throbber
UNITED STATES OF AMERICA
`BEFORE THE
`FEDERAL ENERGY REGULATORY COMMISSION
`
`Maryland Public Service Commission, )
`Complainant
`)
`v.
`)
`PJM Interconnection, L.L.C.,
`)
`Respondent
`)
`
`Docket No. EL08-34-000
`
`ANSWER OF PJM INTERCONNECTION, L.L.C.
`
`Pursuant to Rule 213 of the Commission’s Rules of Practice and Procedure,1 and
`
`the Notice For Extension Of Time issued on January 29, 2008, PJM Interconnection,
`
`L.L.C. (“PJM”) submits this answer to the complaint filed by the Maryland Public
`
`Service Commission (“MdPSC”) in this docket (“Complaint”).
`
`I.
`
`INTRODUCTION AND SUMMARY.
`
`In its complaint, the MdPSC seeks the elimination of the exemption from offer
`
`capping afforded (1) certain newly constructed generating units in PJM (“construction
`
`exemption”) and (2) generating resources used to relieve the reactive limits on the West,
`
`Central, and East interfaces in the Mid-Atlantic Area Council (“MAAC”) Control Zone
`
`and the Allegheny Power System (“APS”) South interface (“interface exemption”).
`
`For the reasons discussed in this answer:
`
`•
`
`although the Complaint does not offer persuasive evidence of market
`power, PJM would not oppose Commission consideration whether, as a
`policy matter, the Commission should revisit the balance of interests that
`led to adoption of the construction exemption;
`
`1
`
`
`
`18 C.F.R. § 385.213 (2007).
`
`

`

`•
`
`•
`
`•
`
`•
`
`to the extent the Commission, in its policy review, determines to retain
`the construction exemption, it should clarify for market participants and
`other stakeholders the current rule that a generator will lose its exemption
`if it exercises “significant” market power;
`
`as required by both the approved tariff and Commission policy against
`re-running markets, any change to the construction exemption should be
`on a prospective basis following any Commission order directing such
`change;
`
`the Commission need not delve at this time into an investigation of
`whether any individual unit exercised market power, both because the
`Complaint does not make a prima facie case that such has occurred, and
`because the construction exemption is better addressed on a generic
`policy basis; and
`
`the Commission should dismiss the allegations regarding the interface
`exemption in order to allow an already initiated stakeholder process to
`continue to examine issues related to the application of the three-pivotal
`supplier test to exempt interfaces.
`
`A.
`
`Construction-Exempt Units.
`
`Four-and-a-half years have passed since PJM first proposed to eliminate the
`
`construction exemption for all post-1996 units, and over three years have passed since the
`
`Commission decided to retain the construction exemption only for certain units
`
`constructed within several narrow locked-in periods. In that time, PJM has implemented
`
`scarcity pricing, special mitigation rules for frequently mitigated units needed for
`
`reliability, and a comprehensive reform of the PJM capacity market. Under the
`
`circumstances, it is fair for the Commission to assess whether that exemption should
`
`continue for the remaining lives of the plants at issue. Therefore, PJM would not oppose
`
`the Commission addressing whether the balance of equities considered in 2005 remains
`
`the correct policy call in today’s market.
`
`2
`
`

`

`The Commission addressed this question as a policy matter when it adopted the
`
`broad post-1996 unit exemption,2 when it initially rejected PJM’s 2003 proposal to
`
`terminate the exemption,3 and when it decided to eliminate the exemption but grandfather
`
`certain units.4 Therefore, the Commission should exercise its discretion to address this
`
`question, if at all, as a policy matter. To the extent the Commission engages in that
`
`policy review, and determines to retain the current construction exemption, it should take
`
`the opportunity to clarify the rule that PJM should file to eliminate the exemption for any
`
`exempt generator that exercises “significant” market power. The Commission could
`
`provide greater certainty to market participants, state regulators, and other stakeholders,
`
`by explaining (for prospective application) what showing is contemplated by this
`
`standard and how, it all, the standard differs from the traditional definition of market
`
`power, i.e., whether a seller has been able profitably to maintain prices above competitive
`
`levels for a significant period of time.5
`
`The Complaint apparently invites the Commission to address this matter based on
`
`whether exempt generators have exercised market power. But, as shown below, the
`
`Complaint does not make a prima facie case that any individual market seller has
`
`exercised market power and, in any event, this question is better addressed, if at all, on a
`
`2
`
`3
`
`4
`
`5
`
`
`
`Atl. City Elec. Co., 86 FERC ¶ 61,248, at 61,904, 61,906 (1999).
`
`PJM Interconnection, L.L.C., 107 FERC ¶ 61,112, at P 54 (2004).
`
`PJM Interconnection, L.L.C., 110 FERC ¶ 61,053, at P 53 (2005) (“January 25
`Order”).
`
`1992 Horizontal Merger Guidelines § 0.1 Purpose and Underlying Policy
`Assumptions of the Guidelines, available at
`http://www.ftc.gov/bc/docs/horizmer.htm.
`
`3
`
`

`

`generic policy basis The Complaint proffers the PJM Market Monitor’s mark-up
`
`analysis, in which he concludes that exempt units “mark up” their energy market offers
`
`above his estimate of their marginal costs and thus “can and do exercise market power.”
`
`However, as PJM previously detailed, there is far less to the Market Monitor’s analysis
`
`than meets the eye.6 For example, the Market Monitor’s analysis makes a simplifying,
`
`but invalid, assumption that the exempt unit setting the market clearing prices would
`
`remain the marginal unit, and therefore still set the market clearing price, once the
`
`exempt unit’s “marked up” offer were reduced to cost. Because this assumption does not
`
`hold in many instances, it leads to an overstatement – estimated by PJM to be more than
`
`three-fold – of the impact of the alleged “mark ups” on energy prices. A significant
`
`amount of the alleged markup impact, more than $32 million, relates to units owned by
`
`municipal load-serving entities that buy more power than they sell at the allegedly
`
`affected locational marginal prices (“LMP”). No rational buyer would increase its power
`
`costs in this way, suggesting that these market participants, and likely the other exempt
`
`unit owners as well, are not in fact offering above marginal costs, and that the Market
`
`Monitor has simply misestimated the exempt units’ costs (which are not reported to the
`
`Market Monitor).
`
`These flaws compound an even more fundamental problem with the MdPSC’s
`
`approach, i.e., the failure to show, or even allege, that any particular generator has in fact
`
`successfully raised market-clearing prices above a competitive level for a significant
`
`period of time. The Market Monitor report on which the MdPSC relies discusses only
`
`average mark-ups of sell offers above the Market Monitor’s administrative estimate of
`
`
`Complaint, Attachment E.
`
`6
`
`4
`
`

`

`unit marginal costs, without showing any actual increases in clearing prices (considering
`
`other competitive sell offers), and without evaluating whether any particular increases
`
`were significant in either magnitude or duration.
`
`Moreover, the only remedy provided in the tariff, even if “significant market
`
`power” is found, is prospective elimination of the exemption for the involved unit.7 The
`
`Commission’s policy disinclination to order re-running of markets8 reinforces that the
`
`only relief likely to be ordered in this proceeding is prospective relief. The Commission
`
`could far more efficiently address the prospective applicability of the construction
`
`exemption as a policy matter, without first holding a long, expensive, and likely
`
`inconclusive hearing on the question.
`
`B.
`
`Exempt Interfaces.
`
`The Commission should dismiss the Complaint with regard to the exempt
`
`interfaces. The Complaint fails to allege any evidence of the exercise of market power on
`
`the exempt interfaces. Congestion on these regional interfaces can be controlled by a
`
`large number of generators and they are among the most liquid in PJM. In the eight
`
`years that the PJM market has been operating, neither the PJM Market Monitor nor PJM
`
`has identified any exercise of market power by any generating unit on them.
`
`Importantly, PJM has already initiated a stakeholder process to examine the
`
`application of the three-pivotal supplier test to the exempt interfaces, along with
`
`examining rules for appropriate scarcity pricing. As indicated in the affidavit attached to
`
`this answer, the PJM Market Monitor supports deferring these issues to this stakeholder
`
`
`Operating Agreement, Schedule 1 § 6.5.
`
`7
`
`8
`
`See n. 37, 38 infra.
`
`5
`
`

`

`process. Less than a year ago, in the proceeding where the current exempt interfaces
`
`were most recently established, the Commission similarly dismissed requests to re-
`
`examine market power mitigation so as to “not preempt the PJM processes through the
`
`establishment of a section 206 proceeding.”9 The Commission should take the same
`
`action here.
`
`C.
`
`Other Issues.
`
`The complaint unfortunately resurrects Market Monitor, state and consumer
`
`advocate claims raised in 2007 that PJM hindered the PJM Market Monitor from
`
`conveying his views on exempt interfaces and exempt generators, this time as a purported
`
`ground for retroactive relief. The Commission already rejected these claims in a
`
`proceeding the MdPSC, among others, initiated. The claims are barred from relitigation.
`
`In any event, PJM took none of the alleged actions and fully complied with its Tariff by
`
`posting all PJM Market Monitor recommendations concerning exempt interfaces. PJM
`
`also fully complied with the PJM Tariff10 by advising the PJM Market Monitor to refer to
`
`the Commission his concerns regarding an exempt generator that might have exercised
`
`market power. Simply put, the MdPSC’s claims already have been rejected by the
`
`Commission and are false. The Commission should not countenance their relitigation.
`
`9
`
`10
`
`
`
`PJM Interconnection, L.L.C., 120 FERC ¶ 61,092, at P 10 (2007).
`
`PJM Open Access Transmission Tariff (“PJM Tariff” or “Tariff”).
`
`6
`
`

`

`COMMISSION
`OPPOSE
`NOT
`PJM WOULD
`II. WHILE
`RECONSIDERATION OF ITS POLICY ON THE CONSTRUCTION
`EXEMPTION, THE MDPSC HAS NOT PRESENTED SUFFICIENT
`EVIDENCE TO WARRANT ADDRESSING THIS
`ISSUE BY
`ATTEMPTING TO DETERMINE WHETHER ANY EXEMPT UNITS IN
`THE PJM REGION HAVE EXERCISED SIGNIFICANT MARKET
`POWER.
`
`A.
`
`Background Of Construction Exemption.
`
`An exemption from offer capping for newly constructed generating units has been
`
`a part of PJM market rules since 1999, when the Commission first approved market-
`
`based pricing for the sale of energy in the PJM market. The Commission found at that
`
`time that encouraging the entry of new generation would, in fact, help eliminate
`
`opportunities for the exercise of local market power. Offer caps, however, could deter
`
`that entry.11 Therefore, the Commission exempted from offer capping all generating
`
`units constructed after July 1996.12
`
`In part responding to concerns expressed by PJM, the Commission subsequently
`
`removed the blanket exemption for all units constructed after 1996.13 However, it found
`
`that “some units may have been built in reliance on the exemption,” raising “equitable
`
`concerns.” Id. Therefore, the Commission refined the exemption and grandfathered “units
`
`in zones other than the original PJM zones for which construction commenced beginning on
`
`the date a transmission owner made a filing with the Commission committing to join
`
`11
`
`12
`
`13
`
`
`
`Atl. City Elec. Co., 86 FERC ¶ 61,248, at 61,904.
`
`This date corresponded to a similar blanket grant of market-based rate authority,
`then contained in the Commission’s regulations to generating units throughout the
`country that were constructed after July 1996. See 18 C.F.R. § 35.27(a) (2007).
`
`January 25 Order at P 53.
`
`7
`
`

`

`PJM.”14
`
`At the same time, the Commission found that, while it needed to take account of the
`
`reliance interest of the generators, it also needed to balance that interest against the need to
`
`provide for mitigation in the event that an exempt generator exercised market power.15
`
`Therefore, the Commission held that the grandfathered units still should be subject to
`
`mitigation in the event that PJM or its Market Monitor concluded that the units exercised
`
`“significant market power.”16 The Commission did not define what would constitute
`
`“significant market power” warranting the lifting of an exemption.
`
`Implementing these orders, Section 6.5 of Schedule 1 of the Operating Agreement17
`
`exempts the grandfathered units specified by the Commission, but provides that “[i]n the
`
`event that [PJM] or the PJM Market Monitor concludes that a generation resource exempted
`
`14
`
`by this section 6.5 exercises significant market power, then [PJM] may impose mitigation on
`
`
`PJM Interconnection, L.L.C., 112 FERC ¶ 61,031, at P 65 (2005) (“EL03-236
`Rehearing Order”) order on reh’g, 114 FERC ¶ 61,302 (2006). Consequently, the
`following units continue to hold a construction exemption: (i) units in the original
`PJM footprint for which construction commenced between April 1, 1999 and
`September 30, 2003; (ii) units in the Duquesne Light Company Zone for which
`construction commenced after August 27, 2001 and before September 30, 2003;
`(iii) units in the Rockland Zone for which construction commenced after October
`17, 2001 and before September 30, 2003; (iv) units in the AP Zone for which
`construction commenced after March 15, 2001 and before September 30, 2003;
`and (v) units in the Dayton Power & Light Zone, the Commonwealth Edison
`Company Zone, the American Electric Power Zone, and the Virginia Electric and
`Power Company Zone for which construction commenced after May 28, 2002 and
`before September 30, 2003. Operating Agreement, Schedule 1, § 6.5.
`
`15
`
`16
`
`17
`
`See PJM Interconnection, L.L.C., 114 FERC ¶ 61,302, at P 4 (explaining January
`25 Order).
`
`January 25 Order at P 60 (emphasis added).
`
`The rules are contained in both Schedule 1 of the Operating Agreement and the
`Appendix to Attachment K of the PJM Tariff, which are identical.
`
`8
`
`

`

`such generation resource, provided that, prior to imposing mitigation, [PJM] or the PJM
`
`Market Monitor makes a filing under section 205 or 206 of the Federal Power Act
`
`documenting the exercise of market power by the generating resource and the Commission
`
`has accepted such filing.”18
`
`Thus, the Commission established a balancing test for determining whether
`
`construction-exempt units should be subject to offer capping. While the reliance interest of
`
`remaining exempt units19 “needs to be taken into account,”20 it can be overcome if an
`
`exempt unit exercises “significant market power.”21
`
`Since these rules have been effect, there has been only one case in which the PJM
`
`Market Monitor has provided an opinion to PJM that a particular construction-exempt
`
`generator allegedly exercised market power. As explained below, in this single case, the
`
`matter was properly referred to the Commission, which evidently determined that there was
`
`insufficient basis for action in the matter.
`
`B.
`
`PJM Would Not Oppose A Commission Re-assessment Of The
`Construction Exemption.
`
`As indicated above, several years have passed since the Commission elected
`
`generally to terminate the offer-capping exemption for post-1996 units, but preserve a
`
`construction exemption for certain units that might have been built partially in reliance on
`
`18
`
`19
`
`20
`
`21
`
`
`
`Operating Agreement, Schedule 1 § 6.5.
`
`As a result of the Commission’s orders, the number of exempt units in PJM was
`reduced from 215 to 56. Complaint, Attachment B – Answers To MdPSC
`Questions, at 23.
`
`January 25 Order at P 60.
`
`Id.
`
`9
`
`

`

`that exemption. In that time, there have been significant changes to the PJM markets,
`
`including implementation of scarcity pricing rules,22 limitations on mitigation of frequently
`
`mitigated units needed for reliability,23 and comprehensive reform of the PJM capacity
`
`market.24
`
`There currently are 56 units that qualify for the construction exemption. Whether or
`
`not the Commission were ever to find that any of these units had exercised market power (as
`
`discussed below, the complaint does not demonstrate such market power), the Commission
`
`still could determine that the equitable reliance interests that prompted the construction
`
`exemption have become attenuated simply by the passage of time, or have been mitigated or
`
`become moot as a result of other market changes.
`
`To be clear, PJM is not convinced that eliminating the construction exemption is
`
`warranted. However, PJM would not object to the Commission re-visiting its prior policy
`
`determination in response to this complaint to further consider the question.25 As noted
`
`above, if the Commission undertakes that policy review, and determines to retain the current
`
`construction exemption, it could provide greater certainty to PJM, state regulators, and
`
`market participants by clarifying the “significant market power” standard.
`
`22
`
`23
`
`24
`
`25
`
`
`
`See PJM Interconnection, L.L.C., 114 FERC ¶ 61,076 (2006).
`
`Id.
`
`See PJM Interconnection, L.L.C., 117 FERC ¶ 61,331 (2006), order on reh’g, 119
`FERC ¶ 61,318, reh’g denied, 121 FERC ¶ 61,173 (2007), pets. for review
`pending sub nom. Pub. Serv. Elect. & Gas Co. v. FERC, Nos. 07-1336, et al.
`(D.C. Cir., filed Aug. 23, 2007).
`
`to focused “paper-hearing”
`That policy assessment may be well-suited
`procedures, in which parties could be invited to express their views on whether
`market changes or other factors should cause the Commission to change the
`balance it struck when it adopted the construction exemption in its current form.
`
`10
`
`

`

`C.
`
`The Complaint Does Not Show That Exempt Units Have Exercised
`Significant Market Power.
`
`The standard for lifting the construction exemption from a unit is its exercise of
`
`“significant market power.”26 In its complaint, the MdPSC relies upon the PJM Market
`
`Monitor’s mark up analysis, which the MdPSC contends demonstrates exercises of
`
`market power. Based on the Market Monitor’s evaluation that exempt units “mark up”
`
`their energy market offers above his estimate of their marginal costs, the PJM Market
`
`Monitor told the MdSPC that exempt units “can and do exercise market power, at times,
`
`that would not be permitted if the units were not exempt.”27 MdPSC alleges that
`
`“[a]ccording to the MMU, all exempt units’ ‘exercise of market power’ added $87.5
`
`million to Maryland’s 2006 real-time energy related charges.”28 Based on the PJM
`
`Market Monitor’s analysis, the MdPSC asks the Commission to eliminate the
`
`construction exemption for all generating units.
`
`While well-intentioned, this approach cannot gain the MdPSC the relief it seeks.
`
`The MdPSC posits that an exercise of market power is demonstrated and quantified by an
`
`exempt unit’s submission of an offer price above the Market Monitor’s administrative
`
`estimate of the unit’s marginal costs, whenever the exempt unit is the marginal unit. As
`
`such, the MdPSC equates the competitive price for the market with the Market Monitor’s
`
`cost estimate of the exempt unit’s costs. But this ignores the competitive offers of all
`
`26
`
`27
`
`28
`
`
`
`Operating Agreement, Schedule 1 § 6.5.
`
`Complaint at 19.
`
`Complaint at 15.
`
`11
`
`

`

`other market participants. And it places too much reliance on the cost-estimating abilities
`
`of a single individual, i.e., the Market Monitor.
`
`As PJM explained to the MdPSC before it filed its complaint,29 the PJM Market
`
`Monitor made the simplifying, but invalid, assumption that the construction-exempt unit
`
`still would be the marginal unit—setting the market clearing price—even though its
`
`“marked up” offer is reduced to an offer capped price. As PJM explained to the MdPSC:
`
`The [PJM] Market Monitor’s analysis is overly conservative because it
`fails to consider that when the supply curve is altered, the marginal
`generator can, and likely will change. Because this dynamic is ignored,
`the [PJM] Market Monitor’s analysis quantifies the impact of markup on
`LMP in a manner very likely to overstate significantly the impact of the
`markup on LMP.30
`
`In other words, the market’s competitive price likely will not be set by the estimated
`
`marginal costs of the exempt unit, but by the unit that submitted the next-lower price
`
`below the exempt unit’s “marked-up” price. If that unit is not exempt, and either did not
`
`require mitigation or was properly mitigated, then it is a better indication of the
`
`competitive price for the market, even though that price may be well above the
`
`administrative estimate of the exempt unit’s marginal costs. Based on PJM’s evaluation
`
`of a sample of the actual offer prices of other units that would set price if exempt units
`
`were offer capped, PJM believes that, considering this factor alone, the alleged increase
`
`29
`
`30
`
`
`
`Letter from Andrew L. Ott to Steven B. Larsen, December 10, 2007, MdPSC
`Complaint, Attachment E.
`
`Complaint Attachment E at 3.
`
`12
`
`

`

`above competitive prices is less than 30 percent of the increase depicted by the PJM
`
`Market Monitor and relied upon by the MdPSC.31
`
`The MdPSC’s approach also places too much reliance on the Market Monitor’s
`
`administrative cost estimates, and there is evidence that those estimates may be faulty.
`
`Based on PJM’s review, at least four of the exempt units that the Market Monitor claims
`
`are “marking up” prices are owned by municipal entities with load-serving obligations.
`
`These municipal load-serving entities are both buyers and sellers of energy, and purchase
`
`far more energy than they sell. Because their generation and load are located at the same
`
`LMP nodes, it is very unlikely they would have any incentive to exercise market power to
`
`raise prices, which would translate into their paying substantially more for their overall
`
`energy needs. More likely, the PJM Market Monitor has inaccurately estimated these
`
`units’ operating costs (as exempt units, they do not report their costs to PJM), thus
`
`resulting in an overstatement of the unit’s “mark up” and resulting impact on prices.
`
`Indeed, PJM’s review indicates that these units’ offers are consistent across all days; they
`
`do not “mark up” their offers during constrained days.32 This is not indicative of an
`
`31
`
`32
`
`
`
`Moreover, even this reduced quantification far overstates the impact of prices on
`load-serving entities in Maryland. The Market Monitor’s State of the Market
`Report indicates that only six percent of load is unhedged against the impact of
`increased real-time energy prices and therefore purchases from the spot market.
`2006 State of the Market Report at 88. Yet, the MdPSC’s allegation that
`Maryland customers suffered $87.5 million of increased costs in 2006 assumes
`that every megawatt of load paid the increased prices. Based on the six percent of
`megawatt-hours actually purchased in the spot market, even if there were no other
`flaws in the Market Monitor’s analysis, the impact on load would be closer to $5
`million in 2006.
`
`Moreover, under PJM market rules, generators may submit only one market-based
`offer curve for any single day. Operating Agreement, Schedule 1, Section
`(Cont’d . . . )
`
`13
`
`

`

`exercise of market power. PJM believes that it is more reasonable to assume that the
`
`PJM Market Monitor did not have sufficient operating cost information available for
`
`these units in his analysis than it is to presume that these load serving entities are
`
`choosing to “mark up” their offers in order to exercise market power.33
`
`The MdPSC’s approach also fails to account for the possibility that the calculated
`
`mark-ups may be warranted by scarcity conditions, even though the Market Monitor
`
`himself recognized in his report to the MdPSC that scarcity conditions produce valid
`
`markups. He stated: “The fact that unit markups affect prices in a zone does not mean
`
`that . . . owners of units . . . have exercised market power.” Complaint, Attachment B at
`
`42. As he explained, “markup on high load days is likely to be the result of appropriate
`
`scarcity pricing rather than market power.” Id. at 43. Neither the Market Monitor nor the
`
`MdPSC evaluates whether any of the alleged “mark ups” were a result of scarcity
`
`pricing.34
`
`The MdPSC ignores these flaws, all of which tend to contradict the claim that
`
`there has been an increase in prices above competitive levels. But more fundamentally,
`
`by simply relying, without more, on the Market Monitor’s report, the MdPSC fails to
`
`
`
`
`
`( . . . cont’d)
`1.10.1A(d)(ii). This rule makes it more difficult for units to attempt to exercise
`market power, because they cannot raise or lower their prices throughout the day.
`
`33
`
`34
`
`As just one example, the PJM Market Monitor may not have complete
`information about the fuel contracts of exempt units, critical to determining a
`unit’s marginal costs. Exempt units do not report that information to PJM.
`
`PJM also understands that the Market Monitor’s analysis includes “mark ups”
`even if the units are not being operated out of merit order to relieve constraints,
`which further inflates the alleged impacts. Even if the MdPSC’s complaint were
`granted, these ordinary mark-ups would be permitted.
`
`14
`
`

`

`make a prima facie showing that any unit has exercised market power. Nowhere does
`
`the MdPSC show that any exempt unit has managed to increase prices by a significant
`
`amount above competitive levels for a significant period of time. As shown above, the
`
`increase, if any, is far less than the Market Monitor portrays, since he insufficiently
`
`accounted for other competitive offers, failed to account for scarcity pricing, and
`
`evidently under-estimated exempt units’ marginal costs. Whether any remaining price
`
`increase, if any, was significant and sustained for a significant period of time is not
`
`addressed. Without an analysis that is far more accurate, rigorous, and detailed, there is
`
`no basis for believing that any particular exempt generator is exercising market power.
`
`The complaint’s generalized claims about average mark-ups certainly provide no basis
`
`for wholesale elimination of the exemption for all currently exempt units.
`
`Notably, although the market rules provide for lifting exemptions only when
`
`significant market power is exercised, with only one exception, the PJM Market Monitor
`
`has informed PJM of only general concerns regarding exempt units exercising market
`
`power. With only one exception, the Market Monitor has not identified to PJM any
`
`specific concerns regarding individual units that he believed were exercising significant
`
`market power that would warrant action under Section 6.5 to remove an exemption.35
`
`The one exception is a single unit that the PJM operations staff initially brought to the
`
`PJM Market Monitor’s attention. With regard to this unit, the PJM Market Monitor
`
`opined that the generating unit had exercised market power and received excess payments
`
`of $20 million. After investigating, PJM determined that, rather than a public filing
`
`seeking to terminate the unit’s exemption, the proper course of action was for the PJM
`
`
`Complaint, Attachment E at 2.
`
`35
`
`15
`
`

`

`Market Monitor to report the situation to the Commission, which it did. However, the
`
`Commission evidently found the referred matter did not warrant any enforcement action
`
`by the Commission, since it took no action. In light of the Commission’s inaction, PJM
`
`reasonably considered that the Commission believed that significant market power had
`
`not been exercised and that there was no basis to terminate the unit’s exemption.36
`
`In short, the MdPSC complaint does not support its allegations of market power.
`
`PJM does not question the earnestness or seriousness of the MdPSC’s concerns about the
`
`potential that market power is being exercised. If any generators are exercising
`
`significant market power, exempt or not, the Commission clearly should address it.
`
`However, the absence of reports by the Market Monitor of the exercise of market power
`
`by individual exempt units undercuts the claim by the MdPSC that there is “clear
`
`evidence of market power.”37
`
`In view of the lack of evidence of actual exercises of
`
`market power and the problematic limitations in the proffered analysis, as described
`
`above, the Complaint’s allegations of market power do not provide a basis for
`
`elimination of the construction exemption. Nonetheless, as stated above, PJM would not
`
`oppose the Commission considering, as a policy matter, whether the construction
`
`exemption remains just and reasonable.
`
`36
`
`
`
`The PJM Market Monitor is obligated to report to the Commission if he has
`identified a significant market problem. See PJM Tariff, Attachment M § IV.A.
`Yet, aside from the one instance described above, neither the MdPSC nor the PJM
`Market Monitor has presented any evidence that individual exempt units have
`exercised market power.
`
`37
`
`Complaint at 16.
`
`16
`
`

`

`D.
`
`Any Change To The Construction Exemption Should Be On A
`Prospective-only Basis.
`
`If the Commission does determine to change the construction exemption in this
`
`proceeding, such changes should be only prospective. Section 6.5 specifically
`
`contemplates prospective mitigation: PJM may mitigate individual exempt units only
`
`after submitting a filing “documenting the exercise of market power by the generating
`
`resource” and after “the Commission has accepted such filing.” In no event should the
`
`Commission require PJM retroactively to re-run energy markets and recalculate market
`
`clearing prices. The Commission generally “disfavor[s] re-determining market outcomes
`
`after the fact.”38 Here, retroactively re-running energy markets with previously exempt
`
`units offer capped would affect not only exempt units that allegedly exercised market
`
`power, but also all other market participants that relied on the daily prices established in
`
`the energy market. Finally, retroactive application as sought by the complainant would
`
`offend equities by holding past market participant conduct to a standard of “significant
`
`market power” that has not yet been defined by the Commission. Therefore, any lifting
`
`of the construction exemptions in this proceeding should be prospective only, following
`
`any Commission decision.39
`
`38
`
`39
`
`
`
`N.Y. Indep. Sys. Operator, Inc. 113 FERC ¶ 61,340, at P 17 (2005). See id. (citing
`Wisvest-Connecticut, LLC v. ISO New England, Inc. 104 FERC ¶ 61,262, at
`61,849 (2003) (“[R]etroactivity is not authorized when a new rule is substituted
`for an old rule that was reasonably clear so that the settled expectations of those
`who had relied on the old rule are protected.”).
`
`See Borough of Chambersburg, PA v. PJM Interconnection, L.L.C., 119 FERC
`¶ 61,166 at P 46 (2007) (stating there was no basis retroactively to re-allocate
`auction revenue rights thereby “upsetting customer expectations” where “it would
`not be practical to re-run the [FTR] auction . . . to implement a change in the
`allocations for all of the participants in the ARR process, not just the
`[Complainants].”); see also Consol. Edison Co. of N.Y. v. FERC, 347 F.3d 964,
`(Cont’d . . . )
`
`17
`
`

`

`III.
`
`THE COMMISSION SHOULD DISMISS THE MDPSC COMPLAINT
`REGARDING
`EXEMPT
`INTERFACES AND ALLOW
`PJM
`STAKEHOLDERS TO ADDRESS THE MATTER
`IN THE
`STAKEHOLDER PROCESS.
`
`A.
`
`The MdPSC Presents No Evidence Of The Exercise Of Market Power
`On The Exempt Interfaces.
`
`The MdPSC presents no evidence in its complaint of the exercise of market power
`
`on the exempt interfaces. Indeed, the PJM market now has operated for over eight years
`
`with the East, West and Central interfaces exempt from offer capping.40 During this
`
`eight-year period, neither the PJM Market Monitor nor PJM has identified any exercise of
`
`market power by any generating unit related to the control of these large, regional
`
`transmission interfaces.41 Congestion on these regional interfaces can be controlled by a
`
`large number of generators, are among the most liquid in PJM, and support significant
`
`over-the-counter bilateral forward transacting as well as, in some cases, futures exchange
`
`
`
`( . . . cont’d)
`969 (D.C. Cir. 2003) (Commission has “no authority to grant retroactive relief for
`the two months prior to the filing [to change the market rule] despite the dramatic
`price spike.”); see also Bangor Hydro-Elec. Co. v

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket