throbber

`
`BP Pipelines (Alaska) Inc.
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`UNITED STATES OF AMERICA
`BEFORE THE
`FEDERAL ENERGY REGULATORY COMMISSION
`
` )
` )
` )
` )
` )
`
`
`
`
`
`
`
`Docket Nos. IS09-348-004, et al.
` IS09-348-006, et al.
`
`(Superseded)
`(SR Phase I Prudence)
`(SR Phase II Cost of Service)
`
`LIMITED BRIEF ON EXCEPTIONS OF
`ANADARKO PETROLEUM CORPORATION
`
`
`
`Joseph S. Koury, Esq.
`Jeffrey G. DiSciullo, Esq.
`Andrew T. Swers, Esq.
`WRIGHT & TALISMAN, P.C.
`1200 G Street, N.W.
`Washington, D.C. 20005-3802
`Telephone: (202) 393-1200
`Facsimile: (202) 393-1240
`koury@wrightlaw.com
`disciullo@wrightlaw.com
`swers@wrightlaw.com
`
`
`
`Robin O. Brena
`David W. Wensel, Esq.
`Anthony S. Guerriero, Esq.
`BRENA, BELL & CLARKSON, P.C.
`810 N Street, Suite 100
`Anchorage, Alaska 99501-2014
`Telephone: (907) 258-2000
`Facsimile: (907) 258-2001
`rbrena@brenalaw.com
`dwensel@brenalaw.com
`aguerriero@brenalaw.com
`
`Sherri B. Manuel, Counsel
`Anadarko Petroleum Corporation
`1201 Lake Robbins Drive
`The Woodlands, Texas 77380
`Telephone: (832) 636-1000
`Facsimile: (832) 636-8001
`sherri.manuel@anadarko.com
`
`
`May 16, 2014
`
`
`
`

`

`
`
`
`I.
`
`TABLE OF CONTENTS
`
`
`PAGE
`
`LIMITED EXCEPTION RAISED ..........................................................................1
`
`II.
`
`SUMMARY .............................................................................................................2
`
`III.
`
`STATEMENT OF THE CASE ................................................................................2
`
`IV.
`
`POLICY CONSIDERATIONS WARRANTING FULL COMMISSION
`REVIEW AND OPINION .......................................................................................3
`
`V.
`
`ARGUMENT ...........................................................................................................4
`
`A.
`
`B.
`
`C.
`
`D.
`
`Anadarko’s Five Remedy Formulations. .....................................................4
`
`The Presiding Judge Found that All SR Costs Are Imprudent and
`Otherwise Unrecoverable in Rates. ..............................................................5
`
`The Presiding Judge’s Selection of Remedy 3 Would Allow $229.2
`Million of Imprudent and Unreasonable SR Costs to be Recovered
`in the Cost of Service. ..................................................................................5
`
`Remedy 1 Is Commensurate with the Presiding Judge’s Findings
`Regarding the SR Project. ............................................................................8
`
`E.
`
`Anadarko’s Other Remedy Proposals. .........................................................8
`
`VI.
`
`CONCLUSION ......................................................................................................10
`
`
`
`
`
`
`
`
`
`i
`
`

`

`TABLE OF AUTHORITIES
`
`
`ADMINISTRATIVE DECISIONS
`
`PAGE
`
`BP Pipelines (Alaska) Inc.,
`
`Notice of Extension of Time,
`
`Docket Nos. IS09-348-004, et al. (Mar. 6, 2014) ....................................................3
`
`BP Pipelines (Alaska) Inc.,
`146 FERC ¶ 63,019 (2014) ........................................................................................ passim
`
`BP Pipelines (Alaska) Inc.,
`
`Order of Chief Judge Extending Initial Decision Deadline,
`
`Docket Nos. IS09 348-004, et al. (Oct. 30, 2013) ...................................................3
`
`BP Pipelines (Alaska) Inc.,
`
`130 FERC ¶ 61,042 (2010) ......................................................................................3
`
`BP Pipelines (Alaska) Inc.,
`
`Order of Chief Judge Severing Strategic Reconfiguration
`
`Issues and Scheduling Prehearing Conferences,
`
`Docket Nos. IS09-348-000, et al. (Jan. 13, 2010) ....................................................3
`
`STATUTES & REGULATIONS
`
`18 C.F.R. § 385.711 .............................................................................................................1
`
`
`
`
`
`
`
`
`
`ii
`
`

`

`TABLE OF ABBREVIATIONS
`
`
`
`
`Authorization for Expenditure
`
`
`AFE
`State of Alaska
`Alaska or State
`Anadarko Petroleum Corporation
`Anadarko
`BP Pipelines (Alaska) Inc.
`BP or BPPA
`BP Exploration (Alaska), Inc.
`BPXA
`ConocoPhillips or CPTAI ConocoPhillips Transportation Alaska, Inc.
`ExxonMobil or EMPCo
`ExxonMobil Pipeline Company
`FERC or Commission
`Federal Energy Regulatory Commission
`
`Koch
`RCA
`SIPPS
`SR
`
`Koch Alaska Pipeline Company
`Regulatory Commission of Alaska
`Safety Integrity & Pressure Protection System
`Strategic Reconfiguration
`
`TAPS
`
`
`
`
`
`Trans Alaska Pipeline System
`
`TAPS Carriers, Carriers or
`Owners
`
`
`Tesoro
`Unocal
`
`
`
`
`
`
`
`BP Pipelines (Alaska) Inc.
`ConocoPhillips Transportation Alaska, Inc.
`ExxonMobil Pipeline Company
`Koch Alaska Pipeline Company, and
`Unocal Pipeline Company
`
`Tesoro Alaska Company
`Unocal Pipeline Company
`
`iii
`
`

`

`
`
`LIMITED BRIEF ON EXCEPTIONS OF
`ANADARKO PETROLEUM CORPORATION
`
`
`To: The Commission
`
`
`
`Pursuant to Rule 711 of the Rules of Practice and Procedure of the Federal Energy
`
`Regulatory Commission (“FERC” or “Commission”), 18 C.F.R. § 385.711, Anadarko
`
`Petroleum Corporation (“Anadarko”) submits this limited brief on exceptions to the
`
`Initial Decision (“ID”), issued by Presiding Judge Cintron, on February 27, 2014.1
`
`
`
`Anadarko would welcome complete affirmance of the ID. Yet, Anadarko expects
`
`that the TAPS Carriers2 will file exceptions to the ID. Accordingly, to fully preserve its
`
`rights, Anadarko raises the limited exception set forth below.
`
`I.
`
`
`
`LIMITED EXCEPTION RAISED
`
`The Presiding Judge found that all costs of the TAPS Carriers’ Strategic
`
`Reconfiguration (“SR”) project were imprudently incurred, are not “used and useful,”
`
`and fail to provide ratepayer benefits; however, the remedy adopted by the Presiding
`
`Judge would allow a significant portion ($229.2 million) of such imprudent and
`
`unreasonable SR costs to be included in rates through an amortization in the cost of
`
`service.3 Accordingly, Anadarko raises this limited exception and claim of error in order
`
`to preserve for the Commission the full array of potential remedies that may be adopted
`
`
`1
`2
`
`BP Pipelines (Alaska) Inc., 146 FERC ¶ 63,019 (2014).
`At the commencement of the proceedings, the Trans Alaska Pipeline System
`(“TAPS”) Carriers (also referred to as “Carriers”) included BP Pipelines (Alaska)
`Inc. (“BP”); ConocoPhillips Transportation Alaska, Inc. (“ConocoPhillips”);
`ExxonMobil Pipeline Company
`(“ExxonMobil”); Koch Alaska Pipeline
`Company, LLC (“Koch”); and Unocal Pipeline Company (“Unocal”). Koch and
`Unocal withdrew from TAPS ownership and cancelled their TAPS tariffs
`effective August 1, 2012.
`The $229.2 million would be part of the total system cost of service that is
`allocated through rate design between the interstate and intrastate costs of service.
`
`3
`
`
`
`
`
`

`

`in accordance with the findings of fact and law to ensure that rates are just and
`
`reasonable.
`
`II.
`
`SUMMARY
`
`
`
`The Presiding Judge found that “the Carriers were imprudent in the development,
`
`design, implementation and management” of the SR project, ID at P 1451, and that “the
`
`SR expenses at issue . . . cannot be flowed through rates.” ID at P 4. The Presiding
`
`Judge further found that the SR costs should be excluded from rates for the separate and
`
`independent reason that the project is “not used and useful and does not provide any
`
`discernable benefits to shippers.” ID at P 1674; see also ID at P 1588.
`
`
`
`To be clear, Anadarko fully endorses these findings. Yet, notwithstanding the
`
`finding that all SR costs are imprudent and cannot be flowed through rates, the remedy
`
`adopted by the Presiding Judge would allow $229.2 million of imprudent and
`
`unreasonable SR costs to be included in rates through an amortization in the cost of
`
`service. ID at P 1673. Specifically, the Presiding Judge adopted “Remedy 3” of five
`
`possible remedies proposed by Anadarko. Id. Anadarko’s proposed Remedy 1 would
`
`exclude from rates all SR capital costs and therefore is commensurate with the Presiding
`
`Judge’s findings of fact and law.4 Anadarko raises this limited exception in order to
`
`preserve for the Commission and possibly a future reviewing court the opportunity to
`
`consider the full array of remedies appropriate to establish just and reasonable rates.
`
`III.
`
`STATEMENT OF THE CASE
`
`These consolidated proceedings concern rates for TAPS for 2009 and 2010 rate
`
`periods, which were protested and set for hearing. The Chief Judge bifurcated the
`
`
`4
`
`Remedy 1 would exclude all capital costs of SR except for approximately $17
`million in Safety Integrity & Pressure Protection System (“SIPPS”) costs.
`
`
`
`2
`
`

`

`hearing into two phases:5 the SR phase, which the ID addressed, and the “Non-SR” phase
`
`which involved pooling and rate of return issues and is currently on appeal at the D.C.
`
`Circuit.6 Given that the SR phase involved issues common to both interstate and
`
`intrastate rates, FERC authorized concurrent hearings with the Regulatory Commission
`
`of Alaska.7
`
`The SR phase addressed a variety of TAPS rate issues, including the prudence and
`
`recoverability of SR costs, supplemental ad valorem taxes from prior periods, and other
`
`cost of service issues. The SR phase hearings spanned 48 days and produced an
`
`enormous record, including over 2000 exhibits and 12,294 transcript pages.8 The parties
`
`submitted 1,817 pages of briefing to the Presiding Judge.9 Briefs on exceptions to the ID
`
`are due May 16, 2014 and briefs opposing exceptions are due July 25, 2014.10 Further
`
`details concerning the SR phase procedural history may be found in the ID at PP 28-91.
`
`IV.
`
`POLICY CONSIDERATIONS WARRANTING FULL COMMISSION
`REVIEW AND OPINION
`
`
`
`The central policy consideration warranting Commission review is that of
`
`ensuring just and reasonable rates and protecting ratepayers from paying imprudent and
`
`unreasonable costs, as discussed in this brief.
`
`
`5
`
`BP Pipelines (Alaska) Inc., Order of Chief Judge Severing Strategic
`Reconfiguration Issues and Scheduling Prehearing Conferences, Docket Nos.
`IS09-348-000, et al. (Jan. 13, 2010).
`Tesoro Alaska Co. v. FERC, Case Nos. 13-1248 & 13-1249 (D.C. Cir. filed Sept.
`13, 2013).
`BP Pipelines (Alaska) Inc., 130 FERC ¶ 61,042 (2010).
`BP Pipelines (Alaska) Inc., Order of Chief Judge Extending Initial Decision
`Deadline, Docket Nos. IS09-348-004, et al., at P 1 (Oct. 30, 2013).
`Id.
`BP Pipelines (Alaska) Inc., Notice of Extension of Time, Docket Nos. IS09-348-
`004, et al. (Mar. 6, 2014).
`
`6
`
`7
`8
`
`9
`10
`
`
`
`3
`
`

`

`V.
`
`ARGUMENT
`
`A.
`
`Anadarko’s Five Remedy Formulations.
`
`Anadarko proposed for the Presiding Judge’s consideration five possible remedies
`
`in order of preference and appropriateness:
`
`Remedy 1:
`
`
`
`Remedy 2:
`
`
`
`
`Remedy 3:
`
`
`
`
`Remedy 4:
`
`
`
`Remedy 5:
`
`
`Exclude all SR capital costs from rates, except for SIPPS costs. ID at
`P 1424; Anadarko Initial Brief at 228-33.11
`
`Exclude all SR capital costs after initial project sanction and amortize in
`the cost of service SR capital costs in original sanction AFE S020. ID at
`PP 1425-26; Anadarko Initial Brief at 234-38.
`
`Exclude all SR capital costs beginning with AFE S020 Supplement 2 and
`amortize in the cost of service SR capital costs prior to AFE S020
`Supplement 2. ID at PP 1427-32; Anadarko Initial Brief at 238-44.
`
`Exclude all capital costs of SR electrification. ID at PP 1433-39;
`Anadarko Initial Brief at 244-51.
`
`Exclude SR Costs as supported in the State of Alaska’s case. ID at
`P 1440; Anadarko Initial Brief at 251-52.
`
`
`
`
`Notably, Anadarko’s Remedies 1-4 would fully exclude all SR capital costs from
`
`rate base, although Remedies 2-4 would permit the Carriers to amortize a portion of SR
`
`costs in their cost-of-service.12 This is consistent with the Presiding Judge’s finding that
`
`all SR costs are imprudent and that “it is unfair to require TAPS ratepayers to pay the
`
`Carriers additional return and taxes due to the inflated costs of a poorly planned and
`
`managed project.” ID at P 1447.
`
`
`11
`
`Post Hearing Initial Brief of Anadarko Petroleum Corp. and Tesoro Alaska Co.
`Following Supplemental Prudence Hearing, Docket Nos. IS09-348-004, et al.
`(Nov. 30, 2012) (“Anadarko Initial Brief”).
`See ID at PP 1425 (Remedy 2), 1427 (Remedy 3), 1433 (Remedy 4); Anadarko
`Initial Brief at 234 (Remedy 2), 238 (Remedy 3), 244 (Remedy 4). All of these
`remedy options propose exclusions of SR capital costs. None attempt to identify
`exclusions of operation and maintenance expenses associated with SR.
`
`12
`
`
`
`4
`
`

`

`
`
`Anadarko proposed this “menu” of remedy options because, while Anadarko
`
`argued that the evidence clearly demonstrated that the SR project was imprudent and not
`
`used and useful to ratepayers, it was impossible to know which remedy would suit the
`
`Presiding Judge’s factual and legal findings. Those findings are now clear.
`
`B.
`
`The Presiding Judge Found that All SR Costs Are Imprudent and
`Otherwise Unrecoverable in Rates.
`
`
`
`The Presiding Judge found that “the Carriers were imprudent in the development,
`
`design, implementation and management” of the SR project. ID at P 1451. Further, the
`
`Presiding Judge ruled that “the SR expenses at issue (which at the time of this decision is
`
`approximately $750 million) were imprudently incurred and cannot be flowed through
`
`rates.” ID at P 4. The Presiding Judge stated, “[s]ince the costs were imprudent, the
`
`recovery of these costs should not be allowed.” ID at P 1458. Additionally, the
`
`Presiding Judge found that SR costs should be excluded from rates for the separate and
`
`independent reason that the project is “not used and useful and does not provide any
`
`discernible benefits to shippers.” ID at P 1674; see also P 1588. In sum, the Presiding
`
`Judge concluded that the costs of SR “should be borne by shareholders and not
`
`ratepayers.” ID at P 1455.
`
`C.
`
`The Presiding Judge’s Selection of Remedy 3 Would Allow $229.2
`Million of Imprudent and Unreasonable SR Costs to be Recovered in
`the Cost of Service.
`
`More than 500 pages of the ID address the Judge’s findings that all SR costs are
`
`imprudent and otherwise not suitable for recovery in rates. Yet, the Presiding Judge
`
`allows the Carriers to recover $229.2 million as a “remedy in equity” because “there are
`
`new assets in the ground [thus] it seems reasonable to let the Carriers recover some of the
`
`costs.” ID at P 1459.
`
`
`
`5
`
`

`

`Specifically, the Presiding Judge adopted Anadarko’s Remedy 3, ID at PP 4,
`
`1458, 1673, which allows the Carriers to amortize $229.2 million of SR capital costs in
`
`their cost of service, outside of rate base and with no return, over the remaining life of
`
`TAPS. ID at P 1427. The $229.2 million allowed under Remedy 3 is the cost level
`
`included in the Carriers’ original corporate authorization that sanctioned the SR project,
`
`i.e. AFE S020,13 plus amount authorized by Supplement 1 to AFE S020.14 As proposed
`
`by Anadarko and adopted by the Presiding Judge, the $229.2 million serves as an
`
`absolute cap on SR recovery for both historic rate periods and future rate periods. ID at
`
`P 1458. Remedy 3 excludes $225.2 million in SR capital costs for 2009 and 2010 rate
`
`periods. ID at PP 1427, 1458.
`
`In explaining why SR cost recovery should be cut off beginning with
`
`Supplement 2,15 the Presiding Judge found that “SR was a discretionary project with the
`
`purpose of reducing costs.” ID at P 1453. Yet, by the time the Carriers were considering
`
`whether to authorize Supplement 2, the Presiding Judge found that they knew that “SR
`
`was off track, original cost estimates were wrong, the scope was not defined, contractors
`
`were not performing, and the economics were not favorable.” ID at P 1444. “When
`
`Exxon evaluated the project economics at Supplement 2 it . . . determined that SR had a
`
`negative net present value. At this point in time they should have stopped and analyzed
`
`
`13
`
`AFE S020 authorized $216.3 million in capital costs. This amount consisted of
`$206.3 million in new funding plus $10 million in capital previously approved.
`Ex. SOA-60 at 2 (Cost Summary); see ID at P 1425.
`Supplement 1 to AFE S020 authorized an additional $16.9 million of additional
`funding for self-generation of power at Pump Station 1. Ex. SOA-65 at 6 (Cost
`Summary).
`See generally ID at PP 1427-1432, 1458; Anadarko Initial Brief at 238-44.
`
`14
`
`15
`
`
`
`6
`
`

`

`the economics of the project and they did not.” ID at P 1452 (citation omitted). The
`
`Presiding Judge concluded:
`
`At supplement 2 the Carriers knew the project was a “train wreck.” Costs
`had nearly doubled, the schedule could not be accomplished, contractors
`were underperforming, the owners were failing to make timely decisions,
`engineering delays, design issues, revision of drawings, unproven pump
`motors, the scope of the project was not well defined (the project scope
`was not fully established until well into detailed design) significant
`brownfield work, inadequate cost accounting. The Carriers knew the
`original cost estimates were wrong. The benefits were eroded once the
`schedule had changed.
`
`ID at P 1458.
`
`
`
`The Presiding Judge further found “[o]wner misalignment and upstream interests
`
`were elements of imprudence at sanction, at approval of supplement 2,” in particular
`
`“BPPA’s concern for its affiliate booking of additional reserves [which] led it to push for
`
`additional funding for SR.” ID at P 1115, see ID at PP 1063, 1067, 1070, 1111, 1169. At
`
`the same time BP executives had determined that SR was a “train wreck” and a
`
`“performance bust,” ID at PP 1036, 1455, “they were advocating that the project continue
`
`because BPXA, the production affiliate, had booked 63 million barrels of oil based on the
`
`SR project.” ID at P 1455; see also ID at P 1067.
`
`
`
`Anadarko certainly understands the Presiding Judge’s rationale for adopting
`
`Remedy 3, which was one of Anadarko’s proposals. However, Anadarko made multiple
`
`remedy proposals because it was not certain what factual and legal findings the Presiding
`
`Judge would make. Now, in light of the ID, it cannot be ignored that Remedy 3 allows
`
`the Carriers to recover from ratepayers $229.2 million of SR capital costs that the
`
`Presiding Judge found to be imprudent and otherwise not suitable for recovery in rates.
`
`See supra Section V.B.
`
`
`
`7
`
`

`

`D.
`
`Remedy 1 Is Commensurate with the Presiding Judge’s Findings
`Regarding the SR Project.
`
`
`
`Anadarko’s proposed Remedy 1 would exclude from TAPS rates all capital costs
`
`of the SR project, except SIPPS costs. ID at P 1424; Anadarko Initial Brief at 228-33.
`
`Remedy 1 comports with the breadth of the Presiding Judge’s findings that “the Carriers
`
`were imprudent in the development, design, implementation and management” of the SR
`
`project, ID at P 1451, and that the project is “not used and useful and does not provide
`
`any discernible benefits to shippers.” ID at P 1674; see also id. at P 1588. Remedy 1
`
`would ensure that ratepayers do not pay costs found to be imprudent and unreasonable
`
`and properly places responsibility for the project on the pipeline owners – who were in
`
`full control of the project.16
`
`E.
`
`Anadarko’s Other Remedy Proposals.
`
`The Presiding Judge commented favorably on all of Anadarko’s remedy
`
`proposals, stating “Anadarko’s remedies are consistent with the evidence in this case and
`
`case law.” ID at P 1443. As discussed above, while the Presiding Judge selected
`
`Remedy 3, Remedy 1 is commensurate with the Presiding Judge’s factual and legal
`
`findings. Given that the ID is subject to review, Anadarko also raises on exceptions its
`
`16
`
`The Presiding Judge viewed it as equitable to permit some recovery of capital
`costs by the Carriers because there are “new assets in the ground.” ID at P 1459.
`However,
`these new assets
`resulted
`from
`imprudent planning and
`mismanagement. ID at PP 1456-59. Indeed, the Presiding Judge found that the
`new turbines are not appropriately sized, ID at P 1521, and should not have been
`electrified. ID at PP 348, 425, 1451. Moreover, concerning the automated
`control system, the Presiding Judge found that “the Carriers automated in an
`imprudent manner . . . and then what was developed is substandard.” ID at
`P 1460; see ID at PP 1552, 1557-62. Thus, from the ratepayers’ perspective,
`simply because the assets are in the ground does not support increased rates for
`equipment that was imprudently constructed, improperly sized, and otherwise not
`beneficial to shippers. Indeed, the ratepayers already paid for the existing
`equipment, which, as the ID found, remained adequate to the task. ID at PP 1451,
`1456.
`
`
`
`8
`
`

`

`additional remedy proposals for the purpose of preserving these remedy options for the
`
`Commission and possibly a reviewing court.
`
`Remedy 2 (Exclude all costs after initial project sanction)
`
`Anadarko’s proposed Remedy 2 would exclude from rates all SR capital costs
`
`above the initial sanction amount of $216.3 million set forth in AFE S020. The $216.3
`
`million would be amortized in the cost of service over the remaining useful life of TAPS,
`
`but would not be allowed rate base treatment and therefore would earn no return. The
`
`$216.3 million would serve as an absolute cap on SR capital cost recovery. Thus, for
`
`2009 and 2010 rates, $238.1 million of SR capital costs would be excluded, and no
`
`further SR capital cost recovery would be permitted in future TAPS rates. ID at P 1425;
`
`Anadarko Initial Brief at 234-38. As the Presiding Judge explained, “this proposal would
`
`charitably give the Carriers the costs of the project they believed would be used and
`
`useful, while protecting the ratepayers from the increased costs of the poorly executed SR
`
`project.” ID at P 1426.
`
`Though she did not select it, the Presiding Judge commented that Remedy 2
`
`“gives the Carriers the benefit of the doubt on their initial sanction decision even though
`
`the evidence in this case supports the finding that at that point in time the economics of
`
`SR were indeed dubious. [Remedy 2] is a ceiling on ratepayer benefits and utility of the
`
`project.” ID at P 1443. Additionally, Remedy 2 is very similar to, and is the foundation
`
`for, Remedy 3, which the Presiding Judge adopted. Those remedies are identical, except
`
`that Remedy 2 would exclude the cost of Supplement 1 ($16.9 million), which is included
`
`under Remedy 3.
`
`
`
`9
`
`

`

`Remedy 4 (Exclude electrification costs)
`
`Anadarko’s Remedy 4 would exclude from rates the capital costs associated with
`
`the electrification of the pump stations. For 2009 and 2010 rates, $397.1 million would
`
`be excluded from TAPS rates, and $57.3 million would be amortized in the cost of
`
`service, outside of rate base, over the remaining useful life of TAPS. ID at P 1433; see
`
`Anadarko Initial Brief at 244-45. Anadarko witness Gary Grasso developed this remedy
`
`calculation based on actual capital cost data in the record, at the request of the Presiding
`
`Judge. Anadarko Initial Brief at 244-45. Again, while the Presiding Judge selected a
`
`different remedy, she favorably commented that “Anadarko’s fourth disallowance theory
`
`under use[d] and useful would be equitable.” ID at P 1674.
`
`Remedy 5 (State’s remedy)
`
`
`
`In addition to proposing the four remedy formulations discussed above, Anadarko
`
`also supported the State’s proposed remedy as a fifth option. Anadarko understands that
`
`the State will discuss its remedy option in its brief on exceptions.
`
`VI. CONCLUSION
`
`
`
`Wherefore, for the foregoing reasons, Anadarko respectfully requests that the
`
`Commission promptly affirm the ID, subject to Anadarko’s limited exception discussed
`
`above.
`
`
`
`10
`
`

`

`By /s/ Robin O. Brena
`Robin O. Brena
`David W. Wensel, Esq.
`Anthony S. Guerriero, Esq.
`BRENA, BELL & CLARKSON, P.C.
`810 N Street, Suite 100
`Anchorage, Alaska 99501-2014
`Telephone: (907) 258-2000
`Facsimile: (907) 258-2001
`rbrena@brenalaw.com
`dwensel@brenalaw.com
`aguerriero@brenalaw.com
`
`By /s/ Joseph S. Koury
`Joseph S. Koury, Esq.
`Jeffrey G. DiSciullo, Esq.
`Andrew T. Swers, Esq.
`WRIGHT & TALISMAN, P.C.
`1200 G Street, N.W.
`Washington, D.C. 20005-3802
`Telephone: (202) 393-1200
`Facsimile: (202) 393-1240
`koury@wrightlaw.com
`disciullo@wrightlaw.com
`swers@wrightlaw.com
`
`
`
`
`
`
`
`Sherri B. Manuel, Counsel
`Anadarko Petroleum Corporation
`1201 Lake Robbins Drive
`The Woodlands, Texas 77380
`Telephone: (832) 636-1000
`Facsimile: (832) 636-8001
`sherri.manuel@anadarko.com
`
`Attorneys for
`Anadarko Petroleum Corporation
`
`
`
`May 16, 2014
`
`
`
`
`
`11
`
`

`

`
`
`
`
`CERTIFICATE OF SERVICE
`
`I hereby certify that I have this day served the foregoing document upon each
`
`person designated on the official service list in accordance with the protective order
`
`issued in this proceeding.
`
`
`
`Dated at Washington, D.C., this 16th day of May, 2014.
`
` /s/ Andrew T. Swers
`Andrew T. Swers
`Wright & Talisman, P.C.
`1200 G Street, N.W., Suite 600
`Washington, D.C. 20005-3802
`(202) 393-1200
`
`Attorney for
`Anadarko Petroleum Corporation
`
`
`
`
`
`

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket