throbber
Exhibit Mo. ATC-344
`
`Page 1 of 2
`=
`From: Bametl, John T <John. T Bamet@conocophil ips.coms
`Sent: Thursday, Dctober D8, 2005 11:01 AM
`To Flood, Patrick M <Patrick M.Flood fconocophil lips. com:
`Subject: FW: DRAFT REPLY: Alyeska reconfiguration - lettar to Mulva
`e —
`Fram: Frogd, Patrick M
`Sant: Wednesday, October 05, 2005 +4:58 PM
`Ta: Earmett, oo T
`[= - Drumm, Tk
`Sulbfoct: FE: DRAFT REFLY; Alyeska neconfigurstion - letier to Muiva
`
`| added same additional language and eliminated the informalion that can ba found In the altachmant,
`
`Pra-sanction Review
`
`A pre-sanction Owner review of the TAPS Strategic Reconfiguration Project was performed in
`October 2003 (note an early preliminary engineering projact assist/raview was hald June
`2003). Al fiva Owner Companies participated, ConocoPhillips had 7 represantativas, 5 from
`Infrastructure Engineering and Project Management. A joint Owners' reporl was issued
`immediately following the review. Tha report, including a list of action items and attendeas, is
`altached.
`
`Post Review Actions
`
`All recommanded actions and deliverables wera addressad prior lo sanction of the AFE. The
`AFE costs were raviewed by third partias, including Larkspur and Alaska Construction
`Contractors, Savings were scrutinized by Owners' staff. The next best alternative was fully
`evaluated and a comparison of alternatives was completed on a component basis. Costs
`ralated to separately juslified work were identified and funded separately. The probability
`analysis included costs, savings, and a prediction of overall project performance. A detailed
`project execulion plan indicaled a tight schedule with zero floal, but the project appeared
`doable with timely decisions. The impact of delay was analyzed, but not recommended
`bacause of increased costs and a significant loss of savings.
`
`Original Project Sanction Timing
`Tha AFE was approved in March of 2004. Long-lead materials were orderad immediately and
`delailed engineering began.
`
`Project Challenges in Hindsight, Current Outlook
`The project team was handed a deadline and conceptual engineering cost estimates that were
`improperly used as banchmarks. The project was "boxed” into those parameters instead of baing
`allowed to fully evaluate options, costs, and risks. The resulting cost estimates and probability
`analyses were not realistic. This did not become apparent until additional engineering was
`
`completed.
`
`For schedule reasons, the project was approved at the end of preliminary engineering. The
`angineering appeared to be well progressed at that point, but the project scope was not fully
`astablished until well into detailed design. Several assumptions from concaptual engineering and
`
`1 FEDERAL ENERGY REGULATORY COMMESSION
`
`e s
`f 2= iY9-
`[k cburetified: 1 L1 TERE 1
`
`
`
`
`
`
`
`
`
`Exhibit No. ATC-344
`
`the "value engineering” process were too aggressive and had to be changed. Page 2of 2
`
`During detailed design, the engineering contractor did not secure sufficient resources and did not
`amploy effective projact controls. This contributed to schedule slippages and the inability to predict
`cost and schedule impacts. Slow decisions, lack of stakeholder alignment, and insufficient
`engineering resources caused significant delays.
`
`The Owner-lead initiative created resistance within the Alyaska organization that resulted in a lack of
`internal resources and alignment. It is obvious that the project would not have progressed to this
`point without cutside help, but the resistance was more than anticipated and caused significant
`
`problems and delays.
`
`Operaticnal readiness conlinues 1o be a concern, but the recent changes to make this an
`Alyaska-lead project should help create alignment. Additional Alyeska resources have
`already been added to the team. Alyeska has lakan over project managament from the
`engineering cantractor and the project execution plan has been revised to includa detailed
`plans from Alaska Construction Contractors. Module fabrication is over 50% complete and
`fiald construction is approximataly 20% complete. The Owners companies will continue to
`watch progress and inlervene, as necessary.
`
`TSRCOPOD105524
`
`
`
`
`
`
`
`
`

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket