throbber
IN THE UNITED STATES COURT OF APPEALS
` FOR THE DISTRICT OF COLUMBIA CIRCUIT
`
`Enerwise Global Technologies, Inc.,
`
`
`Petitioner
`
`v.
`
`Federal Energy Regulatory
`Commission,
`
`Respondent.
`
`
`
`
`
`
`)
`)
`)
`)
`)
`)
`)
`)
`)
`)
`)
`)
`
`Case No.
`
`
`
`PETITION FOR REVIEW OF
`ENERWISE GLOBAL TECHNOLOGIES, INC.
`
`Pursuant to Section 313(b) of the Federal Power Act, 16 U.S.C. § 825l(b), Rule
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`15(a) of the Federal Rules of Appellate Procedure, and Circuit Rule 15 of the United
`
`States Court of Appeals for the District of Columbia Circuit, Enerwise Global
`
`Technologies, Inc. d/b/a CPower (“CPower”) hereby petitions this Court for judicial
`
`review of the following orders issued by the Federal Energy Regulatory Commission:
`
`1. Calpine Corp., et al. v. PJM Interconnection, L.L.C., “Order
`Rejecting Proposed Tariff Revisions, Granting in Part and
`Denying in Part Complaint, and Instituting Proceeding Under
`Section 206 of the Federal Power Act,” 163 FERC ¶ 61,236 (June
`29, 2018).
`
`
`2. Calpine Corp., et al. v. PJM Interconnection, L.L.C., “Order
`Establishing Just and Reasonable Rate,” 169 FERC ¶ 61,239
`(December 19, 2019).
`
`
`

`

`
`
`3. Calpine Corp., et al. v. PJM Interconnection, L.L.C., “Order on
`Rehearing and Clarification,” 171 FERC ¶ 61,034 (April 16,
`2020).
`
`4. Calpine Corp., et al. v. PJM Interconnection, L.L.C., “Order on
`Rehearing and Clarification,” 171 FERC ¶ 61,035 (April 16,
`2020).
`
`
`Copies of these Commission’s orders are attached hereto. Also attached to this
`
`petition are: (1) the corporate disclosure statement required by Rule 26.1 of the Federal
`
`Rules of Appellate Procedure and (2) a Certificate of Service, with the list of parties to
`
`the underlying proceeding.
`
`
`
`
`
`
`
`Respectfully submitted,
`
`
`Howard L. Nelson
`Howard L. Nelson
`Greenberg Traurig LLP
`2101 L Street, NW
`Suite 1000
`Washington, DC 20037
`(202) 331-3163
`nelsonh@gtlaw.com
`
`Counsel for
`Enerwise Global Technologies,
`Inc., d/b/a CPower
`
`
`
`
`
`Dated: June 12, 2020
`
`- 2 -
`
`

`

`IN THE UNITED STATES COURT OF APPEALS
`FOR THE DISTRICT OF COLUMBIA CIRCUIT
`
`Enerwise Global Technologies, Inc.,
`
`Petitioner
`
`v.
`
`Federal Energy Regulatory
`Commission,
`
`Respondent.
`
`
`
`
`
`
`)
`)
`)
`)
`)
`)
`)
`)
`)
`)
`)
`)
`
`Case No.
`
`
`
`CORPORATE DISCLOSURE STATEMENT
`
`Pursuant to Rule 26.1 of the Federal Rules of Appellate Procedure and Circuit
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`Rule 26.1, Enerwise Global Technologies, Inc. d/b/a CPower (“CPower”) states as
`
`follows:
`
`CPower is a leading provider of demand response and energy efficiency
`
`products
`
`in Commission-jurisdictional electricity markets,
`
`including PJM
`
`Interconnection LLC. Parent companies of CPower and publicly-held companies that
`
`have a 10% or greater ownership interest in CPower include:
`
`LS Power Equity Partners IV, LP
`CCS Class A Member, LLC
`CCS Power Holdings, LLC
`CCS Power Finance Co, LLC
`
`
`
`

`

`Respectfully submitted,
`
`Howard L. Nelson
`Howard L. Nelson
`Greenberg Traurig LLP
`2101 L Street, NW
`Suite 1000
`Washington, DC 20037
`(202) 331-3163
`nelsonh@gtlaw.com
`
`Counsel for Enerwise Global
`Technologies, Inc., d/b/a CPower
`
`Dated: June 12, 2020
`
`

`

`IN THE UNITED STATES COURT OF APPEALS
`FOR THE DISTRICT OF COLUMBIA CIRCUIT
`
`Enerwise Global Technologies, Inc.,
`
`Petitioner
`
`v.
`
`Federal Energy Regulatory
`Commission,
`
`Respondent.
`
`)
`)
`)
`)
`)
`)
`)
`)
`)
`)
`)
`)
`
`Case No.
`
`CERTIFICATE OF SERVICE
`
`Pursuant to Rule 15(c) of the Federal Rules of Appellate Procedure, I hereby
`
`certify that I have this 12th day of June 2020, served copies of the foregoing Petition
`
`for Review and Corporate Disclosure Statement via the Federal Energy Regulatory
`
`Commission’s eFiling system in the proceedings below and by first class mail, postage
`
`prepaid to:
`
`Ms. Kimberly D. Bose, Secretary
`Federal Energy Regulatory Commission
`888 First Street, N.E.
`Washington, D.C. 20426
`
`Robert Solomon, Solicitor
`Federal Energy Regulatory Commission
`888 First Street, N.E.
`Washington, D.C. 20426
`
`and by e-mail on all parties on the Commission’s service list in the underlying
`
`

`

`proceeding Docket Nos. EL16-49-000, ER18-1314, and EL18-178-000, attached
`
`hereto.
`
`A file-stamped copy of this Petition for Review will be served on the
`
`respondent, pursuant to 18 C.F.R. § 385.2012, at the following address:
`
`Kimberly D. Bose
`Secretary
`Federal Energy Regulatory Commission
`888 First Street, NE
`Washington, DC 20426
`
`Respectfully submitted,
`
`Howard L. Nelson
`Howard L. Nelson
`Greenberg Traurig LLP
`2101 L Street, NW
`Suite 1000
`Washington, DC 20037
`(202) 331-3163
`nelsonh@gtlaw.com
`
`Counsel for Enerwise Global
`Technologies, Inc., d/b/a CPower
`
`

`

`Attachment 1
`Attachment 1
`
`

`

`Calpine Corp., et al. v. PJM Interconnection, L.L.C., “Order Rejecting
`Proposed Tariff Revisions, Granting in Part and Denying in Part Complaint,
`and Instituting Proceeding Under Section 206 of the Federal Power Act,” 163
`FERC ¶ 61,236 (June 29, 2018)
`
`

`

`163 FERC ¶ 61,236
`UNITED STATES OF AMERICA
`FEDERAL ENERGY REGULATORY COMMISSION
`
`
`Before Commissioners: Kevin J. McIntyre, Chairman;
` Cheryl A. LaFleur, Neil Chatterjee,
` Robert F. Powelson, and Richard Glick.
`
`Calpine Corporation, Dynegy Inc., Eastern
`Generation, LLC, Homer City Generation,
`L.P., NRG Power Marketing LLC, GenOn
`Energy Management, LLC, Carroll County
`Energy LLC, C.P. Crane LLC, Essential
`Power, LLC, Essential Power OPP, LLC,
`Essential Power Rock Springs, LLC,
`Lakewood Cogeneration, L.P., GDF SUEZ
`Energy Marketing NA, Inc., Oregon Clean
`Energy, LLC and Panda Power Generation
`Infrastructure Fund, LLC
`
` v.
`
`
`PJM Interconnection, L.L.C.
`
`PJM Interconnection, L.L.C.
`
`
`PJM Interconnection, L.L.C.
`
` Docket Nos. EL16-49-000
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`ER18-1314-000
`ER18-1314-001
`
`EL18-178-000
`(Consolidated)
`
`ORDER REJECTING PROPOSED TARIFF REVISIONS, GRANTING IN PART AND
`DENYING IN PART COMPLAINT, AND INSTITUTING PROCEEDING UNDER
`SECTION 206 OF THE FEDERAL POWER ACT
`
`(Issued June 29, 2018)
`
`
`
`
`
`I. Background ................................................................................................................ 9.
`A. PJM’s MOPR ....................................................................................................... 9.
`B. Calpine’s Complaint ........................................................................................... 15.
`C. Related Proceedings ............................................................................................ 16.
`D. PJM’s Filing ....................................................................................................... 20.
`
`Paragraph Numbers
`
`

`

`Docket No. EL16-49-000, et al.
`
`- 2 -
`
`
`II. Notice of Filings and Responsive Pleadings ............................................................ 25.
`III. Procedural Matters ................................................................................................. 30.
`IV. Section 205 Review ............................................................................................... 32.
`A. PJM’s Submission of Two Options ..................................................................... 33.
`B. Capacity Repricing ............................................................................................. 34.
`1. PJM’s Proposal ............................................................................................... 35.
`2. Comments and Protests ................................................................................... 43.
`3. Answers .......................................................................................................... 55.
`4. Commission Determination ............................................................................. 63.
`C. MOPR-Ex ........................................................................................................... 73.
`1. PJM’s MOPR-Ex Proposal .............................................................................. 74.
`2. Comments and Protests ................................................................................... 80.
`3. Answers .......................................................................................................... 92.
`4. Commission Determination ........................................................................... 100.
`V. Section 206 Action................................................................................................ 108.
`A. Docket No. EL16-49-000 ................................................................................. 109.
`1. Calpine’s Position ......................................................................................... 110.
`2. PJM’s Position .............................................................................................. 117.
`3. Intervenor Arguments .................................................................................. 118.
`B. Docket Nos. ER18-1314-000, et al. ................................................................. 128.
`1. PJM’s Position .............................................................................................. 129.
`2. Intervenors’ Positions .................................................................................... 136.
`C. Commission Determination .............................................................................. 150.
`1. PJM’s Existing Tariff ................................................................................... 151.
`2. Replacement Rate ......................................................................................... 158.
`
`
`
`
`
`
`
`
`

`

`Docket No. EL16-49-000, et al.
`
`- 3 -
`
`
`
`Over the last few years, the integrity and effectiveness of the capacity market
`
`administered by PJM Interconnection, L.L.C. (PJM) have become untenably threatened
`by out-of-market payments provided or required by certain states for the purpose of
`supporting the entry or continued operation of preferred generation resources that may
`not otherwise be able to succeed in a competitive wholesale capacity market.1 The
`amount and type of generation resources receiving such out-of-market support has
`increased substantially. What started as limited support primarily for relatively small
`renewable resources has evolved into support for thousands of megawatts (MWs) of
`resources ranging from small solar and wind facilities to large nuclear plants. As existing
`state programs providing out-of-market payments continue to grow, more states in the
`PJM region are considering providing more support to even more resources, based on an
`ever-widening scope of justifications.
`
`These subsidies enable subsidized resources to have a suppressive effect on the
`
`price of capacity procured by PJM through its capacity market, called the Reliability
`Pricing Model (RPM). Out-of-market payments, whether made or directed by a state,
`allow the supported resources to reduce the price of their offers into capacity auctions
`below the price at which they otherwise would offer absent the payments, causing lower
`auction clearing prices. As the auction price is suppressed in this market, more
`generation resources lose needed revenues, increasing pressure on states to provide out-
`of-market support to yet more generation resources that states prefer, for policy reasons,
`to enter the market or remain in operation. With each such subsidy, the market becomes
`less grounded in fundamental principles of supply and demand.
`
`This order addresses two proceedings initiated in response to increasing out-of-
`
`market support. The first is a complaint against PJM pursuant to section 206 of the
`
`
`
`
`1 Out-of-market payments include, for example, the zero-emissions credits (ZEC)
`programs and Renewable Portfolio Standards (RPS) programs on which we base our
`determination in this order that PJM’s Open Access Transmission Tariff (OATT or
`Tariff) is unjust, unreasonable, and unduly discriminatory or preferential. As explained
`below (see infra section V.C), we seek comment on the appropriate definition of out-of-
`market payments for purposes of the replacement rate. We emphasize that we cannot,
`and need not, address at this time all of the possible ways a state might provide out-of-
`market support for its preferred generation resources. We need only address the forms of
`state support that we find, in this proceeding, render the current Tariff unjust and
`unreasonable—i.e., out-of-market revenue that a state either provides, or requires to be
`provided, to a supplier that participates in the PJM wholesale capacity market.
`
`(continued ...)
`
`
`

`

`Docket No. EL16-49-000, et al.
`
`- 4 -
`
`
`Federal Power Act (FPA),2 filed by Calpine Corporation, joined by additional generation
`entities (collectively, Calpine), in Docket No. EL16-49-000 (Calpine Complaint). The
`crux of the Calpine Complaint is that PJM’s Tariff and more specifically, the Tariff’s
`Minimum Offer Price Rule (MOPR), is unjust and unreasonable because it does not
`address the impact of subsidized existing resources on the capacity market. Calpine
`proposes interim Tariff revisions for immediate implementation that would extend the
`MOPR to a limited set of existing resources, and it asks the Commission to direct PJM to
`conduct a stakeholder process to develop and submit a long-term solution.
`
`The second proceeding addressed in this order is PJM’s recent filing of proposed
`
`revisions to its Tariff, pursuant to section 205 of the FPA,3 in Docket Nos. ER18-1314-
`000, et al. PJM’s filing consists of two alternate proposals designed to address the price
`suppressing effects of state out-of-market support for certain resources.4 PJM’s first,
`preferred approach is comprised of a two-stage annual auction, with capacity
`commitments first determined in stage one of the auction and the clearing price set
`separately in stage two (Capacity Repricing). PJM’s second, alternative approach, to be
`considered only in the event the Commission determines that Capacity Repricing is
`unjust and unreasonable, revises PJM’s MOPR to mitigate capacity offers from both new
`and existing resources, subject to certain proposed exemptions (MOPR-Ex).
`
` We find, based on the record before us, that it has become necessary to address the
`price suppressive impact of resources receiving out-of-market support. PJM’s existing
`MOPR does not do so, because it applies only to new, natural gas-fired resources. The
`rationale for that narrow MOPR was that, given the short development time required to
`bring such resources on-line, they could be used to suppress capacity prices, and indeed
`certain states had proposed making out-of-market payments to facilitate the entry of new
`natural gas-fired resources.5 Although the role of the MOPR, in PJM, originally was
`
`
`
`
`2 16 U.S.C. § 824e (2012).
`
`3 16 U.S.C. § 824d (2012).
`
`4 PJM asserts that, after a lengthy stakeholder process, neither alternative could
`gain the two-thirds affirmative sector vote needed for endorsement under PJM’s rules.
`See Filing at 17.
`
`5 See PJM Interconnection, L.L.C., 135 FERC ¶ 61,022, at PP 2, 141, 153 (2011)
`(2011 PJM MOPR Order).
`
`(continued ...)
`
`
`

`

`Docket No. EL16-49-000, et al.
`
`- 5 -
`
`
`limited to deterring the exercise of buyer-side market power,6 its role subsequently
`expanded to address the capacity market impacts of out-of-market state revenues.7
`However, because the current MOPR applies only to new natural gas-fired resources,8 it
`fails to mitigate price distortions caused by out-of-market support granted to other types
`of new entrants or to existing capacity resources of any type.
`
`Based on the combined records of the Calpine Complaint proceeding and the PJM
`
`section 205 filing, we find PJM’s Tariff is unjust and unreasonable. We therefore grant
`the Calpine Complaint, in part, and sua sponte initiate an FPA section 206 proceeding in
`Docket No. EL18-178-000.9
`
`
`
`
`6 See PJM Interconnection, L.L.C., 117 FERC ¶ 61,331, at P 103 (2006) (2006
`PJM MOPR Order).
`
`7 2011 PJM MOPR Order, 135 FERC ¶ 61,022 at PP 139-43.
`
`8 Id. P 153; PJM Tariff, Attach. DD, § 5.14(h)(1).
`
`9 The Commission frequently consolidates the record in related proceedings under
`FPA sections 205 and 206. Prior MOPR reform proceedings have followed this pattern.
`See 2011 PJM MOPR Order, 135 FERC ¶ 61,022, order on reh’g, 137 FERC ¶ 61,145
`(2011) (2011 PJM MOPR Rehearing Order), aff’d sub nom. New Jersey Bd. of Pub. Utils.
`v. FERC, 744 F.3d 74 (3rd Cir. 2014) (NJBPU); ISO New England, Inc., 131 FERC ¶
`61,065 (2010), order on reh’g and clarification, 132 FERC ¶ 61,122 (2010), order on
`paper hearing, 135 FERC ¶ 61,029 (2011) (2011 ISO-NE MOPR Order), reh’g denied,
`138 FERC ¶ 61,027 (2012), aff’d sub nom. New Eng. Power Generators Ass’n v. FERC,
`757 F.3d 283 (D.C. Cir. 2014) (NEPGA). Consolidation is particularly appropriate when
`a rate proposal under FPA section 205 fails to remedy the harm identified under FPA
`section 206. See, e.g., Monongahela Power Co., 162 FERC ¶ 61,129, at P 71 (2018)
`(Monongahela). A rate proposal proceeding may also be transformed into Commission-
`initiated complaint proceeding when the record indicates that is necessary or appropriate.
`See, e.g., Western Resources, Inc. v. FERC, 9 F.3d 1568, 1579 (D.C. Cir. 1993) (Western
`Resources); Pub. Serv. Comm’n of State of N.Y. v. FERC, 866 F.2d 487, 491 (D.C. Cir.
`1989) (PSCNY). And the Commission may find that its acceptance of a rate proposal
`under FPA section 205 alters circumstances such that it becomes necessary to change
`other related rate or tariff provisions under FPA section 206. See Advanced Energy
`Management Alliance v. FERC, 860 F.3d 656, 664 (D.C. Cir. 2017) (AEMA).
`
`(continued ...)
`
`
`

`

`Docket No. EL16-49-000, et al.
`
`- 6 -
`
`
`
`Although we agree with Calpine and PJM that changes to the PJM Tariff are
`
`required, we do not accept the changes that have been proposed by either Calpine or
`PJM. Consequently, we deny the proposed remedy in the Calpine Complaint. We also
`reject both of PJM’s proposals because we find that they have not been shown to be just
`and reasonable, and not unduly discriminatory or preferential. However, we are unable to
`determine, based on the record of either proceeding, the just and reasonable rate to
`replace the rate in PJM’s Tariff.
`
`As a result, we are consolidating our newly-established proceeding in Docket No.
`
`EL18-178-000 (into which the record of Docket Nos. ER18-1314-000, et al. is
`incorporated) with the Calpine Complaint in Docket No. EL16-49-000. We are setting
`those consolidated proceedings for a paper hearing to address a proposed alternative
`approach in which PJM would modify two existing aspects of the Tariff. Specifically,
`this approach would (i) modify PJM’s MOPR such that it would apply to new and
`existing resources that receive out-of-market payments, regardless of resource type, but
`would include few to no exemptions; and (ii) in order to accommodate state policy
`decisions and allow resources that receive out-of-market support to remain online,
`establish an option in the Tariff that would allow, on a resource-specific basis, resources
`receiving out-of-market support to choose to be removed from the PJM capacity market,
`along with a commensurate amount of load, for some period of time. That option, which
`is similar in concept to the Fixed Resource Requirement (FRR) that currently exists in the
`Tariff, is referred to in this order as the FRR Alternative. Unlike the existing FRR
`construct, the FRR Alternative would apply only to resources receiving out-of-market
`support. Both aspects of the proposed replacement rate are more fully explained below.10
`
`
`
`
`10 Under PJM’s existing rules, the FRR option is available to a load-serving entity,
`at its election, to satisfy its obligation to provide unforced capacity outside of PJM’s
`capacity auction. See Reliability Assurance Agreement Among Load Serving Entities in
`the PJM Region at Schedule 8.1. In this proceeding, the Commission does not propose to
`eliminate or change the existing FRR option, but instead to add a new resource-specific
`option with distinct characteristics. However, if changes to the existing FRR option are
`necessary, we encourage PJM and its stakeholders to consider and discuss any potential
`changes.
`
`(continued ...)
`
`
`

`

`Docket No. EL16-49-000, et al.
`
`
`I.
`
`Background
`
`- 7 -
`
`PJM’s MOPR
`
`A.
`PJM established its MOPR in 2006 to address concerns that certain resources may
`
`have the ability to suppress market clearing prices by offering supply at less than a
`competitive level.11 PJM’s MOPR is designed to protect against this ability by setting a
`minimum offer level to operate as a price floor. PJM’s MOPR requires that all new, non-
`exempted natural gas-fired resources offer at or above that floor, equal to the Net Cost of
`New Entry (Net CONE) for the applicable asset class (by generator type and location). A
`seller, however, may seek a unit-specific review of its sell offer to justify an offer price
`below the default offer floor.
`
`The existing review procedures require the seller to submit a written request for
`
`review to both PJM and PJM’s Independent Market Monitor (Market Monitor) to
`demonstrate why the unit is able to offer below the default minimum price. Specifically,
`the resource must submit documentation on its fixed development, construction,
`operation, and maintenance costs.12
`
`Prior to 2011, PJM’s Tariff excluded from the MOPR new entry sponsored by a
`
`state, under certain conditions (State Mandate Exemption), namely, “any Planned
`Generation Capacity Resource being developed in response to a state regulatory or
`legislative mandate to resolve a projected capacity shortfall in the Delivery Year affecting
`that state, as determined pursuant to a state evidentiary proceeding that includes due
`notice, PJM participation, and an opportunity to be heard.” In a filing submitted by PJM,
`in Docket No. ER11-2875-000, PJM proposed to replace its State Mandate Exemption
`with a new requirement providing that a request for a MOPR exception, based on state
`policy grounds, must be approved by the Commission pursuant to a section 206
`authorization, subject to a showing that the relevant sell offer was “based on new entry
`
`
`
`
`11 See 2006 PJM MOPR Order, 117 FERC ¶ 61,331 at P 103; see also PJM
`Interconnection, L.L.C., 123 FERC ¶ 61,037 (2008); PJM Interconnection, L.L.C., 126
`FERC ¶ 61,275 (2009); 2011 PJM MOPR Order, 135 FERC ¶ 61,022; 2011 PJM MOPR
`Rehearing Order, 137 FERC ¶ 61,145; PJM Interconnection, L.L.C., 143 FERC ¶ 61,090
`(2013) (2013 PJM MOPR Order), order on reh’g & compliance, 153 FERC ¶ 61,066
`(2015), vacated & remanded sub nom. NRG Power Mktg., LLC v. FERC, 862 F.3d 108
`(D.C. Cir. 2017) (NRG).
`
`12 See PJM Tariff, Attach. DD, § 5.14(h)(5).
`
`(continued ...)
`
`
`

`

`Docket No. EL16-49-000, et al.
`
`- 8 -
`
`
`that is pursuant to a state-mandated requirement that furthers a specific legitimate state
`objective and that the Sell Offer would not lead to artificially depressed capacity prices or
`directly and adversely impact [the Commission’s] ability to set just and reasonable rates
`for capacity sales in the PJM Region or any affected Locational Deliverability Area.”
`
`In the 2011 PJM MOPR Order, the Commission accepted PJM’s proposal to
`
`eliminate its State Mandate Exemption, but rejected PJM’s proposed replacement
`mechanism as duplicative of an aggrieved entity’s right to seek section 206 relief.13 On
`rehearing, in response to petitioners’ arguments that the Commission had erred in
`approving the elimination of the State Mandate Exemption, the Commission found that
`PJM’s MOPR “does not interfere with states or localities that, for policy reasons, seek to
`provide assistance for new capacity entry if they believe such expenditures are
`appropriate for their state.”14 The Commission added that its objective was “to ensure the
`reasonableness of the wholesale interstate prices determined in the markets PJM
`administers.”15
`
`The 2011 PJM MOPR Order also required PJM to propose Tariff revisions that
`
`would allow PJM’s Market Monitor and PJM to review unit-specific cost justifications
`for sell offers that would otherwise be mitigated by PJM’s MOPR.16 On compliance, the
`Commission accepted PJM’s unit-specific review procedures, finding that PJM’s
`proposal appropriately addresses concerns from load-serving entities developing
`resources through arrangements outside of PJM’s capacity market.17
`
`In 2013, to address the effects of new, state-supported natural gas-fired entrants on
`
`its capacity market, PJM submitted proposed Tariff revisions to replace the unit-specific
`review with two categorical exemptions, namely, a competitive entry exemption and self-
`
`
`
`13 See 2011 PJM MOPR Order, 135 FERC ¶ 61,022 at P 139.
`
`14 See 2011 PJM MOPR Rehearing Order, 137 FERC ¶ 61,145 at P 89.
`
`15 Id. It is worth mentioning that the Commission, in the 2011 PJM MOPR Order,
`contemplated that the existing FRR construct in the PJM Tariff provided a mechanism for
`“states seeking full independence in resource procurement choices” to “implement a form
`of capacity procurement that complements the RPM or . . . opt out of the RPM.” See
`2011 PJM MOPR Order, 135 FERC ¶ 61,022 at n.76 and P 193.
`
`16 See 2011 PJM MOPR Order, 135 FERC ¶ 61,022 at P 121.
`
`17 See 2011 PJM MOPR Rehearing Order, 137 FERC ¶ 61,145 at P 242.
`
`(continued ...)
`
`
`

`

`Docket No. EL16-49-000, et al.
`
`- 9 -
`
`
`supply exemption. While the Commission initially accepted those exemptions, subject to
`the condition that PJM retain the unit-specific review process, the United States Court of
`Appeals for the District of Columbia Circuit found, in July 2017, that the Commission
`exceeded its FPA section 205 authority in modifying PJM’s proposal.18 Accordingly, the
`Court vacated and remanded the relevant Commission orders. On remand, the
`Commission rejected PJM’s competitive entry exemption and self-supply exemption,
`effective December 8, 2017.19 At present, unit-specific review is the only way for a new
`natural gas-fired resource subject to PJM’s MOPR to obtain an exemption from that rule.
`B.
`In March 2016, Calpine filed its complaint, asserting that PJM’s MOPR is unjust
`
`and unreasonable because it allows for the artificial suppression of prices in PJM’s
`capacity market, as caused by below-cost offers from existing resources whose continued
`operation is being subsidized by state-approved out-of-market payments.20 Calpine cites
`the out-of-market payments requested by certain resources, pursuant to Ohio
`authorizations that, as explained below, have since been withdrawn by the entities
`seeking these out-of-market payments. Calpine also cites the Illinois ZECs program,21 as
`evidence of a state subsidy that will have a price suppressing effect on PJM’s capacity
`
`Calpine’s Complaint
`
`
`
`
`18 NRG, 862 F.3d at 117.
`
`19 See PJM Interconnection, L.L.C., 161 FERC ¶ 61,252 (2017) (NRG Remand
`Order) and PJM Interconnection, L.L.C., Docket No. ER13-535-006 (Feb. 23, 2018)
`(delegated letter order accepting compliance filing).
`
`20 Calpine Complaint at 2. Calpine also proposed interim Tariff revisions
`governing PJM’s procurements for the 2019-20 and 2020-21 delivery years.
`
`21 See Illinois 99th Gen. Assemb. S.B. 2814 (Dec. 7, 2016). Calpine argues that,
`under this legislation, out-of-market state revenues will be provided to certain existing
`nuclear-powered generation units that would otherwise exit PJM’s capacity market.
`Calpine explains that, under this law, the Illinois Power Agency is directed to procure, on
`behalf of the state’s load-serving entities, contracts for ZECs with 10-year terms
`commencing June 1, 2017. Calpine states that the new law defines a ZEC as a credit that
`represents the environmental attributes of one MW hour of energy produced from a zero
`emissions facility, as defined to include those facilities that are: (1) fueled by nuclear
`power; and (2) interconnected with PJM or the Midcontinent Independent System
`Operator, Inc. (MISO). Calpine Amended Complaint at 6-9.
`
`(continued ...)
`
`
`

`

`Docket No. EL16-49-000, et al.
`
`- 10 -
`
`
`market, absent the MOPR revision it seeks.22 As a remedy, Calpine proposes interim
`Tariff revisions for immediate implementation that would extend the MOPR to a limited
`set of existing resources. As a long-term remedy, Calpine urges the Commission to
`require PJM to propose Tariff revisions addressing this matter.
`
`Related Proceedings
`
`C.
`In May 2017, Commission staff convened a technical conference, in Docket No.
`
`AD17-11-000, to explore the impact of out-of-market support for specific resources or
`resource types in the regional markets operated by ISO New England Inc. (ISO-NE), the
`New York Independent System Operator, Inc. (NYISO), and PJM. Following the
`discussion at the technical conference, staff’s notice requesting comments outlined five
`potential paths forward: (1) a limited, or no MOPR approach; (2) an approach that would
`accommodate resources receiving out-of-market support; (3) retention of the status quo;
`(4) an approach that would balance state policy goals and the needs of a centralized
`capacity market; and (5) an extension of the MOPR to apply to both new and existing
`resources. PJM, in its comments, stated that it had convened a stakeholder proceeding to
`consider these matters, as a preliminary step to an FPA section 205 filing.
`
` On March 9, 2018, the Commission issued an order accepting ISO-NE’s proposal
`to modify its wholesale capacity market to better accommodate state actions to procure
`certain resources outside of ISO-NE’s wholesale electric markets – a mechanism known
`as Competitive Auctions with Sponsored Policy Resources (CASPR).23 In that order, the
`Commission outlined a series of first principles for capacity markets.24
`
` On May 31, 2018, following PJM’s submission of its FPA section 205 filing in
`Docket Nos. ER18-1314-000, et al., CPV Power Holdings, L.P., Calpine, and Eastern
`Generation, LLC (Eastern Generation) (collectively, CPV), filed a complaint against PJM
`
`
`
`22 Calpine Amended Complaint at 10-11.
`
`23 ISO New England Inc., 162 FERC ¶ 61,205 (2018) (CASPR Order).
`
`24 Id. at P 21 (“A capacity market should facilitate robust competition for capacity
`supply obligations, provide price signals that guide the orderly entry and exit of capacity
`resources, result in the selection of the least-cost set of resources that possess the
`attributes sought by the markets, provide price transparency, shift risk as appropriate
`from customers to private capital, and mitigate market power. Ultimately, the purpose of
`basing capacity market constructs on these principles is to produce a level of investor
`confidence that is sufficient to ensure resource adequacy at just and reasonable rates.”).
`
`(continued ...)
`
`
`

`

`Docket No. EL16-49-000, et al.
`
`- 11 -
`
`
`in Docket No. EL18-169-000. CPV seeks Commission action under section 206, and a
`directive requiring PJM to adopt a “clean” MOPR, without exclusions or exemptions,
`applicable to both new and existing resources.25
`
` CPV argues that state subsidies represent an imminent threat to PJM’s capacity
`market.26 CPV further asserts that a “clean” MOPR is required to effectively address the
`impact of these subsidies and that PJM’s proposed self-supply, public entity, and RPS
`exemptions would prevent MOPR-Ex from adequately addressing the problem.27 CPV
`also proposes to eliminate the competitive exemption proposed in MOPR-Ex, because, it
`claims, only unsubsidized resources, which would not be subject to MOPR-Ex, would be
`eligible for the exemption.28 Finally, CPV urges the Commission to require PJM to
`modify the definition of Material Subsidy, as defined below, to cover not only state
`subsidies, but also federal subsidies or other support granted after the date of the
`complaint.29 The CPV complaint remains pending.
`D.
`
`PJM’s Filing
`
`PJM pr

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket