throbber
Case: 24-6696, 11/04/2024, DktEntry: 4.3, Page 1 of 43
`
`ATTACHMENT B
`
`

`

`Document Accession #:
`
`Case: 24-6696, 11/04/2024, DktEnt/1 4.3, Page 2 of 43
`Filed Date: 06 07/2024
`20240607-3056
`
`187 FERC 'I 61,146
`UNITED STATES OF AMERICA
`FEDERAL ENERGY REGULATORY COMMISSION
`
`Before Commissioners: Willie L. Phillips, Chairman,
`Allison Clements and Mark C. Christie.
`
`Public Utilities Commission of the State of California
`
`Docket Nos. EL02-60-016
`
`v.
`
`Sellers of Long-Term Contracts to the California
`Department of Water Resources
`
`California Electricity Oversight Board
`
`v.
`
`EL02-62-015
`
`(consolidated)
`
`Sellers of Long-Terrn Contracts to the California
`Department of Water Resources
`
`ORDER ADDRESSING ARGUMENTS RAISED ON REHEARING
`AND SETTING ASIDE PRIOR ORDER, IN PART
`
`(Issued June 7, 2024)
`
`On January 19, 2024, Shell Energy North America (US), L.P. (Shell)1 and the
`1.
`California Parties2 submitted a request for rehearing of the Commission's December 20,
`2023 order addressing the California Parties' challenges to two Western Energy Crisis-
`era long-term contracts between the California Department of Water Resources (CDWR)
`
`1 Shell was known during the relevant time period as Coral Power, L.L.C.
`
`2 The California Energy Oversight Board (CEOB) was defunded in 2008, at which
`time the Attorney General of California was granted authority to pursue claims relating to
`the Western Energy Crisis in its stead. See Cal. Pub. Util. Code § 343 (2022). Later, the
`Public Utilities Commission of the State of California (CPUC) and the Attorney General
`of California were joined by Pacific Gas and Electric Company and Southern California
`Edison Company to pursue the original claims and present witnesses and evidence during
`much of these proceedings. As such, this order will refer to both sets of complainants
`jointly as the California Parties.
`
`

`

`Document Accession #:
`
`Case: 24-6696, 11/04/2024, DktEnt/1 4.3, Page 3 of 43
`Filed Date: 06 07/2024
`20240607-3056
`
`Docket Nos. EL02-60-016 and EL02-62-015
`
`2
`
`and, respectively, Shell (Shell Contract) and Iberdrola Renewables, LLC (lberdrola
`Contract).3
`
`Pursuant to Allegheny Defense Project v. FERC,4 the rehearing requests filed in
`2.
`this proceeding may be deemed denied by operation of law. However, as permitted by
`section 313(a) of the Federal Power Act (FPA),5 we are modifying the discussion in the
`June 2021 Order and setting aside the order, in part, as discussed below.6
`
`I.
`
`Background
`
`A.
`
`Origins of This Proceeding
`
`A brief summary of the recent history in these proceedings, as it is relevant to this
`3.
`order, is provided here. A comprehensive history of the background and procedural
`history of this case can be found in other judicial opinions and Commission orders.7
`
`On February 25, 2002, the CPUC and the now-defunct CEOB each filed separate
`4.
`complaints pursuant to section 206 of the FPA8 to abrogate the Shell and Iberdrola
`Contracts as unjust and unreasonable or reform the contracts to provide for just and
`reasonable rates, reduce their duration, and strike certain nonprice terms and conditions
`from the contracts." Complainants further alleged that Respondents exercised market
`power that forced CDWR to pay unjust and unreasonable prices and agree to onerous,
`unjust and unreasonable nonprice terms to secure the power necessary to ensure the lights
`
`3 Pub. Utils. Comm 'n ofCal. v. Sellers of Long-Term Contracts to the Cal. Dep 'Z
`of Water Res., 185 FERC 1161,197 (2023) (Opinion No. 587).
`
`4 964 F.3d 1 (D.C. Cir. 2020) (en bane).
`
`5 16 U.S.C. § 825l(a) ("Until the record in a proceeding shall have been filed in a
`court of appeals, as provided in subsection (b), the Commission may at any time, upon
`reasonable notice and in such manner as it shall deem proper, modify or set aside, in
`whole or in part, any finding or order made or issued by it under the provisions of this
`chapter.").
`
`6 Allegheny Def Project, 964 F.3d at 16-17.
`
`7 See, et., Pub. Utils. Comm 'n ofCal. v. FERC, 462 F.3d 1027 (9th Cir. 2006).
`
`8 16 U.S.C. § 824e.
`
`9 Pub. Utils. Comm 'n ofCal. v. Sellers of Long-Term Contracts to the Cal. Dep 't
`of Water Res., 99 FERC 'I 61,087, at 61,377 (2002) (April 25, 2002 Order).
`
`

`

`Document Accession #:
`
`Case: 24-6696, 11/04/2024, DktEnt/1 4.3, Page 4 of 43
`Filed Date: 06 07/2024
`20240607-3056
`
`Docket Nos. EL02-60-016 and EL02-62-015
`
`3
`
`stayed on in Caiif0tnia1" In the April 25, 2002 Order, the Commission set the contracts
`at issue, including the Shell Contract, for hearing.11 Following hearing, the Commission
`affirmed the Administrative Law Judge's partial initial decision and found that (1) the
`applicable standard of review for the contracts was the Mobile-Sierra presumption of just
`and reasonable bilateral contract rates," and (2) CPUC and CEOB had not met their
`burden of proof to justify abrogating or modifying the contracts at issue, thereby
`dismissing Complainants' claims." The Commission then denied rehearing," and CPUC
`and CEOB appealed.
`
`In 2008, the Supreme Court issued the Morgan Stanley15 decision, which refined
`5.
`the application of the Mobile-Sierra presumption, holding that rates set through an arm's-
`length bilateral contract between sophisticated parties with equal bargaining power are
`presumed to be just and reasonable, unless there is unfair dealing by either of the parties
`at the contract formation stage or the contract seriously harms the public interest.16
`Specifically, the Supreme Court held that the Mobile-Sierra presumption could be
`avoided "where there is unfair dealing at the contract formation stage-for instance, if
`[the Commission] finds traditional grounds for the abrogation of the contract such as
`fraud or duress.9017 Other examples of "unfair dealing at the contract formation stage"
`could include "if the 'dysfunctional' market conditions under which the contract was
`
`10 Id. at 61377, 61583, app. A.
`
`11 Id. at 61,383-84.
`
`12 The Mobile-Sierra presumption takes its name from two cases decided by the
`Supreme Court of the United States (Supreme Court) on the same day: United Gas Pipe
`Line Co. v. Mobile Gas Serv. Corp., 350 U.S. 332 (1956) (Mobile) and Fed. Power
`Comm 'n v. Sierra Pac. Power Co., 350 U.S. 348 (1956) (Sierra).
`
`13 Pub. Utils. Comm 'n ofCal. v. Sellers of Long-Term Contracts to the Cal. Dep 'Z
`of Water Res., 103 FERC 1] 61,354, at P 3 (2003).
`
`14 Pub. Utils. Comm 'n ofCal. v. Sellers of Long-Term Contracts to the Cal. Dep 'Z
`of Water Res., 105 FERC 1] 61,182 (2003).
`
`15 Morgan Stanley Cap. Grp. Inc. v. Pub. Util. Dist. No. I of Snonomisn Cnty.,
`Wash., 554 U.S. 527 (2008) (Morgan Stanley).
`
`16 Id. at 547-55.
`
`17 Id. at 547.
`
`

`

`Document Accession #:
`
`Case: 24-6696, 11/04/2024, DktEnt/1 4.3, Page 5 of 43
`Filed Date: 06 07/2024
`20240607-3056
`
`Docket Nos. EL02-60-016 and EL02-62-015
`
`4
`
`formed were caused by illegal action of one of the parties ...."18 The Supreme Court
`reasoned that "[l]ike fraud and duress, unlawful market activity that directly affects
`contract negotiations eliminates the premise on which the Mobile-Sierra presumption
`rests: that the contract rates are the product of fair, [arm's-length] negotiations.,19
`However, the Supreme Court also emphasized that "the mere fact of a party's engaging in
`unlawful activity in the spot market does not deprive its forward contracts of the benefit
`of the Mobile-Sierra presumption. There is no reason why [the Commission] should be
`able to abrogate a contract on these grounds without finding a causal connection between
`the unlawful activity and the contract rate.,,20
`
`In light of the Supreme Court's decision, the United States Court of Appeals for
`6.
`the Ninth Circuit (Ninth Circuit) remanded the case to the Commission for proceedings
`consistent with the Supreme Court's opinion." On remand, the Commission ordered a
`trial-type, evidentiary hearing to supplement the existing record, in light of the Morgan
`Stanley decision." As relevant to this rehearing, the Commission reopened the record to
`allow parties to present evidence on whether the Mobile-Sierra presumption was avoided
`with respect to the implicated contracts." The Commission instructed that "if it is clear
`that one party to a contract engaged in such extensive unlawful market manipulation as to
`alter the playing field for contract negotiations, the Commission should not presume that
`the contract is just and reasonable.,,24 The Commission emphasized that the
`
`18 Id.
`
`19 Id.
`
`20 Id. at 554-55. The Supreme Court held that where the Mobile-Sierra
`presumption does attach to a contract, it may still be overcome in the traditional sense
`upon a showing that "[t]he contract rate ... seriously harm[s] the public interest.972° Id.
`at 548.
`
`21 Pub. Uzil. Dist. No. I of Snohomish Cry., Wash. v. FERC, 547 F.3d 1081 (9th
`Cir. 2008).
`
`22 Pub. Utils. Comm 'n ofCal. v. Sellers of Long-Term Contracts to the Cal. Dep 'Z
`of Water Res., 149 FERC 1] 61,127, at P 1 (2014).
`
`23 Id. PP 19, 20, 23 .
`
`24 Id. P 17 (quoting Morgan Stanley, 554 U.S. at 554) (internal quotations
`omitted).
`
`

`

`Document Accession #:
`
`Case: 24-6696, 11/04/2024, DktEnt/1 4.3, Page 6 of 43
`Filed Date: 06 07/2024
`20240607-3056
`
`Docket Nos. EL02-60-016 and EL02-62-015
`
`5
`
`Complainants must demonstrate a causal connection between any unlawful activity and
`the contract negotiations in order to find that the Mobile-Sierra presumption is avoided."
`
`B.
`
`2016 Initial Decision
`
`On April 12, 2016, the Presiding Judge issued the 2016 Initial Decision in this
`7.
`proceeding, which found, as relevant here, that the Mobile-Sierra presumption of justness
`and reasonableness was avoided as to the Shell Contract." The 2016 Initial Decision
`concluded that Shell committed unlawful activities in the spot market that possessed the
`requisite price effects." However, after concluding that the spot-market price effects had
`an upward influence on the forward-market pricing,28 the Initial Decision stated that
`Complainants did not demonstrate that forward prices influenced the Shell Contract
`negotiations." Thus, the 2016 Initial Decision concluded that Shell's unlawful market
`activity in the spot market did not have a direct effect on the contract negotiations and
`thus determined that the Mobile-Sierra presumption was not avoided on these grounds.3°
`The 2016 Initial Decision also considered and rejected several other theories, such as the
`exercise of market power31 and gas market manipulation" that could potentially avoid
`application of the Mobile-Sierra presumption to the Shell Contract.
`
`Upon consideration of traditional grounds for contract abrogation, the 2016 Initial
`8.
`Decision found that under the laws of California, which is the governing law under the
`Shell Contract, the torts of bad faith, duress, unconscionability, and fraud may serve as
`grounds for abrogating a bilateral power contract, but found that the California Parties
`
`25 Id. P 25.
`
`26 Pub. Utils. Comm 'n ofCal. v. Sellers of Long-Term Contracts to the Cal. Dep 'Z
`of Water Res., 155 FERC 1163,004, at PP 1, 244, 356, 381, 386, 389, 390 (2016) (2016
`Initial Decision).
`
`27 Id. P 130.
`
`28 Id. P 176.
`
`29MP198.
`
`30 Id. P 197.
`
`31 Id. P 207.
`
`32Id. P 213.
`
`

`

`Document Accession #:
`
`Case: 24-6696, 11/04/2024, DktEnt/1 4.3, Page 7 of 43
`Filed Date: 06 07/2024
`20240607-3056
`
`Docket Nos. EL02-60-016 and EL02-62-015
`
`6
`
`failed to carry their burden in establishing any of these theories.33 Nevertheless, the 2016
`Initial Decision sum sponge considered the theories of both fraud-in-the-inducement and
`fraud-in-the-inception as alternative bases for avoiding Mobile-Sierra. The 2016 Initial
`Decision described fraud-in-the-inducement to a contract as :
`
`where the promiser knows what he is signing but his consent is induced by
`fraud, mutual assent is present and a contract is formed, which, by reason of
`the fraud, is voidable. In order to escape from its obligations the aggrieved
`party must rescind, by prompt notice and offer to restore the consideration
`received, if any.34
`
`The 2016 Initial Decision dismissed this theory, in part, because neither party rescinded
`the Shell Contract and because the contract had been carried out in full.
`
`However, the 2016 Initial Decision distinguished fraud-in-the-inducement from
`9.
`fraud-in-the-inception of a contract, which is where :
`
`the fraud goes to the inception or execution of the agreement, so that the
`promiser is deceived as to the nature of his act, and actually does not know
`what he is signing, or does not intend to enter into a contract at all, mutual
`assent is lacking, and it is void. In such a case it may be disregarded
`without the necessity of rescission.35
`
`The 2016 Initial Decision concluded that the California Parties established fraud-in-the-
`inception by demonstrating that Shell falsely claimed it was being forced to purchase
`power for CDWR beginning in April 2001 "at a loss.>=36
`c.
`
`2021 Limited Remand
`
`In an order issued on June 17, 2021,37 the Commission remanded the issue of
`10.
`fraud (including fraud-in-the-inception, fraud-in-the-inducement, and more general fraud
`theories) to the Presiding Judge for full briefing (Limited Remand Proceeding). The
`
`33 Id. P 214 (citing Morgan Stanley, 554 U.s. at 557).
`
`34 Id. at P 217 (emphasis in original).
`
`35 Id (emphasis in original).
`
`36 Id. PP 227-244.
`
`37 Pub. Utils. Comm 'n ofCal. v. Sellers of Long-Term Contracts to the Cal. Dep 'Z
`of Water Res., 175 FERC 1161 ,233 (2021) (Limited Remand Order).
`
`

`

`Document Accession #:
`
`Case: 24-6696, 11/04/2024, DktEnt/1 4.3, Page 8 of 43
`Filed Date: 06 07/2024
`20240607-3056
`
`Docket Nos. EL02-60-016 and EL02-62-015
`
`7
`
`Commission found that the Presiding Judge erred by raising the fraud-in-the-inception
`theory sum sponge in the 2016 Initial Decision as a basis for finding that the Mobile-Sierra
`presumption is avoided with regard to the Shell Contract. The Commission found that
`the Presiding Judge's finding raised due process concerns because the requirements of the
`Administrative Procedure Act ensure that parties will be given the opportunity to present
`rebuttal evidence on all matters decided at the hearing.38
`
`Despite these due process concerns, the Commission found potential merit to the
`11.
`argument that Shell's electric spot market activity could have contributed to inherent
`unfairness that tainted negotiation of the Shell Contract. Specifically, the Limited
`Remand Order highlighted Shell's claims of losses on the April/May 2001 sales to
`CDWR and the need to be made whole as potentially fraudulent." Given the potential
`merit of the argument that fraudulent conduct by Shell may form the basis for avoiding
`the application of Mobile-Sierra, the Commission found that full briefing on this issue
`was warranted before the Commission could fully consider the 2016 Initial Decision's
`findings. Thus, the Commission remanded this limited issue to the Presiding Judge to
`undertake additional fact-finding and issue a revised partial initial decision, consistent
`with the direction provided in the Limited Remand Order."
`
`The Commission explained that, although the California Parties still had the
`12.
`burden to plead and prove their allegations of fraud with specificity, the use of traditional
`grounds of contract abrogation, such as fraud, for the purpose of avoiding Mobile-Sierra
`is distinguishable from using such a claim to abrogate a contract under state law.
`Specifically, the Commission stated that it did not interpret Morgan Stanley as requiring a
`demonstration of unlawful activity that would independently satisfy all the elements of
`wrongdoing under a state or federal statute. Instead, consistent with its precedent in the
`Opinion No. 537 line of cases,41 the Commission stated that it would look to state law as
`a guide to determine whether the type of behavior in question resulted in unfair dealing at
`the contract formation stage such that the contract was not the result of legitimate arm's-
`
`38 Id. P 22.
`
`39 Id. P 24.
`
`40 Id. P 25. The Commission noted that all other issues in the 2016 Initial
`Decision remained pending before the Commission. Id. P 29.
`
`41 See, e.g., Puget Sound Energy, Inc. v. All Jurisdictional Sellers of Energy &
`Capacity at Wholesale into Elec. Energy and Capacity Mkts. In the Pae. No, 151 FERC
`ii 61,173 (2015) (Opinion No. 537), order denying ren 'g, 153 FERC 1161,386 (2015)
`(Opinion No. 537-A), Puget Sound Energy, Inc. v. All Jurisdictional Sellers of Energy &
`Capacity at Wholesale into Elec. Energy and Mkts. In the Pac. No , 157 FERC 1161,026
`(2016) (Opinion No. 552).
`
`

`

`Document Accession #:
`
`Case: 24-6696, 11/04/2024, DktEnt/1 4.3, Page 9 of 43
`Filed Date: 06 07/2024
`20240607-3056
`
`Docket Nos. EL02-60-016 and EL02-62-015
`
`8
`
`length negotiations. The Commission also emphasized that, while parties would be
`permitted to present any relevant evidence to support or rebut claims that fraud tainted
`negotiation of the Shell Contract, they would not be permitted to re-litigate any other
`issue in this proceeding, such as the question of whether evidence of Shell's fraud-in-the-
`inception of the Shell Contract also compels a finding that bad faith, unconscionability,
`or duress altered the playing field for negotiation of the Shell Contract."
`
`13. On July 13, 2021, Shell filed a request for rehearing of the Limited Remand Order.
`On August 13, 2021, the Commission issued a notice denying Shell's rehearing request
`by operation of law. On September 22, 2021, Shell filed a petition for review of the
`Limited Remand Order and Notice of Denial of Rehearing by Operation of Law.
`
`During the course of the Limited Remand Proceeding, Shell filed two
`14.
`interlocutory appeals with the Commission to request reconsideration of rulings by the
`Presiding Judge that (1) prohibited Shell from presenting new expert testimony regarding
`the causes of the Western Energy Crisis, and (2) establishing a page limit for post-hearing
`briefs. In both cases, the Commission issued notices of no determination on the
`interlocutory appeals.43
`
`D.
`
`Revised Partial Initial Decision
`
`In the Revised Partial Initial Decision, issued on June 23, 2022, the Presiding
`15.
`Judge found that the Mobile-Sierra presumption of the justness and reasonableness of the
`Shell Contract should be avoided because Shell committed fraud that directly affected
`contract negotiations.44
`
`The Revised Partial Initial Decision stated that, consistent with Morgan Stanley
`16.
`and the Limited Remand Order, the California Parties need not demonstrate fraud per se
`during contract negotiations to avoid application of Mobile-Sierra but need only
`demonstrate that Shell's fraudulent activity resulted in unfair dealing between the parties
`during the contract formation stage. The Revised Partial Initial Decision stated that it
`would look to state law as a guide to determine whether the type of behavior in question
`resulted in unfair dealing at the contract formation stage, but would not require a
`demonstration of unlawful activity that would independently satisfy all the elements of
`
`42 Limited Remand Order, 175 FERC 1] 61,233 at PP 26-29.
`
`43 Opinion No. 587, 185 FERC 1161,197 at PP 429-430.
`
`44 Pub. Utils. Comm 'n ofCal. v. Sellers of Long-Term Contracts to the Cal. Dep 'Z
`of Water Res., 179 FERC 1163,026, at P 1 (2022) (Revised Partial Initial Decision).
`
`

`

`Case: 24-6696, 11/04/2024, DktEntry: 4.3, Page 10 of 43
`Filed Date: 06/07/2024
`Document Accession #: 20240607-3056
`
`Docket Nos. EL02-60-016 and EL02-62-015
`
`9
`
`wrongdoing under a state or federal statute.45 Therefore, the Revised Partial Initial
`Decision concluded that the California Parties would not have to show the five elements
`of common law fraud46 in order to prevail in avoiding the Mobile-Sierra presumption."
`
`The Presiding Judge applied section 1572 of the California Civil Code,48 which
`17.
`defines "Actual Fraud" under California law, as a guide for evaluating the arguments and
`evidence. Under section 1572, actual fraud can be committed by any of the following
`actions, including:
`
`1. The suggestion, as a fact, of that which is not true, by one who does not
`believe it to be true, 2. The positive assertion, in a manner not warranted by
`the information of the person making it, of that which is not true, though he
`believes it to be true, 3. The suppression of that which is true, by one
`having knowledge or belief of the fact, 4. A promise made without any
`intention of performing it, or, 5. Any other act fitted to deceive."
`
`Based on this framework, the Revised Partial Initial Decision found that Shell's
`18.
`negotiating tactics satisfied several elements of section 1572. Thus, the Revised Partial
`Initial Decision concluded that Shell's unlawful manipulation of the electric markets
`constituted a form of fraud that directly affected negotiation of the Shell Contract.5° The
`Revised Partial Initial Decision noted that the 2016 Initial Decision rejected a theory of
`causation based on forward prices, finding that forward contract prices influenced Shell's
`view of the contract but did not affect CDWR's.51 However, the Revised Partial Initial
`Decision reaffirmed the 2016 Initial Decision's finding of causal effect in Shell's
`manipulation of spot prices. Specifically, the Revised Partial Initial Decision referenced
`
`4514. PP 115-116.
`
`46 The five elements of common law fraud in California are: (1) a
`misrepresentation or omission of material fact, (2) knowledge of falsity (or scienter), (3)
`intent to defraud or induce reliance, (4) justifiable reliance, and (5) resulting damages.
`See, e.g., id. P 174 (noting that all parties agree on the five elements of common law
`fraud under California law).
`
`47 Id. PP 174-180.
`
`48 Id. P 124 (citing Cal. civil Code § 1572 (West 2016);
`
`49 Id.
`
`5014. PP 118-124.
`
`5114. PP 134-135.
`
`

`

`Case: 24-6696, 11/04/2024, DktEntry: 4.3, Page 11 of 43
`Filed Date: 06/07/2024
`Document Accession #: 20240607-3056
`
`Docket Nos. EL02-60-016 and EL02-62-015
`
`10
`
`the 2016 Initial Decision's finding that Shell's purported losses, which it used to insist on
`a higher long-term contract price, stemmed directly from the inflated spot market price
`levels that Shell's own traders had a hand in influencing through manipulative
`strategies."
`
`The Revised Partial Initial Decision concluded that the doctrine of fraud-in-the-
`19.
`inducement does not fit these facts. The Revised Partial Initial Decision found that,
`because Shell's deception of CDWR rendered CDWR unaware of Shell's market
`manipulation when it entered the contract, there could be no mutual assent between the
`parties. However, the Revised Partial Initial Decision found that there was no recission
`of the Shell Contract by CDWR and, therefore, no fraud-in-the-inducement.53
`
`Finally, the Revised Partial Initial Decision concluded that Shell's conduct
`20.
`constitutes fraud-in-the-inception and, as such, the Mobile-Sierra presumption is
`avoided.54
`
`E.
`
`Opinion No. 587
`
`In Opinion No. 587, the Commission affirmed the Revised Partial Initial
`21.
`Decision's finding that Mobile-Sierra is avoided because Shell engaged in fraud that
`directly affected negotiation of the Shell Contract, but declined to adopt the Presiding
`Judge's reasoning and instead provided an alternative analysis.55
`
`The Commission first affirmed the Revised Partial Initial Decision's finding that it
`22.
`is not necessary for the California Parties to present a case that would support an
`independent cause of action under the California state law of fraud. The Commission
`noted that, throughout the Western Energy Crisis-related proceedings, it had consistently
`rejected a restrictive interpretation of Morgan Stanley that would require a showing that
`"traditional types of unfair dealing, such as fraud and duress, need to be independent
`statutory causes of action under state contract law ...."56 Instead, the Commission
`emphasized that it would look to state law as a guide to determine whether the conduct in
`question was the type of behavior that would result in unfair dealing at the contract
`formation stage. Based on this interpretation of the role of state law in the Mobile-Sierra
`
`52 Id. P 136 (citing 2016 Initial Decision, 155 FERC 1163,004 at P 241).
`
`53 Id. PP 195-199.
`
`54 Id. PP 203-218.
`
`55 Opinion No. 587, 185 FERC 1161,197 at P 176.
`
`56 Id. P 180 (quoting Opinion No. 537-A, 153 FERC 1161,386 at P 77).
`
`

`

`Case: 24-6696, 11/04/2024, DktEntry: 4.3, Page 12 of 43
`Filed Date: 06/07/2024
`Document Accession #: 20240607-3056
`
`Docket Nos. EL02-60-016 and EL02-62-015
`
`11
`
`analysis, the Commission found that it was appropriate for the Presiding Judge to frame
`the analysis based on a broader formulation of the law of fraud in California, namely,
`section 1572 of the California Civil Code, which defines Actual Fraud, in part, as "any
`other act fitted to deceive.#157
`
`The Commission affirmed that the evidentiary record supported a conclusion that
`23.
`Shell's representations about losses on the April/May 2001 sales, and its efforts to build
`then-current market prices into the long-term deal to make up for those purported losses,
`were "fitted to deceive" CDWR about Shell's role in artificially inflating those prices and
`misled CDWR into believing it was getting a good deal when it really was not.
`Accordingly, the Commission found that Shell's behavior was deceptive in nature and
`constitutes the type of fraudulent conduct under California state law that had the effect of
`altering the playing field for negotiation of the Shell Contract.58
`
`The Commission also affirmed the Revised Partial Initial Decision's finding that
`24.
`the required causal nexus between Shell's spot market manipulation and its effect on
`negotiation of the Shell Contract had been established. However, the Commission found
`that the chain of causation set forth in the Revised Partial Initial Decision was too
`attenuated and could be interpreted as a sweeping rule that anytime a seller engages in a
`bad act and then later enters into a related long-term contract, the resulting contract
`would not enjoy Mobile-Sierra protection. The Commission also rejected a theory of
`causal connection that attempts to create a nexus between Shell's fraudulent conduct and
`the general need for CDWR to seek and execute the Shell Contract. Instead, the
`Commission found that the required causal nexus is established by the fact that Shell's
`spot market strategies artificially inflated market prices and Shell then krlowingly
`negotiated to include those inflated market prices in the Shell Contract as make whole
`payments for the below market purchases in the early months of the contract.
`Specifically, the Commission found that Shell's representations to CDWR about its
`losses were deceptive in nature and were made with the intention to induce CDWR into
`agreeing to contract prices that reflected the fruits of Shell's unlawful market activity,
`whereas CDWR was unaware that the price terms of the contract were influenced by
`Shell's market manipulation.59
`
`The Commission reversed the Revised Partial Initial Decision's finding that the
`25.
`theory of fraud-in-the-inducement is inapplicable here. The Commission disagreed with
`the Revised Partial Initial Decision's finding that there was no mutual assent to the Shell
`Contract, highlighting that the record contains ample evidence of extensive bargaining
`
`57 Id. P 181 (quoting Cal. Civ. Code § 1572).
`
`5814. PP 178-183.
`
`59 Id. PP 220-228.
`
`

`

`Case: 24-6696, 11/04/2024, DktEntry: 4.3, Page 13 of 43
`Filed Date: 06/07/2024
`Document Accession #: 20240607-3056
`
`Docket Nos. EL02-60-016 and EL02-62-015
`
`12
`
`between the parties concerning various terms of the contract, including many concessions
`that were favorable to CDWR. Further, the Commission concluded that the Revised
`Partial Initial Decision's finding of no mutual assent relied on the flawed premise that,
`because CDWR was not aware of Shell's market manipulation, CDWR did not
`understand the nature of the document it was signing, a claim the Commission found to
`be contrary to relevant case law and record evidence. The Commission also found,
`consistent with its approach of not requiring a strict showing of all five elements of fraud,
`that recission of the contract was not necessary to find this theory to be applicable.
`Moreover, the Commission explained that, because claims of fraud-in-the-inducement are
`evaluated using the same elements as general fraud claims, the evidence that supports a
`general fraud finding equally supports a finding of fraud-in-the-inducement.6"
`
`The Commission also reversed the Revised Partial Initial Decision's finding that
`26.
`Mobile-Sierra should be avoided due to fraud-in-the-inception of the Shell Contract.61
`
`On January 19, 2024, Shell and the California Parties submitted requests for
`27.
`rehearing of Opinion No. 587.
`
`II.
`
`Discussion
`
`A.
`
`Elements of Fraud
`
`1.
`
`Opinion No. 587
`
`28. As noted above, the Commission looked to the California state law of fraud as a
`guide to determine whether Shell's conduct during negotiation of the Shell Contract was
`"the type of behavior that would result in unfair dealing at the contract formation
`stage.9162 As such, the Commission concluded that the Presiding Judge was not required
`to apply and analyze each of the five elements of common law fraud in the manner that
`would be necessary to support an independent cause of action under state contract law.
`Instead, the Commission found that it was appropriate for the Presiding Judge to look to
`the language of section 1572 of the California Civil Code, which defines "Actual Fraud,"
`among other things, as "any act fitted to deceive.9063 For that reason, the Commission
`
`60 Id. PP 245-249.
`
`61 Id. PP 260-265.
`
`62 Id. P 180.
`
`63 Cal. Civ. Code § 1572(5).
`
`

`

`Case: 24-6696, 11/04/2024, DktEntry: 4.3, Page 14 of 43
`Filed Date: 06/07/2024
`Document Accession #: 20240607-3056
`
`Docket Nos. EL02-60-016 and EL02-62-015
`
`13
`
`rejected exceptions concerning whether the California Parties succeeded in demonstrating
`all five elements of fraud.64
`
`The Commission found, based on evidence in the record regarding Shell's spot
`29.
`market manipulation, combined with evidence demonstrating Shell negotiators '
`knowledge of that unlawful spot market activity, that "Shell's statements about losses on
`the April/May 2001 sales constitute misrepresentations that were deceptive in nature.9765
`The Commission rejected Shell's contention that the record contains no evidence that
`statements about those losses were actually made, highlighting an express statement
`made by Ed Brown, chief Shell negotiator, confirming that CDWR "was fully aware"
`that Shell was taking a loss on the April/May 2001 sales.66 The Commission further
`noted that Mr. Brown's testimony also confirmed that Shell's "losses on these sales were
`to be made up for in future periods under the long-term agreement.>=67 In addition, the
`Commission rejected Shell's argument that, even if made, Shell negotiators would have
`believed any such statements about losses to be true. The Commission concluded that
`"Shell's statements about selling to CDWR at below market prices, or 'at a loss,' were
`misrepresentations because Shell, itself, was engaged in manipulative behavior that
`artificially inflated the market prices the parties were using as a benchmark.9168
`
`The Commission referenced undisputed evidence that Shell had engaged in
`30.
`numerous electric spot market strategies that the Commission has determined to be
`unlawful." The Commission explained that evidence of these violations was relevant to
`the analysis here because it "relates directly to the question of whether Shell's statements
`about the losses on the April/May 2001 sales were intended to induce CDWR into
`agreeing to prices that Shell, itself, inflated through its unlawful behavior, under the guise
`of making Shell whole for purported losses.977" The Commission also found that the
`
`64 Opinion No. 587, 185 FERC 1161,197 at P 182.
`
`65 Id. P 183.
`
`66 Id. P 184 (citing EX. snA-219 at 18:14-16).
`
`67 Id. (citing EX. snA-219 at 18:10-13).
`
`68 Id. P 185.
`
`69 Id. P 186 (citing Opinion No. 536, 153 FERC 161,144 at PP 3, 96-98, 101, 102,
`127, 128, 130, 132, 138, & 174, Opinion No. 537, 151 FERC 161,173 at P 118).
`
`70 Id.
`
`

`

`Case: 24-6696, 11/04/2024, DktEntry: 4.3, Page 15 of 43
`Filed Date: 06/07/2024
`Document Accession #: 20240607-3056
`
`Docket Nos. EL02-60-016 and EL02-62-015
`
`14
`
`record is replete with evidence confirming that Shell negotiators had knowledge of the
`unlawful trading strategies as well as their corresponding effects on prices and profits."
`
`The Commission noted that, although the California Parties were not required to
`31.
`prove all five elements of fraud, the record contains ample circumstantial evidence to
`demonstrate Shell's subjective state of mind during negotiation of the Shell Contract.
`Specifically, the Commission found that trader

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket