`
`
`
`
`
`
`
`UNITED STATES OF AMERICA
`BEFORE THE
`FEDERAL ENERGY REGULATORY COMMISSION
`
`
`)
`)
`
`
`Docket Nos. ER24-98-000
` ER24-99-000
`(Not Consolidated)
`
`PJM Interconnection, L.L.C.
`PJM Interconnection, L.L.C.
`
`
`
`
`COMMENTS OF PINE GATE RENEWABLES, LLC
`ON PJM CRITICAL ISSUE FAST PATH FILINGS
`
`
`Pursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy
`
`Regulatory Commission (“Commission”),1 Pine Gate Renewables, LLC (“Pine Gate”) submits
`
`these comments in the above captioned proceedings on PJM Interconnection, L.L.C.’s (“PJM”)
`
`October 13, 2024 filings regarding the Market Seller Offer Cap (“MSOC”)2 and other capacity
`
`market reforms3 (collectively, “October 13 Filings”). As discussed further below, Pine Gate is
`
`largely supportive of the October 13 Filings and believes they are a just and reasonable
`
`improvement over PJM’s current capacity market rules. However, Pine Gate urges the
`
`Commission to reject, as PJM concedes would be permissible under NRG Power Mktg., LLC v.
`
`FERC,4 PJM’s proposed revisions regarding the eligibility of Performance Payments. In addition,
`
`Pine Gate urges the Commission to require PJM to provide greater clarity regarding PJM’s
`
`
`18 C.F.R. § 385.213 (2022).
`Proposed Enhancements to PJM’s Capacity Market Rules - Market Seller Offer Cap, Performance Payment
`Eligibility, and Forward Energy and Ancillary Service Revenues, Docket No. ER24-98-000 (Oct. 13, 2023)
`(“MSOC Filing”).
`Capacity Market Reforms to Accommodate the Energy Transition While Maintaining Resource Adequacy,
`Docket No. ER24-99-000 (Oct. 13, 2023) (“ELCC Filing”).
`MSOC Filing at 4 (citing NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 114-15 (D.C. Cir. 2017) (“NRG”)).
`
`1
`2
`
`3
`
`4
`
`1
`
`
`
`
`
`proposed Binding Notice of Intent to participate in the capacity market.5 To the extent the
`
`
`
`
`
`Commission finds PJM must make further changes to its capacity market in light of the record in
`
`this proceeding and elsewhere,6 Pine Gate encourages the Commission to consider granular
`
`capacity market designs such as those that were presented, but not ultimately adopted, in the PJM
`
`Critical Issue Fast Path (“CIFP”) stakeholder process that culminated in the October 13 Filings.7
`BACKGROUND
`
`I.
`
`Headquartered in Asheville, North Carolina, Pine Gate originates, develops, finances, and
`
`operates utility-scale solar and energy storage projects that generate clean renewable power. Pine
`
`Gate works with energy buyers, corporations, utilities, local communities, and capital partners to
`
`develop and operate these projects across the country, with a particular emphasis on projects in the
`
`PJM region.
`
`Relevant to the October 13 Filings, Pine Gate was an active participant in the CIFP
`
`stakeholder process and sponsored a package advocating for a granular capacity market.8
`
`Specifically, Pine Gate and its co-sponsors put forward an interval pricing concept that would
`
`procure capacity for four intervals of the operating day. Other stakeholders also proposed packages
`
`that included a sub-annual capacity market design. For example, PJM proposed a two-season
`
`capacity market, but also expressed concern that its scope and complexity would make
`
`5
`
`6
`
`7
`8
`
`
`Capitalized terms not defined herein, have the meaning defined or used in the PJM Open Access
`Transmission Tariff (“Tariff”), the Reliability Assurance Agreement (“RAA”), or in the MSOC Filing or
`ELCC Filing.
`See, e.g., PJM Capacity Market Forum, Notice of Forum, Docket No. AD23-7-000 (Apr. 19, 2023);
`American Clean Power Association, Petition for a Technical Conference on Capacity Accreditation, Docket
`No. AD23-10-000 (Aug. 22, 2023).
`See infra § II.D.
`Capacity Coalition, Long-Term Capacity Market Changes, 2 (Aug. 1, 2023), available at 20230807-item-
`02d---leeward---long-term-capacity-market-final.ashx (pjm.com).
`
`2
`
`
`
`
`
`implementation difficult for the truncated CIFP timeline.9 The Independent Market Monitor of
`
`
`
`
`
`PJM (“IMM”) also proposed a sub-annual capacity market that would that would replace Capacity
`
`Performance and ELCC accreditation with an hourly capacity market.10 Stakeholders noted that
`
`the Midcontinent Independent System Operator, Inc. (“MISO”) recently implemented a four-
`
`season capacity market11 while California Independent System Operator (“CAISO”) is developing
`
`a granular resource adequacy program using a “slice of day” concept.
`
`Despite the robust stakeholder discussion regarding sub-annual capacity market design,
`
`PJM staff and stakeholders ultimately could not fully develop any of the sub-annual proposals in
`
`time for the CIFP deadline. At the conclusion of the CIFP process, Pine Gate along with several
`
`other renewable energy companies submitted written comments to the PJM Board of Managers
`
`(“Board”).12 The comments explained that while the companies supported a sub-annual capacity
`
`market, none of the proposed packages were yet ready to be adopted and implemented. Given that
`
`PJM’s annual market has proven inadequate in meeting PJM’s future reliability needs, the letter
`
`urged the Board to direct PJM to initiate a second CIFP process aimed at adopting a more granular
`
`market structure. While the PJM Board has expressed public support for exploring sub-annual
`
`market designs, it has yet to commit to a firm timeline for developing and implementing these
`
`reforms.
`
`9
`
`10
`
`11
`12
`
`
`Capacity Market Reform: PJM’s Initial Proposal – CIFP Resource Adequacy, PJM Interconnection, L.L.C.
`https://www.pjm.com/-/media/committees-groups/cifp-
`(Mar.
`29,
`2023),
`at:
`available
`ra/2023/20230329/20230329-item-04---pjm-cifp-ra-initial-proposal---stage-1-posting.ashx.
`Monitoring Analytics, LLC, Executive Summary of IMM Capacity Market Design Proposal: Sustainable
`Capacity Market (SCM) (Aug. 16, 2023), available at 20230823-item-01g---imm-cifp-executive-
`summary.ashx (pjm.com).
`Midcontinent Indep. Sys. Operator, Inc, 180 FERC ¶ 61,141 (2022).
`Pine Gate Renewables, LLC, et. al, Stakeholder Written Comments – Clean Energy Companies CIFP
`Resource Adequacy (Aug. 18, 2023), available at 20230823-stakeholder-written-comments---clean-energy-
`companies-cifp-resource-adequacy.ashx (pjm.com).
`
`3
`
`
`
`
`
`II.
`
`
`
`
`
`COMMENTS
`A. With the Exception of Certain Items Discussed Below, the Proposed Revisions
`in the October 13 Filings are Just and Reasonable.
`
`Earlier this year, the PJM Board acknowledged that reserve margins in PJM will likely
`
`decline due to increased retirements of conventional resources, demand growth, and changes to
`
`the generation mix.13 Winter Storm Elliot also emphasized the need to address emerging reliability
`
`threats like weather-correlated outages of thermal units during extreme cold weather events. Pine
`
`Gate applauds PJM’s leadership in proactively addressing these issues through the CIFP process.
`
`Pine Gate also commends PJM staff for crafting, under a constrained timeline, a proposal that on
`
`the whole strikes a reasonable balance among stakeholder interests. Below, Pine Gate expresses
`
`support for several specific aspects of the October 13 Filings.
`
`1.
`
`PJM’s proposed MSOC reforms are just and reasonable and should be
`accepted.
`
`PJM mitigates the exercise of seller-side market power—i.e., using economic withholding
`
`or inflated capacity offers to raise prices in order to benefit capacity market sellers—via two
`
`primary tools: (1) capping market seller offers to prevent sellers from inappropriately raising prices
`
`and (2) requiring certain existing market generators to offer their capacity in the market to prevent
`
`economic withholding. In PJM, the first of these tools is referred to as the MSOC and the second
`
`is often called the “must offer rule” or “must offer requirement.” Together, these tools help PJM
`
`ensure competitive outcomes in the capacity market.
`
`Renewable resources in PJM are currently exempted from the must offer rule—and for
`
`good reason. Under PJM’s Capacity Performance construct, capacity resources face substantial
`
`13
`
`
`M. Takahashi, Letter to PJM Stakeholders, PJM Interconnection, L.L.C. (Feb. 24, 2023), available at:
`https://www.pjm.com/-/media/about-pjm/who-we-are/public-disclosures/20230224-board-letter-re-
`initiation-of-the-critical-issue-fast-path-process-to-address-resource-adequacy-issues.ashx.
`
`4
`
`
`
`
`
`financial risks for failure to deliver capacity when called upon. While weather patterns can be
`
`
`
`
`
`forecast with increasing levels of sophistication, renewable generation cannot operate when called
`
`on at certain times of day for reasons entirely outside of the resource owners’ control. The must
`
`offer exemption for renewables allows these resources to reduce their risk of non-performance by
`
`not requiring them to offer their full accreditation into the market. In turn, this improves reliability
`
`by decreasing PJM’s reliance on megawatts to perform during times they cannot feasibly provide
`
`capacity and prevents load from paying for capacity that may not exist when they need it. Granular
`
`capacity market designs, as discussed below, would obviate the need for the must offer exemption
`
`as they would commit capacity only for those time intervals when the capacity would be available.
`
`However, as PJM has opted to maintain its annual capacity market design, along with the Capacity
`
`Performance construct, it is therefore appropriate that PJM has not proposed any changes to the
`
`must offer exemption for renewables in the October 13 Filings.
`
`While leaving the must offer exemption intact, the October 13 Filings would make much-
`
`needed improvements to the MSOC that would allow all resources to appropriately include
`
`Capacity Performance penalty risk in their offers. As PJM explains, the MSOC includes all the
`
`costs that a resource might incur by participating in the capacity market.14 The Commission has
`
`clearly indicated that these costs should include the risk of non-performance penalties that a
`
`resource may incur during a Performance Assessment interval (“PAI”), otherwise known as
`
`Capacity Performance Quantifiable Risk (“CPQR”).15 PJM correctly points out that, despite the
`
`Commission’s assurances, the unit-specific MSOC review process has become unduly contentious
`
`14
`15
`
`
`
`MSOC Filing at 7-9.
`Id. at 8 (citing Indep. Market Monitor for PJM v. PJM Interconnection, L.L.C., 176 FERC ¶ 61,137 (2021),
`order on reh’g, 178 FERC ¶ 61,121, at P 16 (2022), aff’d sub nom. Vistra Corp. v. FERC, 80 F.4th 302 (D.C.
`Cir. 2023)).
`
`5
`
`
`
`
`
`because of a lack of clarity regarding how CPQR can be reflected in offers.16 As a result, many
`
`
`
`
`
`resources are forced to offer into the capacity market at $0.00/MW-day despite the known risk of
`
`potentially substantial non-performance penalties. Pine Gate notes that this situation applies to
`
`renewable resources as well as many non-renewable resources that do not have an exemption to
`
`the must offer requirement.
`
`Resource owners know and understand the risk facing their own investments better than
`
`PJM or the IMM. Resource owners may also have varying degrees of risk tolerance. The Tariff
`
`should allow some level of latitude to resource owners to price and reflect risk in their offers so
`
`long as they can demonstrate that their assessments are reasonable. The MSOC Filing will permit
`
`this type of behavior by more clearly delineating what constitutes acceptable support for a
`
`resource’s risk assessment and by allowing the CPQR to act as a “floor” preventing capacity
`
`market offers from being mitigated down to zero despite substantial risk of non-performance
`
`penalties. For these reasons, Pine Gate strongly supports PJM’s proposed revisions to the MSOC
`
`and urges the Commission to find they are just and reasonable as proposed by PJM.
`
`2.
`
`PJM’s proposal to extend its capacity accreditation methodology to all
`resources rather than unduly singling out renewable resources is just and
`reasonable and should be accepted.
`
`During the two most recent extreme winter weather events, Winter Storm Elliot and Winter
`
`Storm Uri, common mode failures among thermal generators had a significant impact on reliability
`
`of the bulk power system. While correlated weather-related output of renewables has long been
`
`recognized as an operational challenge, correlated weather-related outages among the thermal fleet
`
`have been largely ignored when it comes to capacity accreditation. Recent evidence strongly
`
`16
`
`MSOC Filing at 9.
`
`
`
`6
`
`
`
`
`
`suggests that the correlation of these types of outages needs to be recognized and planned for, as
`
`
`
`
`
`PJM is proposing to do in the instant filing, in order to reliably operate the system.
`
`In the ELCC Filing, PJM proposes to extend its ELCC accreditation approach to all
`
`capacity resources. PJM explains that this proposal represents a break from its previous
`
`accreditation paradigm, which accredited thermal generators using historical forced outage rates.17
`
`Accreditation methods should be applied to all resources without unduly singling out renewable
`
`resources for common mode outages. For these reasons, Pine Gate strongly supports PJM’s
`
`proposal to apply a single capacity accreditation methodology to all capacity resources.
`
`3.
`
`PJM’s proposal to allow more granular PAI obligation transfers is just and
`reasonable and should be accepted.
`
`The current Tariff allows market participants to engage in some bilateral capacity
`
`transactions that include the transfer of performance obligations and associated penalty risk.18 In
`
`the MSOC Filing, PJM proposes to allow market participants to transfer capacity on an interval
`
`basis, which is not allowed under the current rules.19 Thus, as PJM explains, the proposed Tariff
`
`revisions would allow resources to manage penalty exposure risk through bilateral transactions
`
`that reduce obligations for certain times of day.20 The enhanced flexibility afforded to capacity
`
`suppliers under this proposal would improve reliability and market efficiency by allowing, for
`
`example, solar resources to transfer obligations to provide capacity at night. As PJM continues to
`
`operate an annual capacity market with no distinctions between different times of day or seasons,
`
`this flexibility would help ensure that financial capacity commitments are physically backed by
`
`
`
`ELCC Filing at 34.
`See Tariff, Attachment DD § 4.6(f)(iv).
`MSOC Filing at 40.
`Id. at 43.
`
`17
`18
`19
`20
`
`7
`
`
`
`
`
`capacity resources. Pine Gate strongly supports PJM’s proposal. At the same time, Pine Gate notes
`
`
`
`
`
`that this is a new type of bilateral transaction and it remains unclear whether the market will be
`
`sufficiently liquid to achieve its intended effect. For this reason, it is crucial that the Commission
`
`reject PJM’s proposal to eliminate eligibility for bonuses for energy-only resources, as discussed
`
`further below.
`
`B.
`
`The Commission Should Sever and Reject PJM’s Proposal to Limit Eligibility
`for Bonus Payments to Resource That Participate in the Capacity Market.
`
`In the MSOC Filing, PJM proposes changes to the eligibility requirements for Performance
`
`Payments to be paid to those resources that provide capacity during a PAI.21 PJM states the
`
`Commission should consider this element severable from the rest of the MSOC Filing.22 Therefore,
`
`the Commission may reject this portion of PJM’s filing without violating the requirements of NRG
`
`and still accept the rest of the MSOC Filing under section 205 of the Federal Power Act (“FPA”).23
`
`Pine Gate urges the Commission to exercise this option for the reasons discussed below.
`
`
`
`As PJM explains, under existing rules, any resource is eligible for bonus payments under
`
`Capacity Performance if its actual output exceeds its committed capacity during a PAI.24 In
`
`practice, this means that a resource that does not have a capacity commitment is eligible for bonus
`
`payments for any output subject to some adjustments for certain ancillary service commitments.
`
`In the MSOC Filing, PJM proposes to preclude entirely resources without capacity commitments,
`
`i.e. energy-only resources, from eligibility for bonus payments. For resources with capacity
`
`commitments, PJM proposes to limit their eligibility to their installed capacity commitment
`
`
`
`21
`22
`23
`24
`
`Id. at 4, 43.
`Id.
`16 U.S.C. § 824d.
`MSOC Filing at 43.
`
`8
`
`
`
`
`
`equivalent of their committed capacity, i.e. if a resource clears half of its eligible, accredited
`
`
`
`
`
`capacity in the auction, it would only be eligible for bonus payments for half of its total installed
`
`capacity.25 PJM also proposes to effectively exclude demand-side resources from eligibility for
`
`bonus payments.26
`
`PJM provides three reasons in support of this change. First, PJM claims that this will create
`
`a stronger economic incentive for resources to participate in the capacity market.27 Second, PJM
`
`explains that its energy and ancillary services markets are the proper venue for providing payments
`
`to resources that do not have capacity commitments.28 Last, PJM states that this proposed change
`
`aligns with its current formulation of the MSOC, which does not permit opportunity costs to be
`
`included.29
`
`Pine Gate believes PJM’s efforts to encourage resources to participate in the capacity
`
`market are well-intentioned, but ultimately misguided. It is understandable for PJM to seek for its
`
`capacity market to capture all the capacity necessary to maintain system reliability and for all the
`
`resources in the capacity market to be subject to the same qualifications and operating
`
`requirements. For this reason, PJM should continue its efforts to design a more granular capacity
`
`market that does not impose obligations that are physically impossible to satisfy such as requiring
`
`solar resources to be available at night. In the absence of such a market, the status quo eligibility
`
`criteria for bonus payments is just and reasonable whereas PJM’s proposed revisions are not.
`
`
`
`25
`26
`27
`28
`29
`
`Id. at 45.
`Id. at 50-54.
`Id. at 46-47.
`Id. at 47-49.
`Id. at 49-50.
`
`9
`
`
`
`
`
`
`
`
`
`
`The purpose of allowing all resources to receive bonus payments is to facilitate real-time
`
`liquidity in meeting PJM’s physical needs during tight grid conditions—not to incentivize
`
`participation in the capacity market per se. When PJM faces scarce conditions, PJM needs all
`
`available resources to provide output in real-time. Some resources with capacity commitments
`
`may be unavailable. Yet it will be too late for those resources to buy-out of their obligations. The
`
`current Capacity Performance construct facilitates the replacement of unavailable capacity
`
`resources by transferring the dollars PJM collects from penalties to those resources that satisfy
`
`PJM’s needs for capacity during a PAI. In attempting to encourage participation in PJM’s annual
`
`capacity market, restricting eligibility for bonus payments would inadvertently blunt the signal
`
`that Capacity Performance was designed to send to available resources during scarce conditions.
`
`Second, PJM argues that the energy market is the proper avenue for providing an incentive
`
`to perform for non-capacity resources during tight conditions. PJM relies on the capacity market
`
`rather than scarcity pricing in the energy market to send investment signals. As such, energy prices
`
`during PAIs do not provide generators sufficient revenue to cover the cost of investment in
`
`resources that are capable of providing energy when it is needed most. Indeed, if energy and
`
`ancillary service market revenues were sufficient to incentivize this performance, PJM would not
`
`need a capacity market in the first place. During Winter Storm Elliot, PJM relied on resources that
`
`did not have capacity commitments to keep the lights on. Many renewable resources performed
`
`well-beyond their capacity supply obligations.30 While it would be preferrable to count these
`
`resources as committed capacity, it is far too risky for some of these resources to participate in the
`
`capacity market as it is currently designed for the reasons discussed above. Pine Gate believes it
`
`30
`
`
`See PJM Interconnection, L.L.C., Winter Storm Elliot Generator Performance, 8-9 (Feb. 9, 2023), available
`at: https://www.pjm.com/-/media/committees-groups/committees/oc/2023/20230209/20230209-item-04---
`winter-storm-elliott-generator-performance.ashx.
`
`10
`
`
`
`
`
`would threaten reliability to exclude them from bonus payment eligibility given the way PJM’s
`
`
`
`
`
`capacity market is currently designed. To the extent PJM is concerned about eligibility of imported
`
`resources because these resources do not meet certain qualifications,31 PJM should propose a
`
`narrow exclusion from bonus payments for these resources. However, as proposed, PJM’s
`
`proposed revisions are unjust and unreasonable and should be rejected.
`
`Last, regarding making bonus eligibility consistent with PJM’s MSOC calculation, PJM
`
`has not explained the benefit of making these two aspects of its Tariff consistent. PJM did not raise
`
`this issue during the CIFP stakeholder process and its justification in the transmittal letter for the
`
`MSOC filing is difficult to follow. PJM states:
`
`Under the existing rules, opportunity cost in the form of Performance Payments are the
`potential revenues that an uncommitted resource could receive if it performs during a
`Performance Assessment Interval. However, neither the default Market Seller Offer Cap
`nor the unit-specific Market Seller Offer Cap provisions currently allow Capacity Market
`Sellers to include this the [sic] lost opportunity cost of taking on a capacity obligation in
`their capacity offers.32
`
`PJM appears to be stating that while uncommitted resources can receive bonus payments,
`
`committed resources cannot include the lost opportunity of these bonus payments in their offers
`
`under the MSOC rules. If Pine Gate’s understanding is correct, then PJM’s conclusion that bonus
`
`payment eligibility should be restricted to committed resources does not logically follow. An
`
`uncommitted resource does not lose an opportunity to earn bonus payments if it becomes a
`
`committed resource. On the contrary, both are eligible for bonus payments under the current rules.
`
`While a committed resource may not be allowed to include the foregone revenue from bonus
`
`payments in its capacity offer, that committed resource is nevertheless eligible for the same bonus
`
`payments as an uncommitted one. Therefore, it is unclear what issue PJM is attempting to address.
`
`31
`32
`
`MSOC Filing at 46.
`Id. at 49-50.
`
`
`
`11
`
`
`
`
`
`To the extent the Commission shares PJM’s concern about whatever inconsistency PJM is
`
`
`
`
`
`attempting to identify, it should require PJM to explain its rationale further before accepting the
`
`MSOC Filing, including why PJM did not propose to modify the MSOC rules (as it is already
`
`doing elsewhere in the instant filing) instead of the bonus eligibility rules to address this issue.
`
`C.
`
`The Commission Should Seek Greater Clarity From PJM on its Proposed
`Binding Notice of Intent.
`
`PJM proposes changes to its capacity auction procedures that PJM argues will better enable
`
`it to account for planned generation resources in PJM’s modeling that precedes the auction.33 In
`
`particular, PJM faces a challenge with modeling planned generation resources when setting what
`
`is known as the Capacity Emergency Transfer Objective (“CETO”). The CETO determines the
`
`amount of capacity that needs to be imported in a particular geographic area given the amount of
`
`native, internal capacity in that area. Prior to the auction, this internal amount of capacity is not
`
`known because planned resources have not yet offered into the auction. Thus, PJM must use a
`
`projection.34 Pine Gate notes that projecting internal capacity for a given delivery year can be
`
`especially challenging in PJM because, unlike some neighboring regions, PJM does not use a
`
`prompt auction and instead conducts an auction three years in advance of the delivery year. To
`
`make its projection, PJM currently models any planned generation resource that has an executed
`
`Interconnection Service Agreement (“ISA”) as if it would be available in the auction for the
`
`purpose of determining the CETO. At the time of the actual auction, some of those resources that
`
`PJM previously modeled because they had executed an ISA may not show up. This mismatch
`
`between capacity modeled in setting the CETO and capacity offered in the auction can create
`
`significant discrepancies as happened in PJM’s most recent capacity auction. For this reason,
`
`
`
`ELCC Filing at 72-77.
`See RAA Schedule 10.1, § B.
`
`33
`34
`
`12
`
`
`
`
`
`earlier this year, the Commission accepted revisions to PJM’s auction rules that allow PJM to
`
`
`
`
`
`exclude planned resources with ISAs from its modeling if those resources do not offer in the
`
`auction and if a certain threshold is reached.35
`
`In the instant filing, PJM proposes to modify this approach and instead require planned
`
`resources to submit a binding notice of intent to offer prior to the auction.36 Under its proposal,
`
`every resource seeking to offer in a capacity auction must submit a notice of intent to offer capacity
`
`or be precluded from participating in the auction. PJM proposes a deadline of December 1 for each
`
`Baseline Residual Auction and 90 days prior to the conduct of each Incremental Auction.
`
`
`
`PJM’s proposed approach is reasonable in principle and preferrable to the approach PJM
`
`adopted in the CETO Filing. However, several critical questions remain regarding implementation
`
`details. First, it is not clear what process will exist to address issues that may arise beyond a market
`
`participant’s control. In the roughly six-month period between when a resource submits a notice
`
`of intent to offer and the auction, many issues could arise that could delay a project and thus
`
`prevent it from participating in the capacity auction. These include interconnection delays from
`
`the interconnecting utility, delays in commissioning a project, procurement or supply chain issues,
`
`and labor shortages. It is unclear what recourse, if any, a market participant would have if any of
`
`these issues arose. Second, it is not clear if a resource would need to indicate a precise quantity of
`
`capacity or what denomination of capacity, i.e. accredited capacity, nameplate, or installed
`
`capacity, PJM will require. Resources would be especially challenged to provide precise
`
`information in the notice of intent because ELCC values would be unknown at the time the notice
`
`
`See PJM Interconnection, L.L.C. 182 FERC ¶ 61,109 (2023) (“CETO Filing”).
`ELCC Filing at 74.
`
`35
`36
`
`13
`
`
`
`
`
`is submitted. Third, PJM has not formally committed to publishing indicative ELCC values, which
`
`
`
`
`
`are an essential factor in a resource’s decision on whether or not to offer capacity.
`
`
`
`Pine Gate notes that PJM held a one-hour training workshop with stakeholders on
`
`November 8, 2023 to address the “Process for Planned Generation Offer Notification.” In that
`
`workshop, PJM provided helpful clarifications verbally that address some of the issues raised
`
`above. However, PJM has not yet publicly posted the materials for this workshop. Pine Gate
`
`emphasizes that it believes PJM is acting in good faith to address these issues and respond to the
`
`concerns raised by stakeholders. Nevertheless, it is clear that many important details have not yet
`
`been finalized. For this reason, the Commission cannot yet determine whether PJM’s proposal is
`
`just and reasonable without further clarification from PJM.
`
`D.
`
`If the Commission Directs Further Capacity Market Reform, it Should
`Require PJM to Consider Interval or Hourly Capacity Market Designs.
`
`As discussed above, PJM’s proposed revisions in the October 13 Filings overall represent
`
`an improvement over the status quo and should be accepted as just and reasonable with the
`
`exceptions described above. Pine Gate commends PJM staff for its willingness to incorporate
`
`stakeholder feedback under a demanding timeline during the CIFP process. Pine Gate has every
`
`reason to believe that PJM will continue to work constructively with its stakeholders to seek
`
`reasonable solutions to the reliability challenges PJM faces in the future. Therefore, Pine Gate is
`
`not requesting that the Commission take further action under FPA section 206 to direct additional
`
`capacity market reforms.
`
`Many of the reforms in the October 13 Filings take steps towards a capacity market that
`
`will better maintain reliability in light of PJM’s rapidly changing resource mix. PJM’s proposed
`
`new accreditation method for thermal generators will now account for so-called common mode
`
`outages—when many resources go offline for the same reason—such as natural gas supply
`
`14
`
`
`
`
`
`shortfalls. Such outages, like those experienced during recent extreme winter storms, are one of
`
`
`
`
`
`the greatest reliability threats facing PJM. In addition, PJM has made several other changes that
`
`appropriately shift the focus of its resource adequacy planning and operations from meeting
`
`summer peak load to addressing winter reliability challenges and the duration of such outages, i.e.,
`
`using Expected Unserved Energy (“EUE”). These are essential features of a well-designed market
`
`that the Board should maintain going forward. As evidence of PJM’s willingness to incorporate
`
`stakeholder feedback, several companies withdrew their own packages from consideration with
`
`confidence that PJM’s filing would include these design features.
`
`At the same time, the revisions proposed in the October 13 Filings do not go nearly far
`
`enough in addressing the reliability challenges that PJM will face in the coming years. As
`
`resources retire and are replaced by more intermittent and limited-duration resources, PJM will
`
`increasingly face challenges to ensure it has sufficient capacity available in particular hours of the
`
`day that will differ from one season to the next. Designing a capacity market that facilitates
`
`participation of all resources will also pose a challenge. Intermittent resources face a different risk
`
`profile than conventional generators because of their operating characteristics. While coupling
`
`battery storage with renewable generators can close some of this gap, PJM’s markets currently do
`
`not adequately value the reliability benefits that storage can provide. At the same time, the October
`
`13 Filings retain the Capacity Performance penalty regime that can expose these market
`
`participants to undue financial harm during events like Winter Storm Elliott. The must offer
`
`exemption for renewables allows resources not technically capable of operating during all hours
`
`of the day to reduce their risk of non-performance by not requiring them to offer their full
`
`accreditation into the market. In turn, this improves reliability by decreasing PJM’s reliance on
`
`megawatts to perform during times they cannot feasibly provide capacity and prevents load from
`
`15
`
`
`
`
`
`paying for capacity that may not exist when they need it. Time-of-day markets, as discussed below,
`
`
`
`
`
`obviate the need for the must offer as they only commit resources for times they are technically
`
`capable of performing.
`
`Pine Gate understands that in light of these outstanding issues and others, the Commission
`
`may opt to take additional action such as requiring PJM to file an informational report, propose
`
`additional Tariff revisions, or explain why its Tariff remains just and reasonable without further
`
`reform. If the Commission takes one of these actions, Pine Gate strongly encourages the
`
`Commission to consider sub-annual capacity market designs in its assessment of potential options
`
`for additional reform.
`
`Creating a market that builds upon the foundation of PJM’s existing capacity market and
`
`incorporates granular time-of-day prices can attract new resources, add cutting-edge technologies,
`
`and send a price signal to develop innovative future solutions that can provide capacity during the
`
`intervals when the market needs it most. With more granular price signals, investors and
`
`technology developers can effectively make informed decisions about what technology attributes
`
`are needed and when. Of critical importance, a more granular capacity market (including intra-day
`
`and seasonal price shapes) will also g



