacity
`of the Adelphia pipeline system would increase by 16,500 Dekatherms per day (Dth/d), from 250,000 to
`265,500 Dth/d. There would be no abandonment or reduction in service to any customer of Adelphia as a
`result of the Project.
`
`
`
`
`Environmental Impact -- Conclusions:
`
` Categorical Exclusion
`
`
`
`
`
` Environment Not Involved
`
` X Environment Complete
`
`Environmental Considerations or Comments:
`
` See attached environmental comments.
`
`
`
`
`
`Prepared by:
`/s/ John J. Wisniewski
`
`
`
`
` Date:
` 2/8/21
`
`
`
`
`
`
`
`
`
`
`
`
`
` Deficiency Letter Required
`
` EA/EIS Required
` No NOI Required
` NOI Required
`
`
` Approved by Branch Chief:
`
`
`
` Date:
` 2/9/21
`
`

`

`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
` ATTACHMENT
`
`
`
`Adelphia Gateway, LLC (Adelphia)
`Marcus Hook Electric Compression Project
`Docket No. CP21-14-000
`
`Environmental Comments
`
`
`Proposed Action
`
`
`A.
`
`On December 7, 2020, Adelphia Gateway, LLC (Adelphia) filed a request with the
`
`Federal Energy Regulatory Commission (FERC or Commission) for a Prior Notice under
`its Blanket Certificate issued in FERC Docket No. CP18-46-000 for the Adelphia
`Gateway Project. Adelphia proposes to install and operate an electric-motor driven
`(EMD) 3,000-horsepower (hp) compressor unit and associated equipment at Adelphia’s
`certificated Marcus Hook Compressor Station (MHCS) in Delaware County,
`Pennsylvania. The new electric compressor would be in addition to the three 1,875-hp
`natural gas-fired reciprocating compressor units that are part of the Adelphia Gateway
`Project.
`
`Adelphia is proposing the Marcus Hook Electric Compression Project (Project) to
`
`deliver 75,000 dekatherms per day (Dth/d) of firm natural gas capacity from the
`certificated MHCS to Adelphia’s customer at Adelphia’s interconnection with Columbia
`Gas Transmission, LLC (Columbia). Adelphia’s certificated capacity would increase
`from 250,000 to 265,500 Dth/d. Adelphia states that the purpose of this Project is to
`enable Adelphia to install facilities necessary to meet demonstrated market need for
`75,000 Dth/d of firm natural gas capacity from the MHCS to an interconnect with a
`Columbia-owned pipeline at the Delmarva Meter Station at the western terminus of the
`Parkway Lateral. No interruptions of service are planned or anticipated as a result of the
`proposed Project.
`
`The Project consists of the installation of an EMD 3,000-hp fourth compressor
`
`unit and related ancillary facilities, entirely within the MHCS’s certificated footprint.
`The new unit would be installed in the same building as the other three certificated units
`at the MHCS, and no modifications to the building would be required. Proposed
`ancillary facilities would be installed within the MHCS’s limits of disturbance (LOD).
`Adelphia would use a state highway (i.e., Ridge Road) to access the site, and construction
`materials would be staged within the MHCS’s LOD. No additional contractor yards or
`temporary workspace would be required. No facilities would be abandoned as part of
`this Project. Appendix A contains Project mapping.
`
`
`
`
`
`2
`
`

`

`
`
`
`
`In addition to the EMD 3,000-hp compressor unit, the Project would include the
`
`following ancillary facilities installed within the MHCS’s certificated LOD:
`
`
`• one horizontal process gas cooler with two 25-hp electric-driven motors;
`two variable frequency drives;
`•
`• a motor control center assembly to control the electric compressor engine from a
`central location;
`instrumentation and communication equipment necessary to monitor and control
`the operation of the Project components; and
`• electrical infrastructure to handle the required motor loads.
`
`•
`
`
`Adelphia proposes to start Project construction during the 2nd quarter of 2021
`
`after receipt of all required federal, state and local authorizations and permits. The
`Project’s in-service date is expected to occur in the 4th quarter of 2021. Construction is
`expected to require 40 workers per day; last four to six months, ten hours per day, six
`days per week; and occur concurrently with the Adelphia Gateway Project construction
`activities in the same area.
`
`
`Land Requirements
`
`Construction of the proposed Project would require approximately 4.3 acres of
`
`paved and graveled, industrial use land within the existing 7.5-acre MHCS Site. Of the
`4.3 acres affected during construction, Project operations would affect 0.3 acre of land for
`the ancillary facilities. Adelphia and its contractors would access the Project site via
`Ridge Road during construction and operations. No improvements to Ridge Road would
`be required for the Project.
`
`Construction Procedures
`
`The Project facilities would be constructed, tested, operated, and maintained in
`
`accordance with applicable federal, state and local regulations. This includes but is not
`limited to, the Natural Gas Pipeline Safety Act of 1968, as amended; the U.S.
`Department of Transportation of Natural Gas or Other Gas by Pipeline; Minimum
`Federal Safety Standards (49 Code of Federal Regulations [CFR] Part 192); and the
`FERC’s Siting and Maintenance Requirements (18 CFR § 380.15). Construction
`activities associated with the Project would primarily consist of conventional
`construction techniques. No vegetation clearing beyond that required for the
`concurrently constructed Adelphia Gateway Project would be required for the Project.
`
`The work would be performed by the same contractors for the Adelphia Gateway
`
`Project and would not require incremental construction equipment. Erosion control
`devices would already be in place at the Project site, and Project work would begin and
`end prior to completion of the Adelphia Gateway Project. Work sequencing would
`
`
`
`3
`
`

`

`
`
`
`
`include the installation of foundations for ancillary equipment followed by the
`trenching for electrical infrastructure and would conclude with the placement and
`connection of Project components. Adelphia would minimize or avoid impacts on soil
`during construction by adhering with the FERC’s Upland Erosion, Revegetation, and
`Maintenance Plan (FERC’s Plan), and FERC’s Wetland and Waterbody Construction
`and Mitigation Procedures (FERC’s Procedures), as applicable. Following facility
`installation and completion of other on-site construction activities associated with the
`Adelphia Gateway Project, all areas used as construction workspace would be cleaned
`up and returned to pre-construction conditions.
`
`Adelphia would hire one full-time environmental inspector (EI) for the Project.
`
`The EI position would be in effect throughout the duration of construction; would report
`directly to Adelphia’s Environmental, Health, and Safety Manager; and would have stop-
`work authority. The EIs’ duties would be consistent with the FERC’s Plan and would
`include ensuring compliance with Adelphia’s environmental designs and specifications,
`and other permits and authorizations.
`
`Adelphia does not currently have any future plans for expansion or abandonment
`
`for the Project facilities.
`
`Non-Jurisdictional Facilities
`
`Non-jurisdictional facilities are limited to connecting existing electrical supply to
`
`the Project components at the MHCS. Such facilities are minimal and would not require
`upgrades to the existing electrical supply to accommodate the Project. Any
`environmental review of the non-jurisdictional facilities would be conducted by the
`applicable state and local agencies.
`
`
`B.
`Environmental Analysis
`
`
`Based on our1 review of the Project, the following resources and hazards are
`
`either not present or would not be affected by the Project’s activities and would not be
`discussed further:
`• surface waterbodies and wetlands (none present);
`• vegetation and wildlife (Project area is located in a highly developed
`industrial/commercial area and consists of a maintained gravel lot and existing
`facilities with no vegetation);
`threatened and endangered species (Pennsylvania Natural Diversity Inventory
`review dated October 12, 2020 indicated no known impacts on threatened and
`endangered species from the U.S. Fish and Wildlife Service, the Pennsylvania
`
`1 “We,” “us,” and “our” refer to the environmental staff of the FERC Office of Energy Projects
`
`•
`
`(OEP).
`
`
`
`4
`
`

`

`
`
`
`
`•
`
`•
`
`(PA) Department of Conservation and Natural Resources, PA Fish and Boat
`Commission, and PA Game Commission);
`the project is not within a flood hazard zone;
`•
`• no hydrostatic testing would occur as part of this Project;
`• mineral resources: there are no mineral producers, including oil and gas wells;
`coal mines; or non-fuel mineral resources near the MHCS. Similarly, an online
`search did not identify any potentially exploitable mineral resources within 0.25
`mile of the MHCS;
`• subsidence from previous mining or karst terrain: the Project is not in an area of
`known active or previous mining and the Project is not with any known karst
`areas;
`landslides and steep slopes: the Project is confined to an area identified as low
`susceptibility and low incidence of landslide and slumping occurrence, and the
`Project site does not have any steep slopes;
`• active faults: the closest active fault/seismic zone is the Central Virginia Seismic
`Zone located southeast of Charlottesville, Virginia. There are no active faults in
`proximity to the Project.
`• blasting: the Project would not require blasting;
`• cultural resources (in a letter dated December 18, 2020 the Pennsylvania
`Historical and Museum Commission State Historic Preservation Office provided
`comments that there are no historic or archaeological properties in the area of this
`Project);
`there are no National Park System Lands, Indian Reservations, National
`Wildlife Refuges, or National Wilderness Areas within 0.25 mile of the
`Project. Additionally, there are no All-American Roads, Natural Areas,
`historic areas, hiking trails or scenic areas identified within 0.25 mile of the
`Project; and
`the Project is not located on any state, federal, or conservation lands.
`
`•
`
`
`Groundwater
`
`Adelphia would require additional water during construction of the Project for
`
`dust suppression and concrete work (i.e. foundations and supports). Adelphia would
`obtain water for these activities from municipal sources.
`
`The Project overlies crystalline rock-type Piedmont and Blue Ridge bedrock
`
`aquifer. The Project is also within the Delaware River Streamflow Zone / New Jersey
`Coastal Plains Aquifer sole source aquifer zone. Four groundwater supply wells are
`within 150 feet of the Project Area; all four are abandoned. Adelphia did not identify
`any springs during its field survey of the Project Area. No excavation would occur
`along the access road, and the Project would not require blasting. Furthermore,
`Adelphia is not aware of any contaminated soil or groundwater at the MHCS Site.
`
`
`
`5
`
`

`

`
`
`
`
`Some excavation would be required to install foundations for the ancillary facilities.
`Excavation depths would range from 5 to 8 feet below ground surface. A boring log
`collected at the northeast corner of the MHCS Site found depth to groundwater to be 9
`feet below ground surface. Therefore, it is not expected that groundwater would be
`encountered during construction. Should groundwater be encountered, Adelphia would
`dewater the excavation area in accordance with its Soil, Groundwater, and Drilling
`Fluid Management Plan2 for the Adelphia Gateway Project as well as the FERC’s
`Procedures and Plan. Given groundwater conditions in the Project area and with
`implementation of the measures discussed above, we conclude that construction and
`operation of the planned Project facilities would not significantly adversely impact
`groundwater quality or supply.
`
`
`Geologic Resources
`
`
`The proposed Project would be located entirely within the certificated LOD of the
`
`MHCS. The Project facilities are located within the Lowland and Intermediate Upland
`Section of the Atlantic Coastal Plain Province. Bedrock underlying the MHCS consists
`of anorthosite from the Lower Paleozoic and Trenton gravel from the tertiary. The site
`has been historically maintained as an industrial site and is well graveled and mostly
`level.
`
`Geologic Hazards
`
`
`site:
`
`The following geologic hazards have a low potential of occurring at the Project
`
`
`• Seismicity – Probabilistic seismic-hazard maps show the Project is within an area
`where Peak Ground Acceleration are estimated to be 2-3 percent gravity with a ten
`percent probability of being exceeded in 50 years;
`
`• Soil Liquefaction – Due to the low probability of a significant seismic event and
`the industrial nature of the Project site, the risk of soil liquefaction occurring and
`affecting the Project is minimal. The U.S. Geological Survey (USGS) has mapped
`areas susceptible to liquefaction but there are no areas identified within
`Pennsylvania or Delaware.
`
`
`Due to the lack of mineral resources and low potential of geologic hazards in the
`
`Project area, we conclude that the Project would not impact local geological resources
`and would not be impacted by geologic hazards.
`
`
`
`2 The Soil, Groundwater, and Drilling Fluid Management Plan for the Adelphia Gateway Project
`is available on the FERC docket at accession number 20201005-5008.
`
`
`
`6
`
`

`

`
`
`
`
`Soils and Erosion Control
`
`Adelphia compiled soil descriptions for the Project from information in the U.S.
`
`Department of Agriculture Natural Resources Conservation Service’s (NRCS) Web Soil
`Survey. The Web Soil Survey provides soil characteristics that can be used to describe
`limitations of the soils including shallow depth-to-bedrock, poor revegetation potential,
`high compaction, high wind erodibility, high water erodibility, and farmland
`classification. Two soils, Othello Silt Loam (4.0 acres) and Urban Land (0.3 acre), occur
`within the Project area.
`
`The Urban Land soil type does not have any relevant soil limitations. Othello Silt
`
`Loam has a high compaction potential, moderate wind and water erosion potentials, and a
`moderate revegetation potential. Shallow depth to bedrock is not associated with this
`soil. Neither the Othello Silt Loam nor Urban Land are considered Prime Farmlands,
`Farmlands of Statewide Importance, or hydric soils. Because the Project area is an
`industrial area that has been completely graveled or paved, no Project-related adverse
`impacts to soils are expected to occur. Adelphia would minimize or avoid impacts on
`soil during construction by adhering with the FERC’s Plan, as applicable.
`
`
`Based on the limited scope of the Project and because Adelphia would minimize
`or avoid impacts on soil during construction by adhering with the FERC’s Plan and
`Procedures, we conclude that the Project would not have a significant impact on soils.
`
`Land Use
`
`The Project area is located entirely on industrial use land, including Project access
`
`roads, associated ancillary facilities, and parking areas. The Project would be entirely
`located within the certificated MHCS’s paved/graveled LOD, and the fourth unit would
`be housed within the certificated compressor building. The industrial use category
`describes paved, graveled, or maintained areas with little to no vegetation. The MHCS
`was certificated for 7.5 acres of operational impacts, and this Project would use 4.3 acres
`within that 7.5 acres. No expansion of the existing fence line or additional temporary
`workspace is proposed as part of the Project.
`
`Residences and Special land Uses
`
`One public recreational area, Analine Village Park, is located 0.1 mile from the
`
`Project. In addition, the Lawncroft Cemetery is located 0.1 mile north of the Project.
`Potential Project-related impacts to Analine Village Park and Lawncroft Cemetery would
`be limited to those associated with traffic. However, Adelphia does not anticipate any
`traffic impacts to Analine Village, because the only road that accesses the park would not
`be used or affected by the Project. However, there may be some temporary traffic
`impacts to Lawncroft Cemetery during construction of this Project that would coincide
`
`
`
`7
`
`

`

`
`
`
`
`with construction of the Adelphia Gateway Project. No temporary or permanent
`restrictions on land use to either area would occur as part of the Project. Adelphia made
`an agreement with Lawncroft Cemetery to maintain unrestricted access to the Cemetery’s
`entry and exit points during construction and operations of the Adelphia Gateway Project
`and would also honor this agreement during all phases of this Project.
`
`There is a residential area to the northwest and west of the Project, and the areas to
`
`the east and south consist of industrial and commercial properties. There are a total of 27
`residences and 4 non-residential buildings within 100 feet of the Project, all of which are
`included in the existing outreach plan in place for the Adelphia Gateway Project, and will
`continue to receive the appropriate notifications of construction activities. Adelphia is
`committed to minimize disruption to traffic flow to the greatest extent possible and
`maintain access to these residences at all time. No residences are within 50 feet of the
`edge of the Project’s LOD. Because Project construction would take place concurrently
`with construction of the Adelphia Gateway Project, Adelphia would implement
`applicable measures in its Residential and Traffic Management Plan for the Adelphia
`Gateway Project to avoid and/or mitigate adverse Project-related impacts on nearby
`landowners and traffic.3 The Air/Noise Section of this Environmental Assessment
`Report discusses measures Adelphia would implement to minimize fugitive dust
`emissions and noise levels.
`
`The Project would be located within the Delaware Estuary Coastal Zone. In
`
`accordance with the Federal Coastal Zone Management Act, Adelphia submitted a
`federal consistency determination to the Pennsylvania Department of Environmental
`Protection Coastal Resources Management Program for the Project on the date this
`application was filed. Adelphia would obtain all required permits or authorizations prior
`to initiating Project construction.
`
`Therefore, based on the above information, we conclude the Project would have a
`
`minimal impact on residences and special land uses.
`Contaminated Sites
`
`According to the U.S. Environmental Protection Agency’s (USEPA) Cleanups in
`
`My Community website, there are no Resource Conservation and Recovery Act
`Corrective Action Sites that occur within 250 feet of the Project. Adelphia’s January 15,
`2021 data response indicates that based on a review of the USEPA’s Cleanups in My
`Community website and the Pennsylvania Environmental Facility Application
`Compliance Tracking System (eFACTS), the following landfills or hazardous waste sites
`are located within 0.25 mile from the Project’s LOD that may affect soil and groundwater
`media: Chemtrade Solutions, LLC (Formerly General Chemical Corporation), (0.25 mile
`
`3 Adelphia’s Residential and Traffic Management Plan for the Adelphia Gateway Project is on
`the FERC docket at accession number 20201001-5029.
`
`
`
`8
`
`

`

`
`
`
`
`South); Honeywell International, Inc., ( 0.25 mile South); Lawncroft Cemetery, (0.25 mile
`Northeast); and Allied Chem DDT Disposal (0.1 mile Southeast).
`
`Adelphia indicates that Project-related excavation activities would be minimal and
`
`limited to a small area in the Project site. In addition, Adelphia would adhere to its Soil,
`Groundwater, and Drilling Fluid Management Plan and its Unanticipated Discovery of
`Contamination Plan submitted for the Adelphia Gateway Project during construction of
`this Project. Therefore, Adelphia does not anticipate any of the above-listed sites to be
`impacted by the proposed Project, and no associated Project mitigation or
`permits/approvals/consultations would be required.
`
`Adelphia conducted a phase one environmental site assessment for the MHCS as
`
`part of its purchase of the property for the Adelphia Gateway Project. Five Historical
`Recognized Environmental Conditions (HRECs) were identified during the assessment.
`No Recognized Environmental Conditions or Controlled Recognized Environmental
`Conditions were identified. Contaminated soils are not expected to be encountered
`during construction of the MHCS. If any contaminated soils are encountered, they would
`be disposed of during construction of the Adelphia Gateway Project. Therefore, no
`contaminated soils, sediments, or groundwater are expected at the MHCS. If during
`construction, contaminated soils are encountered Adelphia would follow the procedures
`in its Unanticipated Discovery of Contamination Plan for the Adelphia Gateway Project.4
`Therefore, we conclude the Project would have a minimal impact on contaminated soils,
`sediments or groundwater.
`
`Visual Resources
`
`
`The Project would not have a significant effect on visual resources in the area.
`Construction would be visible to the residences located to the northwest and from
`commuters using Ridge Road. However, the Project operationally would not
`significantly affect visual resources in the area as the major facilities and equipment
`would be located within the compressor building. Equipment not installed in the
`building would be in-kind with equipment being installed on the site as part of the
`Adelphia Gateway Project and would not change the visual character of the Project site.
`Therefore, we conclude the Project would have a minimal impact on visual impacts.
`
`
`
`
`
`
`
`
`4 Adelphia’s Unanticipated Discovery of Contamination Plan for the Adelphia Gateway Project
`is on the FERC docket at accession number 20200814-5282.
`
`
`
`9
`
`

`

`
`
`
`
`Air Quality/Noise
`
`Air Quality
`
`
`Construction of the Project would cause a temporary reduction in local ambient air
`quality due to fugitive dust and emissions generated by construction equipment. This
`impact would occur only in the immediate vicinity of the construction activities.
`Construction emissions would be temporary in nature and limited to various construction
`activities and equipment occurring over a four to six month period. Federal and state air
`quality standards are designed to protect human health. The USEPA has developed
`National Ambient Air Quality Standards (NAAQS) for criteria air pollutants such as
`oxides of nitrogen (NOx) and carbon monoxide (CO), sulfur dioxide (SO2), and inhalable
`particulate matter (PM2.5 and PM10). PM2.5 includes particles with an aerodynamic
`diameter less than or equal to 2.5 micrometers, and PM10 includes particles with an
`aerodynamic diameter less than or equal to 10 micrometers. The NAAQS were set at
`levels the EPA believes are necessary to protect human health and welfare. Volatile
`organic compounds (VOC) are regulated by USEPA mostly to prevent the formation of
`ozone (O3), a constituent of photochemical smog. Many VOCs form ground-level ozone
`by reacting with sources of oxygen molecules such as NOx in the atmosphere in the
`presence of sunlight. NOx and VOCs are referred to as ozone precursors. Hazardous air
`pollutants (HAP) are also emitted during fossil fuel combustion and are suspected or
`known to cause cancer or other serious health effects; such as reproductive effects or
`birth defects; or adverse environmental effects.
`
`Pennsylvania is in the Ozone Transport Region, a group of states in the
`northeastern United States classified as moderate nonattainment for ozone that are
`required to install a certain level of controls for the pollutants that form ozone. The
`Project is in Delaware County, Pennsylvania, which is part of the Metropolitan
`Philadelphia Interstate Air Quality Control Region (AQCR), and is listed as attainment
`for all criteria pollutants, with the exception of being designated as nonattainment for
`2015 and 2008 O3, and maintenance for 1997, 2006 and 2012 PM 2.5.
`
`Greenhouse Gases (GHG) produced by fossil-fuel combustion are carbon dioxide
`
`(CO2), methane (CH4), and nitrous oxide (N2O). GHGs status as a pollutant is not related
`to toxicity. GHGs are non-toxic and non-hazardous at normal ambient concentrations,
`and there are no applicable ambient standards or emission limits for GHG under the
`Clean Air Act. GHGs emissions due to human activity are the primary cause of increased
`atmospheric concentration of GHGs since the industrial age. These elevated levels of
`GHGs are the primary cause of warming of the climatic system. These existing and
`future emissions of GHGs, unless significantly curtailed, will cause further warming and
`changes to the local, regional and global environmental resources. During construction
`of the project, these GHGs would be emitted from construction equipment. The project
`entails installation of a new electric driven compressor unit; no operational emissions
`
`
`
`10
`
`

`

`
`
`
`
`would be realized from the Project, other than minor fugitive emissions. Emissions of
`GHGs are typically expressed in terms of CO2 equivalents (CO2e).5
`
`
`Fugitive dust is particulate matter that arises from the mechanical disturbance of
`soil or rock material and is lifted into the air. It typically is comprised of particles of
`various sizes. Fugitive dust results from activities such as the physical movement of soil,
`vehicles traveling over unpaved surfaces, heavy equipment operation, blasting, and wind.
`Fugitive dust typically contains a mix of particle sizes (PM2.5, PM10 and larger
`particulates). Smaller particulates can be health hazards while larger particulates may be
`a public nuisance (visibility impacts, deposition, and physical irritant).
`
`
`As mentioned earlier, to mitigate fugitive dust and exhaust emissions during
`construction, Adelphia would implement dust control measures outlined in Adelphia’s
`existing Fugitive Dust Emissions Control Plan for the Adelphia Gateway Project 6,
`including watering roadways, removing debris from paved surfaces, as well as ensuring
`proper maintenance of equipment, and compliance with federal, state, and local
`regulations for exhaust emissions from construction equipment. These temporary
`impacts would occur only in the immediate vicinity of the construction activities. Once
`completed, fugitive dust and emissions would subside. The estimated construction
`emissions in tons per year (tpy) for the project construction are presented in table 1
`below.
`
`
`
`
`
`
`Table 1
`Estimated Construction Emissions
`VOC HAP CO2e
`PM10 PM2.5 NOX
`CO
`SO2
`Emission Source
`0.03
`0.06
`2,948
`0.25 0.24
`3.40
`1.23
`0.02
`Construction Equipment Exhaust
`0.02
`0.01
`168
`0.01 0.01
`0.22
`0.40
`0.01
`On-Road Vehicle Traffic
`--
`--
`--
`14.29 1.43
`--
`--
`--
`Off-Road Vehicle Traffic
`--
`--
`--
`0.01 0.01
`--
`--
`--
`Earthmoving Fugitives
`--
`--
`--
`1.53 0.15
`--
`--
`--
`Construction Activity – Fugitives
`--
`--
`--
`0.03 0.01
`--
`--
`--
`Pile Erosion
`0.05
`0.07
`3,116
`16.12 1.85
`3.62
`1.63
`0.03
`Total
`25
`NA
`NA
`NA
`100
`25
`NA
`100
`General Conformity Rule De Minimis
`General Conformity de minimus thresholds only apply to nonattainment/maintenance pollutants, which include O3 , with precursors of NOx and
`VOCs; and PM2.5, with precursors of SO2 NOx, ammonia and VOCs. Delaware County is nonattainment for O3 and maintenance for PM 2.5
`
`
`There would be no operational emissions from the new electric driven compressor
`unit, but small quantities of emissions would result from piping component fugitives,
`valves, and natural gas venting operations for maintenance purposes. These would be
`considered negligible and are presented in table 2.
`
`5 Other GHG gases are converted to CO2e by means of the global warming potential of each gas.
`6 Accession number 20200612-5119
`
`
`
`11
`
`

`

`
`
`
`
`
`
`Table 2
`Operational Emissions (tpy)
`
`
`Pollutant
`
`Post-Project Potential
`to Emit
`(tpy)
`
`Project
`Current
`Potential to
`Potential to
`Emit
`Emit
`(tpy)
`(tpy)
`1.9
`NA
`1.9
`PM10
`1.9
`NA
`1.9
`PM2.5
`0.1
`NA
`0.1
`SO2
`10.8
`NA
`10.8
`CO
`17.1
`NA
`17.1
`NOx
`23.7
`1.2
`22.5
`VOC
`41,463
` 407
`41,056
`CO2e
`a. PSD = Prevention of Significant Deterioration permitting program
`b. NSR = New Source Review permitting
`
`
`Major Source
`Threshold (tpy)
`
`Major Source
`Program
`
`Subject to Major
`Source
`Permitting
`
`250
`250
`250
`250
`25
`25
`NA
`
`PSDa
`PSD
`PSD
`PSD
`NSRb
`NSR
`PSD
`
`No
`No
`No
`No
`No
`No
`No
`
`
`
`Based on the short duration of construction activities and minor operational
`fugitive emissions, we conclude that there would not be significant impacts on air quality
`due to the Project.
`
`Noise
`
`
`Adelphia previously identified three residential Noise Sensitive Areas (NSAs)
`surrounding the MHCS during noise surveys conducted on December 12, 2017 as part of
`the Adelphia Gateway Project to characterize the existing ambient sound quality. Since
`the time of the survey, no new NSA’s have been constructed and the noise environment
`remains similar to the time of the initial survey.
`
`Short term, temporary noise impacts associated with construction activities, would
`primarily result from the use of heavy construction equipment and machinery. Noise
`levels would vary throughout construction depending on the phase of work. Typically,
`the most prevalent sound source during construction would be the internal combustion
`engines used to power the construction equipment. Noise levels of major construction
`equipment including cranes, rollers, and trucks have a measured sound level of 85
`decibels (dBA) at 50 feet from the source, diminishing with distance. To mitigate these
`short-term impacts, Adelphia would restrict construction to daytime hours, six days a
`week, and maintain vehicles and equipment in accordance with manufacturers’
`recommendations.
`
`
`
`
`12
`
`

`

`
`
`
`
`Operational noise levels are presented in table 3. The closest NSA is
`approximately 530 feet from the proposed unit. The noise model developed for the
`MHCS as part of the Adelphia Gateway Project was updated to incorporate the additional
`equipment to be installed as part of the Project using the most recent site plans for the
`MHCS. Considering the current environment and lack of construction in the area since
`the completion of the initial noise survey, those conclusions reached are not impacted by
`the Project’s modifications.
`
`
`Estimated Total
`Ldn (dBA)
`
`66.1
`66.1
`63.2
`
`Predicted Change
`from Existing
`Ambient Ldn
`(dBA)
`+0.3
`+0.3
`+0.0
`
`NSA-1a
`NSA-1b
`NSA-2
`
`Due to the temporary nature of construction activities and that construction of the
`project would be limited to daytime hours, we believe that construction of the Project
`would not have a significant impact on noise quality in the Project area. Based on the
`minimal projected increase in operational noise from the approved MHCS, and as
`Adelphia would be required to file a full load noise survey within 60 days of the placing
`the MHCS in-service as part of their Adelphia Gateway Project requirements, we
`conclude that operation of the Project would not have a significant impact on noise
`quality in the project area.
`
`Staff’s Conclusion
`
`Based on the above environmental analysis, the staff has determined that approval
`
`of th

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket