throbber
UNITED STATES OF AMERICA
`BEFORE THE
`FEDERAL ENERGY REGULATORY COMMISSION
`
`Docket No. EL13-888-000
`
`)
`)
`
`))
`
`)
`)
`)
`)
`)
`
`Northern Indiana
`Public Service Company
`
`v.
`
`Midcontinent Independent
`System Operator, Inc. and
`PJM Interconnection, L.L.C.
`
`MOTION TO INTERVENE AND COMMENT OF
`INTERNATIONAL TRANSMISSION COMPANY d/b/a ITCTRANSMISSION, MICHIGAN
`ELECTRIC TRANSMISSION COMPANY, LLC, AND ITC MIDWEST LLC
`
`Pursuant to Rule 214 of the Rules of Practice and Procedure1 of the Federal Energy
`
`Regulatory Commission (“Commission”), International Transmission Company d/b/a
`
`ITCTransmission, Michigan Electric Transmission Company, LLC, and ITC Midwest LLC
`
`(collectively, “ITC” or “ITC Companies”) respectfully move to intervene in the above-captioned
`
`proceeding, and submit these comments on the issues raised by the Northern Indiana Public
`
`Service Company (“NIPSCO”) therein. ITC has filed a timely, unopposed motion to intervene in
`
`the four dockets which comprise the competing interregional transmission planning and cost
`
`allocation proposals filed by the Midcontinent Independent System Operator, Inc. (“MISO”) and
`
`1 18 C.F.R. §385.214 (2013). On October 1, 2013, the Commission issued a notice
`extending the deadline for responding to NIPSCO’s complaint to October 31, 2013. “Notice
`of Extension of Time,” Docket No. EL13-88-000 (Oct. 1, 2013).
`
`

`

`Docket No. EL13-88-000
`
`PJM Interconnection, L.L.C. (“PJM”) against which NIPSCO has made its complaint,2 and by
`
`operation of Rule 214(c)(1) is a party to those proceedings. As discussed further herein, ITC
`
`concurs with NIPSCO’s assessment that the current MISO-PJM interregional planning
`
`process under the existing Joint Operating Agreement (“JOA”) is flawed, and that
`
`perpetuation of that process is neither fully compliant with Order No. 1000 nor likely to
`
`remedy the failure of the JOA to produce a single interregional transmission project between
`
`MISO and PJM.
`
`I.
`
`MOTION TO INTERVENE
`
`International Transmission Company d/b/a ITCTransmission, Michigan Electric
`
`Transmission Company, LLC, and ITC Midwest LLC are independent, stand-alone
`
`transmission companies engaged exclusively in the development, ownership and operation
`
`of facilities for the transmission of electric energy in interstate commerce. Each is a
`
`subsidiary of ITC Holdings Corp., which invests exclusively in the electric power
`
`transmission grid to improve electric reliability, facilitate access to renewable and other
`
`generation, improve access to power markets, and reduce the overall cost of delivered
`
`electric power. Transmission service over facilities developed and owned by the ITC
`
`Companies is provided by the MISO pursuant to the Tariff. The ITC Companies are all
`
`Transmission Owner members of the MISO. As MISO Transmission Owners and parties to
`
`the Order No. 1000 compliance filing proceedings in which MISO and PJM have made their
`
`respective proposals, the ITC Companies are each directly impacted by the interregional
`
`2 “Motion to Intervene and Comment of International Transmission Company, et al.”,
`Docket Nos. ER13-1924-000; ER13-1943-000; ER13-1944-000; ER13-1945-000 (Aug. 26,
`2013) (“ITC Intervention”).
`
`- 2 -
`
`

`

`Docket No. EL13-88-000
`
`planning and cost allocation provisions against which NIPSCO has filed a complaint. Thus,
`
`the ITC Companies have a specific, direct, and substantial interest in the outcome of this
`
`proceeding. The ITC Companies have unique interests that cannot be adequately
`
`represented by any other party. Accordingly, the ITC Companies request that the
`
`Commission grant this Motion for Leave to Intervene in this proceeding and permit it to
`
`become a full party for all purposes.
`
`II.
`
`COMMENT
`
`In the comments filed in the MISO and PJM Order No. 1000 interregional
`
`transmission planning and cost allocation compliance dockets, the ITC Companies
`
`observed that the two proposals proffered therein would only perpetuate the past failure of
`
`the current JOA provisions to identify a single interregional transmission project. While
`
`ITC limited its comments in those proceedings to the aspects of interregional transmission
`
`planning and cost allocation required by Order No. 1000 over which the two Regional
`
`Transmission Organizations (“RTOs”) actively disagreed, ITC agrees that additional
`
`reforms beyond the requirements of Order No. 1000 may be needed to properly plan for and
`
`identify potential interregional projects across the irregular and highly intertwined seam
`
`between these two RTOs. ITC further agrees that the unique circumstances and history of
`
`the MISO-PJM seam forms a context in which the Commission should evaluate the justness
`
`and reasonableness of interregional cost allocation methodologies proposed therein, and that
`
`this context may require reforms beyond the scope of Order No. 1000’s compliance
`
`requirements. In direct contrast to other RTOs, which were created using boundaries that
`
`reflected long-standing physical divisions of the bulk electric system, MISO and PJM were
`
`created using an essentially arbitrary geographic boundary between the two RTOs which cut
`
`- 3 -
`
`

`

`Docket No. EL13-88-000
`
`through overlapping systems owned by member utilities from a common historical planning
`
`region, resulting in a seam which the Commission itself observed is “highly
`
`interconnected.”3 ITC reiterates its observation that it is simply inconceivable that there
`
`does not exist a single interregional transmission project across this “highly interconnected”
`
`seam which would not provide some economic, congestion, reliability, or public policy
`
`benefit to the customers of both regions. Yet the JOA which PJM proposes to continue
`
`using as the basis for interregional planning and interregional project cost allocation (which
`
`MISO proposes to further curtail) has abjectly failed to identify any such project.
`
`Continuation of the JOA will only continue to deny customers of MISO and PJM from
`
`receiving the benefits of cross-border transmission projects.
`
`If the goals of Order No. 1000’s interregional transmission planning provisions are to
`
`be achieved where, as here, the RTOs sharing a common border have failed to agree upon a
`
`cost allocation methodology, it is incipient upon the Commission to act upon its stated
`
`intention to “develop a cost allocation method or methods that meets its proposed
`
`requirements.”4 Furthermore, in so doing, the Commission should reject narrowly defined
`
`project categories for cross-border projects based on only a single benefit metric, in favor of
`
`provisions that would allow consideration of all of the types of benefits – whether
`
`economic-, reliability-, or public policy-based – that new transmission projects can provide
`
`when interregional studies are performed. To that end, NIPSCO’s proposed Reforms 3, 4,
`
`and 5 represent possible features of a MISO-PJM interregional cost allocation methodology
`
`3 Alliance Cos., 103 FERC ¶ 61,274 at P 26 (2003) .
`4 Transmission Planning and Cost Allocation by Transmission Owning and
`Operating Public Utilities, Order No. 1000, 136 FERC ¶ 61,051 at P 607 (2011) (“Order
`No. 1000”), order on reh’g, Order No. 1000-A, 139 FERC ¶ 61,132, order on reh’g, Order
`No. 1000-B, 141 FERC ¶ 61,044 (2012).
`
`- 4 -
`
`

`

`Docket No. EL13-88-000
`
`that would be more consistent with the requirements of Order No. 1000. As already
`
`established in ITC’s initial comments, MISO’s and PJM’s proposals do not fully comply
`
`with Order No. 1000 because they fail to consider all but the most limited types of project
`
`benefits within narrowly-defined project categories for potential interregional transmission
`
`projects.5 NIPSCO’s proposed Reforms 3-5 would provide a single set of criteria for
`
`interregional projects, permit consideration of additional benefit metrics for cross-border
`
`Market Efficiency Projects, and eliminate arbitrary voltage and project cost thresholds.
`
`Although ITC supports a more robust suite of potential project benefits than NIPSCO has
`
`proposed in Reform 4, NIPSCO’s proposal is nonetheless significantly more compliant with
`
`Order No. 1000’s interregional cost allocation principles than either MISO’s or PJM’s
`
`proposals. Cost allocation reform for cross-border projects is imperative to ensure that
`
`effective planning can occur, and while ITC and NIPSCO may differ in their exact positions
`
`on the nature of that reform, ITC nonetheless strongly supports NIPSCO’s general points
`
`that neither MISO nor PJM have proposed an acceptable interregional cost allocation
`
`methodology, and that the Commission must take action to ensure that the failure of the
`
`JOA is not perpetuated and that the goals of Order No. 1000 are realized.
`
`III.
`
`CONCLUSION
`
`WHEREFORE, for the reasons discussed herein, the ITC Companies respectfully ask the
`
`Commission to act in manner consistent with the foregoing.
`
`Respectfully submitted,
`
`/s/ James W. Bixby
`
`5 ITC Intervention at 9-14.
`
`- 5 -
`
`

`

`Docket No. EL13-88-000
`
`October 28, 2013
`
`James W. Bixby
`ITC Holdings Corp.
`1300 I Street N.W.
`Suite 300W
`Washington, DC 20005
`
`Attorney for the ITC Companies
`
`- 6 -
`
`

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket