throbber

`UNITED STATES OF AMERICA
`BEFORE THE
`FEDERAL ENERGY REGULATORY COMMISSION
`
`
`
`
`
`Pacific Gas and Electric Company ) Docket No. ER16-2320-002
`
`
`
`
`
`
`REPLY BRIEF OF THE COMMISSION TRIAL STAFF
`
`
`
`
`
`
`
`
`
`
`
`
` Edith A. Gilmore
` Commission Staff Counsel
`
`
`
`
`
`
`
`
`Washington, D.C.
`April 17, 2018
`
`
`
`
`
`
`
`
`TABLE OF CONTENTS
`
`INTRODUCTION ............................................................................................................... 1
`ARGUMENT ....................................................................................................................... 2
`I. Rate of Return on Equity (ROE) .............................................................................. 2
`a. Whether PG&E’s proposed ROE is just and reasonable .............................. 2
`b. Whether anomalous market conditions exist and, if so,
`whether these conditions affect the placement of the
`authorized ROE within the range of reasonable returns ............................... 9
`II. Cost of Long-Term Debt ........................................................................................ 10
`a. Whether PG&E’s proposed cost of debt is just and reasonable .................. 10
`b. Whether PG&E’s proposal to use net proceeds to calculate its
`long-term debt costs is appropriate ............................................................. 11
`c. Whether PG&E has appropriately forecasted its split of 10-
`year and 30-year bond issuances to estimate the cost of
`PG&E’s long-term debt ............................................................................... 13
`
`d. Whether PG&E has appropriately forecasted interest rate
`estimates included in its calculated cost of long-term debt ......................... 13
`
`III. Capital Structure ..................................................................................................... 14
`a. Whether PG&E’s proposed capital structure and resulting rate
`of return are just and reasonable ................................................................. 14
`b. Whether PG&E has included San Bruno-related costs in the
`equity ratio of its proposed capital structure ............................................... 15
`IV. Depreciation ........................................................................................................... 16
`a. Whether PG&E’s proposed depreciation rates are just and
`reasonable .................................................................................................... 16
`b. Whether the average service lives and dispersion patterns (i.e.
`Iowa Curves) proposed by PG&E are reasonable ....................................... 17
`
`c. Whether PG&E’s proposed net salvage and cost of removal
`ratios are appropriate ................................................................................... 27
`d. Whether PG&E’s proposed accounting for accumulated
`depreciation is appropriate .......................................................................... 34
`
`e. Whether PG&E has appropriately reflected the composite
`depreciation rate for land rights .................................................................. 34
`
`V. Capital Additions .................................................................................................... 34
`
`
`
`
`
`
`
`ii
`
`a. Whether PG&E’s capital additions forecast is just and
`reasonable .................................................................................................... 34
`b. Whether PG&E has included any imprudent capital costs in
`the TO18 Transmission Revenue Requirement ........................................... 36
`c. CPUC PROPOSED ADDITIONAL SUB-ISSUE: Other
`capital additions issues, including, without limitation, whether
`PG&E’s procedures related to capital additions, such as
`planning and prioritization, recordkeeping, cost estimating,
`and project cost containment are appropriate .............................................. 36
`VI. Common, General and Intangible (CGI) Plant........................................................ 37
`a. Whether PG&E’s methodology for allocating CGI plant costs
`is appropriate ............................................................................................... 37
`VII. Operation and Maintenance (O&M) Expenses ....................................................... 40
`a. Whether PG&E’s O&M expense forecast is just and
`reasonable .................................................................................................... 40
`VIII. Administrative and General (A&G) Expenses ........................................................ 42
`a. Whether PG&E’s A&G expense forecast is just and
`reasonable .................................................................................................... 42
`b. Whether it is appropriate to include all or part of certain
`enterprise-wide department expenses, such as Short Term
`Incentive Pay, Enterprise Records and Information
`Management, Enterprise Corrective Action Program, Edison
`Electric Institute membership dues, and Pension expenses in
`PG&E’s TO18 revenue requirement ........................................................... 44
`IX. Materials and Supplies (M&S) Escalation Rate...................................................... 44
`a. Whether PG&E’s proposed escalation factors used in
`developing forecasts of M&S expense in its O&M and A&G
`expenses are appropriate .............................................................................. 44
`X. Allocators ............................................................................................................... 44
`a. Whether PG&E has appropriately calculated its line-of-
`business and network transmission labor allocators ................................... 44
`XI. Sales Forecast ......................................................................................................... 46
`a. Whether PG&E’s proposed gross load forecast results in just
`and reasonable rates ..................................................................................... 46
`b. Whether PG&E’s proposed forecast of Helms pumping load
`results in just and reasonable rates .............................................................. 50
`
`
`
`
`
`
`
`iii
`
`XII. Other ..................................................................................................................... 53
`a. Whether PG&E should be allowed to include certain non-
`capital items in rate base, including: ........................................................... 53
`i. Habitat Conservation Plan (HCP) .................................................... 53
`ii. Alviso (environmental) credit ........................................................... 55
`iii. Working cash .................................................................................... 56
`iv. Other receivables .............................................................................. 58
`b. Whether PG&E should be required to include certain items in
`rate base, including: ..................................................................................... 60
`i. Unfunded reserves ............................................................................ 60
`ii. ADIT associated with abandoned projects in its rate
`base when PG&E includes those abandoned projects in
`its rate base ....................................................................................... 61
`c. Whether PG&E has included any items as prepaid expenses in
`rate base that should not be included as prepaid expenses in
`rate base ....................................................................................................... 61
`d. Whether PG&E has used a reasonable methodology to
`functionalize and allocate prepaid expenses determined to be
`appropriately included in rate base to Network Transmission
`customers ..................................................................................................... 62
`e. Whether PG&E’s forecast of Non-Tariffed New Products and
`Services (NP&S) expenses and revenue is just and reasonable .................. 63
`f. How PG&E’s self-acknowledged errors in its filing should be
`corrected ...................................................................................................... 66
`g. What adjustments to PG&E’s franchise fee expense are
`appropriate to reflect the impact of any authorized
`adjustments to PG&E’s cost of service ........................................................ 67
`h. Whether there are any other costs that are improperly included
`by PG&E in its TO18 Transmission Revenue Requirement ....................... 67
`CONCLUSION ................................................................................................................. 68
`
`Appendix of Acronyms…………………………………………………………………..69
`
`
`
`
`
`
`
`iv
`
`TABLE OF AUTHORITIES
`Court Cases
`
`Bluefield Water Works and Improvement Co. v. Pub. Serv. Comm’n of W. Va.,
` 262 U.S. 679, (1923) ..................................................................................................... 2
`
`Federal Power Comm’n v. Hope Natural Gas Co.,
`U.S. 591 (1944) ................................................................................................................... 2
`
`Administrative Proceedings
`
`Association of Business Advocating Tariff Equity, et al.
` v. Midcontinent Independent System Operator,
` 156 FERC ¶ 61,234 (2016) ........................................................................................ 4, 7
`
`Boston Edison Co., Opinion No. 299,
` 42 FERC ¶ 61,374 (1988) ............................................................................................ 48
`
`Consumers Energy Co., Opinion No. 429,
` 85 FERC ¶ 61,100 (1998) .............................................................................................. 6
`
`Delmarva Power and Light Co., Opinion No. 185,
` 24 FERC ¶ 61,199 (1983) ............................................................................................ 49
`
`Ind. and Mich. Mun. Disrib. Ass’n v. Ind. Mich. Power Co.,
` 59 FERC ¶ 61,260 (1992) ............................................................................................ 48
`
`Kern River Gas Transmission Co., Opinion No. 486-B,
` 126 FERC ¶ 61,034 (2009) ............................................................................................ 6
`
`Kern River Gas Transmission Co., Opinion No. 486,
` 117 FERC ¶ 61,077 (2006) .......................................................................................... 37
`
`Martha Coakley, Mass. Attorney General, et al. v. Bangor Hydro-Electric Co., et al.,
` Opinion No. 531, 147 FERC ¶ 61,234 (2014), order on paper hearing,
` Opinion No. 531-A, 149 FERC ¶ 61,032 (2014), order on reh’g,
` Opinion No. 531-B, 150 FERC ¶ 61,165 (2015), vacated and remanded sub nom.
` Emera Maine v. FERC, 854 F.3d 9, 17 (D.C. Cir. 2017). .................................... passim
`
`Minnesota Power and Light Co., Opinion No. 20,
` 4 FERC ¶ 61,116 (1978), aff’d Opinion No. 20-A, 5 FERC ¶ 61,091 (1978) ............. 38
`
`
`
`
`
`
`
`
`v
`
`New England Power Co., Opinion No. 295,
` 42 FERC ¶ 61,016 (1988) ............................................................................................ 55
`
`Pacific Gas and Electric Co.,
` 156 FERC ¶ 61,238 (2016) ............................................................................................ 2
`
`Public Service Co. of Indiana, Opinion No. 783-A,
` 57 FPC 1173 (1977), affirmed, Public Service Co. of Indiana v. FERC,
` 575 F. 2d 1204 (7th Cir. 1978). ................................................................... 35, 41, 43, 49
`
`Southwestern Pub. Serv. Co., Opinion No. 339,
` 49 FERC ¶ 61,354 (1989) ............................................................................................ 48
`
`Sys. Energy Res., Inc., Opinion No. 446,
` 92 FERC ¶ 61,119 (2000); order on reh’g, Opinion No. 446-A,
` 96 FERC ¶ 61,165 (2001) ...................................................................................... 12, 13
`
`Statutes
`
`
`18 C.F.R. § 385.706(b)(iii) (2017) .............................................................................. 47, 63
`
`18 CFR Pt. 101 (2017) ....................................................................................................... 20
`
`Other
`
`Public Utility Depreciation Practices, published by the National Association of
`Regulatory Utility Commissioners in 1996……………………………………………. .19
`
`
`
`
`
`
`
`
`UNITED STATES OF AMERICA
`BEFORE THE
`FEDERAL ENERGY REGULATORY COMMISSION
`
`
`
`Pacific Gas and Electric Company ) Docket No. ER16-2320-002
`
`
`
`REPLY BRIEF OF THE COMMISSION TRIAL STAFF
`
`To: The Honorable David H. Coffman
` Presiding Administrative Law Judge
`Pursuant to Rule 706 of the Commission’s Rules of Practice and Procedure,1 and
`the Presiding Judge’s procedural orders,2 the Commission Trial Staff (Trial Staff)
`submits its Reply Brief in the above-captioned proceeding.
`INTRODUCTION
`On March 15, 2018, Initial Briefs were filed by Pacific Gas and Electric Company
`(PG&E); the California Public Utilities Commission (CPUC); the Cities of Anaheim,
`Azusa, Banning, Colton, Pasadena, and Riverside, California (Six Cities); the California
`Department of Water Resources State Water Project (SWP); the Transmission Agency of
`
`1 18 C.F.R. § 385.706 (2017).
`2 “Order Establishing Procedural Schedule,” Docket No. ER16-2320-002 (March
`31, 2017); “Order Adopting Rules for the Conduct of the Hearing,” at P 59, Docket No.
`ER16-2320-002 (Dec. 4, 2017).
`
`
`
`
`
`
`
`Docket No. ER16-2320-002 2
`Northern California (TANC); and Trial Staff.3 Trial Staff primarily responds to the
`arguments set forth by PG&E.
`The issues addressed in this case arise out of PG&E’s eighteenth Transmission
`Owner Tariff filing (TO18), proposing a wholesale base transmission revenue
`requirement (Wholesale Base TRR) of $1.705 billion and a retail base transmission
`revenue requirement (Retail Base TRR) of $1.718 billion. On September 30, 2016, the
`Commission accepted PG&E’s proposed rates, suspended them for five months (to
`become effective March 1, 2017, subject to refund) and set the matter for hearing and
`settlement procedures.
`4
`ARGUMENT
`
`I. Rate of Return on Equity (ROE)
`
`a. Whether PG&E’s proposed ROE is just and reasonable
`
`PG&E generally alleges that the intervenors and Trial Staff’s recommended base
`ROE is too low to satisfy the Hope and Bluefield standard.5 PG&E argues that: (1) the
`median value obtained by employing the DCF methodology to determine an appropriate
`
`3 On March 16, 2018, Trial Staff submitted an errata to its Initial Brief that was
`accepted by the Presiding Judge. “Order Granting Motion to Accept Corrected Initial
`Brief of Commission Trial Staff,” Docket No. ER16-2320-002 (March 23, 2018).
`4 Pacific Gas and Electric Co., 156 FERC ¶ 61,238 (2016).
`5 PG&E Initial Br. at 3-5 (citing Federal Power Comm’n v. Hope Natural Gas
`Co., 320 U.S. 591, 603 (1944) (Hope); Bluefield Water Works and Improvement Co. v.
`Pub. Serv. Comm’n of W. Va., 262 U.S. 679, 692-93 (1923) (Bluefield) (collectively,
`Hope and Bluefield)).
`
`
`
`
`
`
`
`Docket No. ER16-2320-002 3
`base ROE will not conform to the Commission’s findings in Opinion Nos. 531 and 551;6
`(2) the proxy group used by the intervenors and Trial Staff is too small and should
`include Avangrid;7 (3) alternative benchmarks show that use of the median would not
`produce a just and reasonable result for PG&E;8 (4) PG&E’s ROE should not go below
`CPUC-approved ROEs;9 (5) the intevenors and Trial Staff ignore transmission risk;10 and
`(6) the intervenors and Trial Staff fail to consider model risk or the use of a model other
`than the DCF methodology.11 Each of these assertions and criticisms of Trial Staff’s
`recommended base ROE are unfounded. As discussed below, Trial Staff’s application of
`the two-step DCF methodology is appropriate and consistent with Commission
`precedent.
`First, contrary to PG&E’s contention, the results obtained by the intervenors and
`Trial Staff do not fall far below the level that investors would expect and require under
`Hope and Bluefield. PG&E argues that the Commission found in Opinion No. 531
`12 that
`the midpoint of the DCF (9.39 percent) was too low to satisfy Hope and Bluefield, and
`
`6 PG&E Initial Br. at 3-5.
`7 Id. at 5-6, 9-10.
`8 Id. at 7.
`9 Id. at 9.
`10 Id. at 8-9.
`11 Id. at 10-12.
`12 Martha Coakley, Mass. Attorney General, et al. v. Bangor Hydro-Electric Co.,
`et al., Opinion No. 531, 147 FERC ¶ 61,234 (2014), order on paper hearing, Opinion
`No. 531-A, 149 FERC ¶ 61,032 (2014), order on reh’g, Opinion No. 531-B, 150 FERC ¶
`61,165 (2015), vacated and remanded sub nom. Emera Maine v. FERC, 854 F.3d 9, 17
`(D.C. Cir. 2017).
`
`
`
`
`
`
`
`Docket No. ER16-2320-002 4
`that, later, the Commission similarly found in Opinion No. 55113 that the DCF midpoint
`of 9.29 percent did not meet the Hope and Bluefield standard. PG&E relies upon the
`Commission decision in that case to consider alternative benchmarks as well as ROE’s
`approved by state commissions to determine whether an upward adjustment to the central
`tendency of the DCF results was necessary. Thus, PG&E suggests that the intervenors
`and Trial Staff disregarded the Commission’s guidance in Opinion Nos. 531 and 555 and
`used only the median result in recommending base ROEs for PG&E that are far below
`the levels rejected by the Commission in those opinions. This is an incorrect
`interpretation of those opinions.
`Importantly, Commission precedent continues to support the use of its two-step
`DCF methodology to evaluate whether PG&E’s proposed ROE is just and reasonable.
`Under the Hope and Bluefield standard, the rate of return allowed for a public utility
`should be sufficient to: (1) maintain the financial integrity of the enterprise; (2) enable
`the company to attract new capital; and (3) provide a return to the common equity owner
`that is commensurate with returns on investments in other enterprises of corresponding
`risk. Trial Staff witness Green explains how the Commission’s DCF methodology was
`designed to meet the Hope and Bluefield standard.
`14 Further, as explained in Trial Staff’s
`Initial Brief (at 13-21), he properly applied each and every element of the adopted
`methodology. Accordingly, the application of the Commission’s DCF method
`
`13 Association of Business Advocating Tariff Equity, et al. v. Midcontinent
`Independent System Operator, 156 FERC ¶ 61,234 (2016) (Opinion No. 551).
`14 Ex. S-0006 at 10:8-13; 13:18-14:12; 15:1-25.
`
`
`
`
`
`
`
`Docket No. ER16-2320-002 5
`demonstrates that PG&E’s proposed ROE is not just and reasonable and exceeds the level
`required to satisfy this standard.
`Moreover, Opinion No. 531 adopted the two-step DCF methodology for use in
`setting the ROE for electric utilities.15 Although that opinion was subsequently vacated,
`the vacatur did not address the two-step methodology, nor did the parties in the current
`proceeding reject the use of the two-step DCF methodology. In addition, the placement
`above the central tendency in that case was based on a finding of the presence of
`anomalous capital market conditions. As discussed below and in Trial Staff’s Initial
`Brief (at 45-59), the record in this proceeding does not support such a finding during the
`relevant study period and, thus, there is no need to review alternative benchmarks. The
`Commission has historically found that for single entities, such as PG&E, the best
`measure of central tendency is the median. The Opinion No. 531 series of orders does
`not alter that determination.
`Second, Trial Staff witness Green properly determined the proxy group that should
`be used in this proceeding. Contrary to PG&E’s assertions, it is not too small and
`Avangrid should not be included. PG&E contends that using a limited group of
`companies increases the potential for error in the reliability of a DCF analysis and, for
`that reason, PG&E witness McKenzie recommended a refinement of the proxy group
`criteria to allow companies that meet either the Moody’s or the S&P credit rating criteria
`to be included in the proxy group. As explained in Trial Staff’s Initial Brief (at 24), this
`
`15 Opinion No. 531 at P 31.
`
`
`
`
`
`
`
`Docket No. ER16-2320-002 6
`is inconsistent with Commission precedent. Opinion No. 531 requires proxy group
`companies to meet both the Moody’s and the S&P credit rating.16 The test is whether the
`credit rating of the proxy group company under either Moody’s or S&P is one notch
`above or below the credit rating of PG&E. If so, the company should be eliminated from
`the proxy group.
`Moreover, as a whole, Mr. Green’s proxy group is sufficiently large to eliminate
`or significantly reduce measurement error, thereby producing a rate of return on equity
`estimate for PG&E that is representative of its true cost. Trial Staff explained in its
`Initial Brief that the Commission has accepted proxy groups with as few as three
`companies, and has also stated that “a proxy group should consist of at least four, and
`preferably at least five members, if representative members can be found.”17 Mr. Green’s
`proxy group of eight companies is twice that size, so it is clearly large enough to
`eliminate or severely reduce measurement error.
`In addition, Avangrid should not be included in the proxy group because it simply
`fails the Commission’s credit rating screening criteria. As mentioned above, it must meet
`both Moody’s and S&P’s credit ratings bands. Avangrid was rated Baa1 during the data
`
`16 Opinion No. 531 at P 107.
`17 See Trial Staff Initial Br. at 19-20 (quoting Kern River Gas Transmission Co.,
`Opinion No. 486-B, 126 FERC ¶ 61,034, at P 104 (2009) (Kern River). See also
`Consumers Energy Co., Opinion No. 429, 85 FERC ¶ 61,100, at 61,361 (1998)
`(Commission adopted proxy group of four companies, rejecting arguments that a proxy
`group of four companies was too small).
`
`
`
`
`
`
`
`Docket No. ER16-2320-002 7
`period in the record. Because PG&E was rated A2 during this period, Avangrid falls
`outside of the notch band for PG&E of A1 to A3.18
`Third, PG&E’s reliance on its alternative benchmarks as support for its position
`that applying the median of the results of the DCF methodology would not produce a just
`and reasonable ROE for PG&E is unfounded. As explained in Trial Staff’s Initial Brief
`(at 33-45), PG&E’s alternative ROE benchmarks are flawed and unreliable. In Opinion
`Nos. 531 and 551, the Commission emphasized that it was not departing from relying on
`the DCF methodology but was only looking to other record evidence to inform the
`placement of the ROE within the zone of reasonableness provided by the DCF
`methodology due to its finding of anomalous capital market conditions. 19 Thus, only if
`anomalous conditions exist would it be necessary to review state-allowed ROEs and other
`alternative methods as a tool for corroborating the placement of the ROE. As discussed
`below, Trial Staff does not agree that anomalous market conditions existed during the
`relevant six-month DCF data period.
`Fourth, PG&E’s reliance on CPUC-approved ROEs is misplaced. The fact that
`PG&E’s state-approved ROE for the portion of its business under the jurisdiction of the
`CPUC (10.4 percent for 2017) is not controlling and should not be considered by this
`Commission unless there is a finding of anomalous capital market conditions. In this
`case, there should be no such finding. However, even if the Commission were to find
`
`18 See also Trial Staff Initial Br. at 27.
`19 Opinion No. 531 at P 146; Opinion No. 531-B at PP 91, 103, 120; Opinion No.
`551 at P 137.
`
`
`
`
`
`
`
`Docket No. ER16-2320-002 8
`anomalous capital market conditions in this proceeding, it would look to average state
`ROEs for all utilities during a specific time period, and not simply rely upon PG&E’s
`state-approved ROE.
`Fifth, PG&E’s contention that the intervenors and Trial Staff ignore transmission
`risk lacks merit. The record shows that the companies included in the proxy group have
`significant transmission, as well as unregulated business operations that are riskier than
`transmission or distribution and are automatically considered in the DCF results of those
`companies.20
`Lastly, PG&E’s assertion that the intervenors and Trial Staff fail to concede that
`model risk is any concern and its vaulted criticism of Trial Staff witness Green’s
`unwavering and consistent practice of applying the Commission’s DCF methodology
`“since at least the late 1990s”21 is off base. It bears repeating here that there are no
`anomalous market conditions and, thus, there is no need to consider alternative ROE
`analyses. Even so, as previously discussed, the Commission continues to require and has
`not departed from its use of the DCF methodology in establishing a reasonable ROE. 22
`Also, as pointed out by Six Cities’ witness Solomon on re-direct examination, the CAPM
`and Risk Premium models are more affected by anomalous markets that may undermine
`confidence in the model’s results. This is because interest rates and utility bond yields,
`which are identified by PG&E witness Quackenbush as being affected by anomalous
`
`20 See Ex. S-0009 at 385-392.
`21 PG&E Initial Br. at 12.
`22 Opinion No. 531 at P 146.
`
`
`
`
`
`
`
`Docket No. ER16-2320-002 9
`market conditions, are a direct input into those models, whereas interest rates are not an
`input to the DCF model.23
`b. Whether anomalous market conditions exist and, if so, whether these
`conditions affect the placement of the authorized ROE within the range of
`reasonable returns
`
`PG&E contends that the market conditions that the Commission found to be
`anomalous in Opinion Nos. 531 and 551 continue to exist today.24 Trial Staff disagrees.
`PG&E’s reliance on Opinion Nos. 531 and 551 is misplaced. As fully explained in Trial
`Staff’s Initial Brief (at 45-59), anomalous market conditions do not currently exist, based
`on an additional two and one-half years of data and information that is now available and
`an analysis of economic and capital market conditions. Trial Staff witness Green
`explains how conditions differ today from the record presented in the Opinion No. 551
`proceeding. Despite anticipation that bond yields would rise shortly after the Federal
`Reserve phased out its bond buying program, in October of 2014, bond yields have not
`risen. Also, the ten-year Treasury bond yield has fluctuated between about 1.5 and 4
`percent since 2008, and since 2012, Moody’s public utility bond index has traded in a
`relatively tight range of roughly 3.9 percent to 4.5 percent. Therefore, sufficient time has
`passed, nearly ten years, that a relatively low interest rate environment, by historical
`standards, can no longer be considered anomalous and should instead be considered a
`
`23 Ex. PGE-0033 at 11:12-13.
`24 PG&E Initial Br. at 12-15.
`
`
`
`
`
`
`
`Docket No. ER16-2320-002 10
`“new normal” going forward. Accordingly, there is no justification in this case to set
`ROE above the median of the zone of reasonableness.
`II. Cost of Long-Term Debt
`
`a. Whether PG&E’s proposed cost of debt is just and reasonable
`
`PG&E contends that it made a reasonable forecast of the anticipated cost of debt it
`would incur for debt issuances it expected to make during 2017 (Period II). PG&E
`claims that it developed the forecast in the spring of 2016, based on end-of-year data
`from 2015 (Period I), and then made its best estimate of expected costs of long-term debt
`that would be incurred during the remainder of 2016 and calendar year 2017.
`25 PG&E
`argues that the intervenors and Trial Staff’s criticisms of the forecast were based, in part,
`on information that only became available after PG&E filed its case in this proceeding
`and that, in doing so, ignores the Commission’s policy that forecasts should be based on
`whether they were “reasonable when made.”26 Trial Staff disagrees.
`PG&E filed its rebuttal testimony with some updates and, thus, clearly could have
`updated their cost of debt calculations at that time to conform with current and forecasted
`interest rates at that time. PG&E’s continued use of outdated forecasts at the time of the
`rebuttal testimony when updated information was available overstates the true costs and
`shows that the original forecasts were not reasonable when made. As explained in Trial
`Staff’s Initial Brief (at 60-61), Mr. Green calculated PG&E’s long-term debt cost net
`
`25 PG&E Initial Br. at 16-17.
`26 Id.
`
`
`
`
`
`
`
`Docket No. ER16-2320-002 11
`proceeds data as of December 31, 2016,27 and then analyzed updated information that
`reflects new debt issuances that occurred from January 1, 2017 through May 25, 2017.
`He also included PG&E’s forecasts of upcoming debt issuances through December 31,
`2017. He also modified the coupon rates for the 10-year and 30-year bonds, which
`PG&E planned to issue in the fourth quarter of 2017 to be 3.30 percent and 4.00 percent,
`respectively, to reflect actual coupon rates observed for debt issuances which occurred
`most recently (in March 2017) for bonds of the same durations. Mr. Green’s use of the
`updated information shows that PG&E’s estimate of its long-term debt cost was not
`reasonable when made. Accordingly, Trial Staff’s recommended cost of long-term debt
`for Period II for PG&E of 4.95 percent should be adopted.
`b. Whether PG&E’s proposal to use net proceeds to calculate its long-term
`debt costs is appropriate
`
`PG&E recognizes that the Commission has opted in the past to use the gross
`proceeds of debt issuances to calculate its long-term debt costs. However, PG&E also
`explains how the use of gross proceeds is not explicitly required by the Commission’s
`regulations and that this method is fundamentally flawed.
`28 Trial Staff agrees that the use
`of net proceeds to calculate its recommended cost of long-term debt for PG&E is
`appropriate.29 TANC, on the other hand, contends that the use of gross proceeds from
`debt issuances is appropriate to calculate the debt component of capital structure, relying
`
`27 Ex. S-0006 at 70:3-5; Ex. S-0007 at 13.
`28 PG&E Initial Br. at 20-21.
`29 Trial Staff Initial Br. at 61-62 (citing Ex. S-0006 at 70:3-5, 140:10-142:8).
`
`
`
`
`
`
`
`Docket No. ER16-2320-002 12
`on the Commission’s decision in System Energy Resources, Inc. (SERI).30 As discussed
`below, TANC’s reliance upon SERI is misplaced.
`At the outset, TANC appears to misunderstand the issue set forth in this section.
`The issue is whether PG&E’s proposal to use net proceeds to calculate its long-term debt
`costs is appropriate, not whether the use of such method is appropriate to calculate the
`debt component of its proposed capital structure. The rulings in SERI upon which TANC
`relies address the use of gross proceeds for long-term debt principal outstanding to
`calculate the debt component of the capital structure.31 Opinion No. 446 addressed the
`following two proposed changes: (1) a change to the “calculation of the cost rate of debt
`by switching from the yield-to-maturity method to the embedded cost method”; and (2) a
`change to the “calculation of the long-term debt ratio by switching from use of the gross
`proceeds of debt method (i.e., the total principal outstanding of long-term debt) to the net
`proceeds of debt method (i.e., gross proceeds less unamortized premium, discount,
`expenses, and losses).”
`32 The Commission approved SERI’s switch to the embedded cost
`method for determining the cost rate of long-term debt, but rejected the proposed switch
`to a net proceeds method for deriving the long-term debt ratio.
`
`30 TANC Initial Br. at 67-70 (citing Sys. Energy Res., Inc., Opinion No. 446, 92
`FERC ¶ 61,119 at 61,447-49 (Opinion No. 446) (2000); order on reh’g, Opinion No.
`446-A, 96 FERC ¶ 61,165 at 61,740-41 (Opinion No. 446-A) (2001) (SERI).
`31 TANC Initial Br. at 67-68 (citing Opinion No. 446 at 61,447-49; Opinion No.
`446-A at 61,740-41).
`32 Opi

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket