throbber
1
`
` UNITED STATES OF AMERICA
`BEFORE THE
`FEDERAL ENERGY REGULATORY COMMISSION
`
`)
`)
`Southwest Power Pool ) Docket No. ER25-2296-000
` )
` )
`
`COMMENTS OF THE
`CLEAN ENERGY BUYERS ASSOCIATION
`
`Pursuant to Rule 211 of the Federal Energy Regulatory Commission’s (“Commission”)
`Rules of Practice and Procedure, 18 C.F.R. § 385.211,1 the Clean Energy Buyer Association
`(“CEBA”) hereby files this Motion to Intervene and submit the following comments on the filing
`by the Southwest Power Pool (“SPP”) to establish the Expedited Resource Adequacy Study
`(ERAS) process.
`On May 22, 2025, SPP filed a proposal to establish the ERAS process to provide a
`framework for a one-time accelerated study of generation projects that are needed to address
`urgent resource adequacy and reliability needs in the near term.
`CEBA is a business trade association that activates energy buyers and partners to advance
`low-cost, reliable, carbon emissions-free global electricity systems. CEBA has over 400
`members, collectively with more than $20 trillion in market capital, including one-fifth of the
`Fortune 500. These members comprise a diversity of commercial, industrial and institutional
`energy customers, including large commercial customers, data centers, and manufacturing
`customers representing some of the largest sources of load growth in this country. Recent reports
`
`1 18 C.F.R. § 385.211 (2025).
`
`
`
`
`
`
`
`2
`
`show that total US electricity demand will grow by 35-50% by 2040, requiring more than 1,000
`GW of new generation including renewables, natural gas and energy storage.2 With respect to
`clean energy demand specifically, a recent study by Wood Mackenzie also found that Fortune
`1000 companies need an additional 275 GW of carbon emissions free power by 2035.3 That
`study found the Fortune 1000 could be expected to procure 15.3 GW of new clean energy
`projects in SPP to meet their corporate clean energy commitments.4 This creates an urgent need
`for faster interconnection of new resources to the grid. Failure to meet the moment has
`widespread consequences of stifling our nation’s economic growth and competitiveness, and
`risks increasing costs to consumers. We support the intent behind ERAS and recognize that
`increasing load growth within SPP’s footprint has introduced new challenges to balancing supply
`and demand, particularly given SPP’s extensive queue backlog. As such, the urgency of securing
`adequate capacity in the region is apparent, and we appreciate SPP’s efforts to explore a
`temporary solution for urgent resource adequacy needs.
`However, to meet the needs of new load cost effectively, CEBA’s energy buyers must
`have timely access to diverse, competitive, and affordable generation resources. CEBA is
`concerned that the SPP ERAS proposal grants Load Responsible Entities (LREs), most of which
`are vertically integrated utilities, the unilateral ability to select which resources are submitted to
`SPP for ERAS consideration—without open access protections or any state regulatory review—
`resulting in undue discrimination against competitive generation. We are concerned that SPP
`
`2 S&P Global Commodity Insights, US National Power Demand Study Executive Summary, at 2-3 (Mar.
`10, 2025).
`3 Wood MacKenzie, US Corporate Carbon Emissions-Free Demand Outlook, at 4 (Jan. 30, 2025),
`available at: https://cebuyers.org/wp-content/uploads/2025/01/CEBA_US-Corporate-Carbon-Emissions-
`Free-Demand-Outlook.pdf.
`4 WoodMackenzie, US Corporate Carbon Emissions-Free Demand Outlook, at 5 (Jan. 30, 2025),
`available at https://cebuyers.org/wp-content/uploads/2025/01/CEBA_US-Corporate-Carbon-Emissions-
`Free-Demand-Outlook.pdf.
`
`
`
`
`
`
`
`3
`
`ERAS framework will undermine open access and enable preferential grid access for utility-
`affiliated generation, elevating the risk of uneconomic resources advancing through the queue,
`locking up transmission capacity, and raising costs for consumers.
`CEBA believes prioritizing reforms that resolve the existing generator interconnection
`queue backlog remains the most critical and effective solution to ensure resource adequacy. We
`support SPP’s efforts to integrate its transmission and interconnection processes and explore a
`novel “entry fee model” under the Consolidated Planning Process (CPP) and urge SPP to keep
`those efforts on track to ensure we see improvements to SPP’s traditional queue in a timely
`manner. Resolving the current backlog for the interconnection queue would unlock about
`145 GW of new, low-cost clean energy resources that could be brought to the grid.5
`I. Introduction: CEBA Recognizes LRE’s Underlying Resource Adequacy Concern
`but Disagrees with the Discriminatory Criteria
`SPP’s resource adequacy shortfall is the nexus of queue delays, increases in resource
`adequacy requirements, and significant load growth. SPP’s short-term generator delays are in
`part the result of regular delays in its Definitive Interconnection System Impact Study (DISIS).
`Despite significant backlog clearing, SPP’s queue consistently takes between 2 and 3 years
`before GIAs are able to be executed. Moreover, each DISIS study is contingent upon the prior,
`meaning that a delay in one, or an error which could cause it to need to be re-run, has
`implications for each successive study. Such was the case when SPP did not conduct tariff-
`defined studies on five clusters beginning with the 2017 DSIS and continuing through 2020.
`
`5 Lawrence Berkeley National Lab, Queued Up: 2024 Edition, at pg. 9 (April 2024), available at
`https://emp.lbl.gov/sites/default/files/2024-04/Queued%20Up%202024%20Edition_R2.pdf
`
`
`
`
`
`
`
`4
`
`In addition to slow generation interconnection, there have also been significant changes
`in SPP’s RA requirements in recent years. Following Winter Storm Uri, SPP passed significant
`reforms shifting away from a 15% annual planning reserve margin to seasonal winter and
`summer planning reserve requirements. Despite LRE concerns, SPP subsequently increased
`those reserves from 15% year-round to 16% in the summer and 36% in the winter of 2026, a
`significant step up in a comparatively short amount of time.
`These two policy dynamics by themselves are significant; however, they may have been
`manageable in other years where load growth was relatively flat. Now, SPP’s LRE’s are faced
`with the added pressure of significant load growth across the SPP footprint, both increasing their
`RA requirements and driving the need to interconnect new resources quickly.
`Recognizing the need for reform in its planning and interconnection process, SPP started
`developing the Consolidated Planning Process (CPP) in 2021. The process seeks to harmonize
`the generation interconnection, transmission planning, and load forecasting, which all play a
`significant role in determining resource adequacy. However, the development and
`implementation of the CPP has been slow.
`The fraught existing DISIS process coupled with slow CPP implementation led
`stakeholders to pursue a one-time, expedited DISIS study, ERAS, in an attempt to relieve some
`of the near-term resource adequacy shortfall. To differentiate the one-off study and bypass the
`delays which plague the current process, SPP needed to reduce the modeling complexity by
`imposing eligibility criteria to limit the number of resources and prioritizing those that were most
`likely to interconnect. Stakeholders proposed and adopted language restricting the resources
`
`
`
`
`
`
`
`5
`
`selected to those being brought forward by LREs. In doing so, SPP cut out any other type of
`market participant from bringing forward resources.
`SPP justified these proposed actions on two principles. First, on the flawed logic that
`LREs carry the PRM obligation and therefore are the only harmed entities. Second, SPP stated
`that this policy would not set precedent as it was only a one-off study. CEBA disagrees with
`SPP’s justifications.
`First, LRE’s may be the entity responsible for the load obligation under the SPP tariff;
`however, all end-use consumers are harmed by resource adequacy shortfalls. The penalty costs
`from failing to meet PRM requirements are passed down to end-use ratepayers like CEBA
`members. To address this, many CEBA members are capable of bringing their own resources in
`open access markets to meet their own obligations. SPP’s criteria prevent this, limiting market
`access.
`Additionally, though SPP does not intend to repeat the ERAS process, there is no clear
`end to the nexus of issues that have put the RTO in this predicament. The CPP will likely not
`solve all of the issues overnight, load will still likely continue to grow, and PRM requirements
`could get more stringent, providing the same conditions for which SPP justified ERAS. A new
`tariff filing, striking the limited use case in the preamble of the proposed Attachment AW
`6, could
`be adopted and non-LRE's would have limited ability to prevent it.
`Non-LRE stakeholders repeatedly raised this concern throughout the voting process;
`however, SPP’s voting body does not provide a strong avenue for non-LREs. Notably, ERAS
`
`6 Southwest Power Pool, Inc., Submission of Tariff Revisions to Implement the Expedited Resource Adequacy
`Study, Docket No. ER25-2296-000 (filed May 25, 2025) (“ERAS Proposal”).
`
`
`
`
`
`
`
`6
`
`received no support from large consumers like CEBA members, independent power producers,
`or public interest groups, and nearly full support from vertically integrated utilities.7
`II. ERAS eligibility requirements are unduly discriminatory against competitive
`generation, with a broad precedential effect of undermining FERC’s principle of
`open access.
`CEBA’s members, as end-use customers, are committed to the principle of open access,
`which underpins competitive wholesale markets and ensures access to a competitive mix of
`generation resources. We firmly believe that non-discriminatory grid access for all generation
`sources, including third-party competitive generation, fosters competitive pressure that drives
`technological innovation and resource diversity. This, in turn, helps lower costs for end-use
`customers. CEBA is concerned that SPP’s proposed ERAS will erode open access to the grid by
`imposing unduly discriminatory barriers that prevent Independent Power Producers (IPPs) from
`direct participation in ERAS thereby allowing for preferential treatment of load-responsible
`entities (LREs) with self-built generation.
`Under the proposed ERAS framework, only LREs may submit resources to SPP for
`consideration in ERAS. Competitive generation resources from IPPs are excluded from
`eligibility for direct submission into ERAS. Under this approach, IPPs are effectively barred
`from ERAS participation unless they are first selected by an LRE, giving LREs full control over
`
`7 See, Sw Power Pool, Inc., Board of Directors/Members Committee Meeting Minutes, at P 4 (May 6,
`2025), available at https://www.spp.org/documents/73856/2025-05-06%20bod%20mc%20minutes.pdf;
`and Sw Power Pool, Inc., Markets and Operations Policy Committee Meeting Minutes and Ballots, at P
`27 (Apr. 15, 2025), available at
`https://spp.org/documents/73691/mopc%20meeting%20minutes%20and%20ballots%20combined_20250
`415.pdf
`
`
`
`
`
`
`
`7
`
`which resources can access ERAS enabling preferential access for utility-affiliated generation
`and denying IPPs grid access on the same or comparable basis.
`This structure is inconsistent with FERC’s principle of open access and long-standing
`Commission concerns that vertically integrated utilities have both the incentive and ability to
`favor their own generation.8 As established in Order No. 888,9 FERC found that “[a]n open
`access tariff that is not unduly discriminatory or anticompetitive should offer third parties access
`on the same or comparable basis, and under the same or comparable terms and conditions, as the
`transmission provider's uses of its system”
`10 with ongoing recognition that open access
`requirements specific to the generator interconnection process is a “critical component of open
`access transmission service.”11 We believe that open access is not only a foundational principle
`of wholesale competition but also a critical safeguard against utility self-dealing that drives up
`costs for consumers. The ERAS proposal circumvents these protections. By giving LREs
`exclusive submission rights and by excluding competitive generators from direct access to
`ERAS, the proposal effectively permits LREs to access preferential queue access, secure
`interconnection agreements, and tie up transmission capacity without a comparable opportunity
`for IPPs. This is a textbook case of undue discrimination in violation of FERC’s open access
`principles.
`
`8 See, e.g., Xcel Energy Operating Cos., 106 FERC ¶ 61,260, at P 23 (2004); see also Am. Clean Power
`Ass’n v. FERC, 54 F.4th 728 (2022) (citing Ameren Services Co. v. FERC, 880 F.3d 578 (2018))
`(“Ameren emphasized that ‘if the transmission owners still owned integrated generation facilities, that
`would present a competitive motive’ to discriminate in favor of their own facilities.”)
`9 Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by
`Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888,
`FERC Stats. & Regs. ¶ 31,036 (1996) (“Order No. 888”).
`10 Order No. 888, FERC Stats. & Regs. ¶ 31,036 at 31,647.
`11 Standardization of Generator Interconnection Agreements & Procs., Order No. 2003, 104 FERC ¶
`61,103, at PP 9, 12 (2003) (Order No. 2003).
`
`
`
`
`
`
`
`8
`
`FERC has consistently upheld and applied the principle of open access, permitting
`expedited or priority access to the queue only under narrowly defined circumstances.12 Most
`recently, in rejecting MISO’s Expedited Resource Addition Study, the Commission found that
`MISO did not ensure the proposal was ”aligned with FERC’s open access principles in an
`objective and transparent manner.“13 Similarly, FERC rejected MISO’s proposed exemptions to
`its queue cap, reaffirming that grid access must be offered on an equal or comparable basis.14
`We are concerned that approval of the SPP ERAS would represent a departure from this
`precedent and would significantly undermine the protections otherwise provided by FERC’s
`continued adherence to open access principles. A shift in precedent would prevent third parties’
`grid access on the same or comparable basis, which will reduce competitive pressures, stifle
`technology innovation, and reduce available generation options all increasing costs for end-use
`customers. CEBA understands the need to expedite grid access to meet growing demand.
`However, this must be achieved in a manner that preserves open access and maintains FERC’s
`established precedent that ensures non-discriminatory grid access to protect consumers from
`increasing costs.
`III. Lack of state regulatory oversight creates further potential for undue discrimination
`against competitive generation, preventing cost-effective generation and increasing
`costs for consumers.
`
`
`12 See, e.g., Midcontinent Indep. Sys. Operator, Inc., 186 FERC ¶ 61,054, at P 177 (2024), Xcel Energy
`Operating Cos., 106 FERC ¶ 61,260, at P 23 (2004).
`13 Midcontinent Indep. Sys. Operator, Inc., 191 FERC ¶ 61,131, at P 203 (2024).
`14 Midcontinent Indep. Sys. Operator, Inc., 186 FERC ¶ 61,054, at P 176 (2024) (”MISO’s proposal to
`include unbounded cap exemptions in its generator interconnection procedures is inconsistent with the
`requirement that MISO must offer access to the generator interconnection process on the same or
`comparable basis”).
`
`
`
`
`
`
`
`9
`
`Compounding concerns surrounding the lack of open access and undue discrimination,
`the SPP’s ERAS process also excludes any role for state regulators to review or validate ERAS
`resource submissions by LSEs. In the case of extraordinary measures, such as a one-time queue-
`jumping process in vertically integrated regions, a strong role for state regulators, who have
`authority over resource adequacy, is necessary to serve as a check and balance in the absence of
`open access.
`Unfortunately, SPP’s ERAS process allows LREs to determine resource adequacy need
`and select resources for ERAS without state regulatory oversight. Moreover, SPP itself performs
`no independent validation of ERAS submissions, deferring all decisions regarding both need and
`resource solutions to the LREs. We are concerned that this lack of state regulatory review will
`allow for self-dealing among vertically integrated LREs, preventing opportunities for the
`selection of more cost-effective generation resources and driving up costs for consumers.
`The importance of the state regulatory review was recently highlighted by Commissioner
`Lindsay See in her remarks on the FERC Order rejecting MISO’s ERAS proposal stating that in
`vertically integrated regions, she “would be skeptical if a proposal like ERAS didn’t give the
`States a leading role.” She emphasized that it is “the States that assess need when it comes to
`resource adequacy questions in their borders.” Yet in SPP ERAS, state regulators have no role
`whatsoever in validating an LRE’s identification of resource adequacy need or reviewing an
`LRE resource submission into ERAS. This stands in contrast to the MISO ERAS proposal where
`states regulators were at least required to provide notification that a proposed ERAS project
`“should be considered for the ERAS process.”15 Even with the inclusion of this, albeit limited
`
`15 Midcontinent Indep. Sys. Operator, Inc., 191 FERC ¶ 61,131, at PP 10, 31, 85 (2024). See also,
`Midcontinent Indep. Sys. Operator, Inc., 191 FERC ¶ 61,131 (See, Comm’r, concurring at 6).
`
`
`
`
`
`
`
`10
`
`form of state review, FERC rejected the MISO proposal, finding that “MISO has not
`demonstrated that the proposed Tariff language is tailored to ensure that only those resources
`capable of addressing identified near-term resource adequacy or reliability needs are eligible for
`expedited study through the ERAS process.”16
`Additionally, Commissioner See raised concerns regarding the lack of transparency on how
`resources would be selected by states under MISO ERAS, including the lack of explanation
`regarding the factors considered or how alternative projects would be compared.17 In the case of
`SPP ERAS, where LREs have the exclusive ability to submit resources into ERAS, SPP’s
`proposal similarly lacks objective criteria for resource selection. LREs need only attest that a
`resource adequacy need cannot be met cost-effectively by existing or queued resources—but
`there is no requirement to show how this determination was made, nor any requirement to
`consider or disclose alternative options. The lack of transparency and objective criteria
`eliminates any practical check on LRE discretion and elevates the risk of uneconomic resources
`advancing through the queue, locking up transmission capacity and potentially raising costs for
`consumers. Together, these findings should serve as a clear indication that SPP’s omission of
`state regulatory review of resource adequacy need or resource submission to ERAS, particularly
`in the absence of open access, would be inconsistent with FERC precedent.
`
`
`16 Midcontinent Indep. Sys. Operator, Inc., 191 FERC ¶ 61,131, at P 202 (2024)
`17 Midcontinent Indep. Sys. Operator, Inc., 191 FERC ¶ 61,131 (See, Comm’r, concurring at 6).
`
`
`
`
`
`
`
`11
`
`IV. A well-functioning queue is the most effective, long-term solution to address
`resource needs and SPP must prioritize holistic reforms to its queue process.
`CEBA believes that resolving the existing generator interconnection queue backlog
`remains the most effective solution to deliver shovel-ready projects, including carbon emissions-
`free generation projects that customers are seeking, that support resource adequacy. Resolving
`the current backlog for the interconnection queue would have the consequential impact of
`unlocking more than 145 GW of new clean energy resources in the queue at a time of
`unprecedented load growth.18 We agree with Commissioner Rosner that temporary solutions,
`such as ERAS, are “not a substitute for a well-functioning interconnection process that allows all
`resources to connect to the grid quickly and efficiently.”19 We commend SPP on its recent
`announcements with Hitachi to speed queue processing with automation techniques and look
`forward to seeing the results of those efforts.20 Additionally, we appreciate the effort underway
`in SPP to establish an integrated interconnection and transmission planning process and explore
`a novel “entry fee model” under the Consolidated Planning Process. We urge SPP to keep those
`efforts on track to ensure we see improvements to SPP’s traditional queue in a timely manner.
`V. Conclusion
`Thank you for the attention to these comments. Specifically, we believe Commission
`guidance should encourage SPP to make ERAS consistent with open access by allowing direct
`participation by all resource providers that can meet verified resource adequacy shortfalls and
`establishing an appropriate role for state regulator review.
`
`18 Lawrence Berkeley National Lab, Queued Up: 2024 Edition, at pg. 9 (April 2024), available at
`https://emp.lbl.gov/sites/default/files/2024-04/Queued%20Up%202024%20Edition_R2.pdf
`19 PJM Interconnection, L.L.C., 190 FERC ¶ 61,084 (2025) (Phillips and Rosner, Comm’r, concurring at
`P 7).
`20 Southwest Power Pool, SPP Partners with Hitachi to Develop Advanced AI Solution, Press Release (Jun 5, 2025)
`available at https://www.spp.org/news-list/spp-partners-with-hitachi-to-develop-advanced-ai-solution/.
`
`
`
`
`
`
`
`12
`
`Respectfully submitted,
`/s/ Bryn Baker
`Bryn Baker
`Senior Director, US Policy
`Clean Energy Buyers Association
`1501 M St, NW, Ste 900
`Washington, DC 20005
`
`Dated June 12, 2025
`
`
`
`
`
`
`
`

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket