throbber
_seq-~396,e¢ te
`
`STINSON
`LEONARD
`STREET
`
`Bovid W.D'Alessandro
`
`202.728.3014 DIRECT
`202.572.9989 DIRECT FAX
`devid.dalessandro@sfinson.com
`
`.
`
`2
`
`.
`
`.
`see bt stepth FILED
`. SECEAT:7 OFTHE mS
`Be
`
`2b Ji28 PF 13
`
`
`aTAMEEctaeaa
`
`Lo hat
`
`wacotiinoe
`
`
`District of Columbia Circuit
`E. Barrett Perryman U.S. Courthouse
`333 Constitution Avenue, N.W.
`
`Washington, DC 20001-2866
`
`
`NITED STAT.aCv"2OF APPEALS
`ORIGINAL
`ARDISTRICT OFCOLUMBIACIRCUIT
`
`
`JAN 79 2016
`
`
`.
`
`t§- 102 2
`
`Re:
`
`Koch Alaska Pipeline Company, LLC v. Federal Energy Regulatory Commission.etal.,
`Case No. 16-
`
`Dear Mr. Langer.
`
`Enclosed forfiling in the captioned proceeding are an original and four copies of the
`Petition for Review of Koch Alaska Pipeline Company, LLC and Corporaie Disclosure
`Statement. Also enclosed ts a filing fee of $500.00 payable to Clerk, U.S. Court of Appects,
`and a copyof the Federal Energy Regulatory Commission order on appeal. We have also
`enclosed two exira copies of fhesefilings. Please time and date stamp these additional
`copies and retum them to the courier.
`IF you have any questions regarding this filing. please contact the undersigned.
`
`Respectfully submitted,
`
`Stinson Leonard Street LLP
`
`Aud Whvobypg
`
`’ David W. D' Alessandro
`
`;
`|
`
`|
`
`DWD:SLS
`
`Enclosures
`
`ce:
`
` Afl parties to proceedings
`
`STINSON.COM
`
`GORE(30054699.0002/1 14016745.)
`
`wee
`
`&
`
`-
`
`W775 PENNSYLVANIA AVENUE N.W., SUITE 800 * WASHINGTON, DC 20006
`202.785.9100 MAIN «© 202.785.9143 FAX
`
`

`

`
`
`THE DISTRICT OF COLUMBIA CIRCUIT
`UNTER STATES COUNT OF
`FOR DISTRICT CF COLUNGIAGIRGUTT
`
` IN THE UNITED STATES COURT OF APPEALS
`
`KOCH BNUtesPIPELINE
`COMBROEWED
`
`yp
`
`.
`16-1022
`
`) )
`
`)
`} No
`}
`)
`)
`
`) )
`
`))
`
`Petitioner,
`
`VS.
`
`.
`FEDERAL ENERGY
`_ REGULATORY COMMISSION
`AND UNITED STATES OF
`AMERICA -
`
`‘Respondents.
`
`PETITION FOR REVIEW
`
`Pursuantto Rule 15 ofthe Federal Rules ofAppellate Procedure and 28
`«USC. 85 2342-2344, Koch Alaska Pipeline Company, LLC hereby petitions this
`
`Court for review of BP Pipelines (Alaska) Inc.,Order on Initial Decision, 153
`FERC { 61,233 (Nov. 20, 2015), issued by Respondent Federal Energy Regulatory
`Commission in DocketNos. [S09-348-004, etal. (“Opinion No. 544”). A copyof
`Opinion No. 544 is attached hereto as Exhibit A.
`ae
`
`

`

`
`
`Respectfully submitted,
`
`Anat)(oancbeiws
`
`David D’Alessandro
`Kelly A. Daly
`M. Denyse Zosa
`Stinson Leonard Street LLP
`1775 Pennsylvania Ave NW, Suite 800
`Washington DC, 20006
`(202) 785-3100
`(202) 785-9163- Fax
`david.dalessandro@stinson.com
`kelly.daly(@stinson.com
`denyse.zosa(@stinson.com
`
`Counselfor Koch Alaska Pipeline
`Company, LLC
`
`Dated: January 19, 2016
`
`

`

`
`
`
`IN THE UNITED STATES COURT OF APPEA
`
`
`
`_
`
`) ) ))
`
`Cl TORRENS
`ITED STATES
`asp TIT
`OFCOLNEcIRCUT
`aapworeBURYOFAPRDISTRICT OF COLUMBIA CIRCY
`
`FOR DISTRICTOF 60
`:
`uo}
`uAN 19 2018
`KOCH
`\gIPELINE
`COMPRECEIVER
`
`
`
`CLERK
`
`No__.__16-1022
`
`)
`)
`)
`
`)) )
`
`~
`FEDERAL ENERGY
`REGULATORY COMMISSION
`AND UNITED STATES OF
`AMERICA
`
`Respondents.
`
`CORPORATE DISCLOSURE STATEMENT
`OF KOCH ALASKA PIPELINE COMPANY, LLC
`
`Pursuant to Rule 26.1 of the Federal Rules of Appellate Procedure and the
`Rules of this Court, Koch Alaska Pipeline Company, LLC (““KAPCO”)
`respectfully submits ihis Corporate Disclosure Statement. During the period at
`issue in this proceeding, KAPCO owned an interest in the Trans Alaska Pipeline
`
`System (“TAPS”) and providedtransportation service through TAPS in accordance
`with the terms ofits tariff. KAPCOis a limitedliability company organized under
`the laws of the state of Alaska. KAPCO is wholly owned by Koch Pipeline
`Company, L.P., a Delaware limited partnership. No publicly held corporation
`
`owns 10% or more of KAPCO’s stock.
`
`

`

`
`
`Koch Alaska Pipeline Company, LLC is also an indirect subsidiary of Koch
`
`Industries, Inc., a Kansas corporation. Koch Industries, Inc. has no parent, noris
`
`there any publicly held company that holds a 10% or larger interest in Koch
`
`Industries, Inc.
`
`Respectfully submitted,
`
`
`
`Kelly A. Daly
`M. Denyse Zosa
`Stinson Leonard Street LLP
`1775 Pennsylvania Ave NW, Suite 800
`“Washington DC, 20006
`(202) 785-3100
`(202) 785-9163- Fax
`david.dalessandro@stinson.com
`kelly.daly@stinson.com
`denyse.zosa(@stinson.com
`
`Counselfor Koch Alaska Pipeline
`Company, LLC
`
`' Dated: January 19, 2016
`
`

`

`EXHIBITA|
`
`[copy of Opinion No. 544]
`
`

`

`
`
`153-FERC f 61,233
`UNITED STATES OF AMERICA
`
`FEDERAL ENERGY REGULATORY COMMISSION
`
`OPINION NO. 544
`
`BP Pipelines (Alaska)Inc.
`BP Pipelines (Alaska) Inc.
`BP Pipelines (Alaska) inc.
`BP Pipelines (Alaska) Inc,
`ConocoPhillips Transportation Alaska Inc.
`ConocoPhillips Transportation Alaska Inc.
`ConocoPhillips Transportation Alaska Inc.
`
`ExxonMobil Pipeline Company
`ExxonMobil Pipeline Company
`ExxonMobil Pipeline Company
`ExxonMobil Pipeline Company
`
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`Koch Alaska Pipeline Company, L.L.C.
`Koch Alaska Pipeline Company, L-L.C.
`
`_ BP Pipelines (Alaska) Inc.
`BP Pipelines (Alaska) Inc.
`BPPipelines (Alaska) Inc.
`BP Pipelines (Alaska) Inc.
`
`Docket No. 1809-348-004
`Docket No. 1S09-395-004
`Docket No. 1810-204-002
`Docket No. 18 10-491-000
`
`Docket No. IS09-384-004
`Docket No. IS 10-205-003
`Docket No. IS10-476-001
`
`Docket No. IS09-391-004
`Docket No. IS09-177-005
`Docket No. I810-200-002
`Docket No. I1S10-547-000
`
`Docket No. 1S09-176-004
`Docket No. IS07-41-005
`Docket No. 1S808-53-005
`Docket No, IS10-52-001
`Docket No. OR10-3-001
`Docket No. 1810-490-000
`. Docket No. IS11-3-000
`
`Docket No. IS 10-54-001
`Decket No. IS 10-496-000
`
`Docket No. 1S09-348-006
`Docket No. 1809-395-006
`Docket No. 1810-204-004
`Docket No, IS10-491-003
`
`ConocoPhillips Transportation Alaska Inc.
`ConocoPhillips Transportation Alaska Inc.
`ConocoPhillips Transportation Alaska Inc.
`
`Docket No. IS09-3 84-006
`Docket No. I§10-205-005
`’ Docket No. IS10-476-003
`
`

`

`
`
`~ Docket No. 809-348-004,er al.
`
`ExxonMobil Pipeline Company
`ExxonMobil Pipeline Company
`ExxonMobil Pipeline Company
`ExxonMobil Pipeline Company
`
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`
`Koch Alaska Pipeline Company, L.L.C.
`Koch Alaska Pipeline Company, L.L.C.
`
`-ii-
`
`Docket No. IS09-391-006
`Docket No. IS09- 177-007
`Docket No. [§10-200-004
`Docket No. IS10-547-002
`
`Docket No. IS09-176-006
`Docket No. I807-41-007
`Docket No. IS08-53-007
`Docket No. 1§10-52-003
`Docket No. OR10-3-004
`Docket No. IS10-490-002
`Docket No. IS1 1-3-002
`
`Docket No. I§10-54-003
`Docket No. IS10-496-003
`
`ORDER ON INITIAL DECISION
`
`Issued November 20, 2015
`
`

`

`Docket No. IS09-348-004,etal.
`
`- fii -
`
`OPINION NO. 544
`
`TableofContents
`
`Page
`
`4.
`
`Future CarrierFilingstoRecoverfor SRProjectUpgrades.sevenaneeaeescsessventes -55-
`
`General Background ..........cccsccssscsssessensnceecesocseatsnsesesnssanaeetsetseserssssseesevarseseaaeeeones -2-
`T.
`Il. Prudence of the SR Project..........ssssssssssssesseeeessassassensecteaseceecectansaceerseeseecnereconeeas ~4-
`A. Description of the SR Project .......-.ccssssssscssessscnssssanssersssseseeeersseccenessenssteeeenesees -4-
`B.
`Initial Decision... ccescessssseensestsscssssecscecsonsensnsscneusuqensyssssatstenstansutyenseteetanseaes -~7-
`CC.
` DASCUSSIONL..........sccccsceseeeseercanseneeorenensssersnarsecrsnseesaseatedecerteseeessseceees senses snrenerecsesers -§8-
`Serious Doubt Exists Regarding the SR Project ..............cc.-sscessssssseeeeereres - 10-
`The Carriers Have Not Satisfied Their Burden..................peetessennsnececenatentes -24-
`Prudence Remedies.............ccessssecescsossertescsssvescesencobesqasnavatteatsuaneasarauessseosens - 50-
`
`1.
`2,
`3.
`
`TH.—_Basse and Test Period .........:sssscsssssscesssecessessssesennsensnsnssneareesesestuarsenessanenennsteosane - 57-
`A. The Initial Decision .................cccseccsnesenessccensaseenenseencedysnascenaseeessntenseaseseensesnets -57-
`B. Briefs On and Opposing Exceptions ......0........ecssesscseesiessescenseeesensteetsarenvarteases -57-
`C. Commission Decision......:sccccssereresccsssecscesscssssecssesteneersestacsceasutateetenssetseotetaas ~ 58-
`TV.
`Add Valorem Taxes........cenesssusssrrecsesseessssseassnerayenssatesrsaseeenssaseeeetesensssarsaterssnrase - 59-
`A. The Initial Decision ............:..sceesencsecessatscensennsecsesgateettnenedunsensteraueasasttnatstesaeeas - 59 -
`B. Briefs On and Opposing Exceptions -..........scscsseselecctseeseesesccanensenseesesrereteeees - 59-
`C. Commission Decision..............c.cescecssssreressencensseneneteccecenesensserseneegarsenaeneces sense -61-
`V. Litigation Expenses .......scccsssssssessseeseessesetsnseersereetsensteceerenae nsacesntonensssnesceseeasenens - 62 -
`A.
`TheInitia] Decision ..............ccccacescesssrartoressacssacnsaceessrascanseesecerenssseargnesaetesaaases - 62-
`B. Briefs On and Opposing Exceptions .............:.--cssesssssseceerseesrrstserssnegneeateaeseeee - 63 -
`C. Commission Decision..............:scccessscssscesenerscssvepstesnenscesesstugaetevacsengenscsueseavens? - 63 -
`VIL
`Oil-Spili-Related Cost of Service ISsves............:.ccueeccccarssereneerersersserseneeceeteeenes - 65 -
`A.
`Initial Decision 20... ccscescceccenseeeseeecnessnsensersessegepateesnsasgressaneters¢sansuqeenataceaseees - 65 -
`B. Briefs On and Opposing Exceptions ............:ccscssscsssseneesseccerarseneneceaseceataaeatees - 65 -
`C. Commission Decision... eeececceceeeeesenseesenenseretseesseersnenncseeceepegeunsearecennsoen - 65 -
`
`

`

`
`
`153 FERC 61,233
`UNITED STATES OF AMERICA
`’. FEDERAL ENERGY REGULATORY COMMISSION
`
`Before Commissioners: Norman C. Bay, Chairman;
`Cheryl A. LaFleur, Tony Clark,
`and Colette D. Honorable.:
`
`BP Pipelines (Alaska) Inc.
`BP Pipelines (Alaska) Inc.
`BPPipelines (Alaska) Inc.
`BP Pipelines (Alaska) Inc.
`
`ConocoPhillips Transportation Alaska Inc.
`ConocoPhillips Transportation Alaska Inc.
`ConocoPhillips Transportation Alaska Inc.
`
`ExxonMobil Pipeline Company
`ExxonMobil Pipeline Company
`ExxonMobil Pipeline Company
`ExxonMobil Pipeline Company
`
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`
`Koch Alaska Pipeline Company, L.L.C,
`Koch Alaska Pipeline Company, L.L.C.
`
`BP Pipelines (Alaska) Inc.
`BPPipelines (Alaska) Inc.
`BP Pipelines (Alaska) Inc.
`BP Pipelines (Alaska) Inc.
`
`ConocoPhillips Transportation Alaska Inc.
`ConocoPhillips Transportation AlaskaInc.
`ConocoPhillips Transportation Alaska Inc.
`
`Docket No, 109-348-004
`Docket No. IS09-395-004
`Docket No. IS10-204-002
`Docket No. IS10-491-000
`
`Docket No. IS09-384-004
`Docket No. IS10-265-003
`Docket No. IS10-476-001
`
`Docket No. IS09-391-004
`Docket No. [S09-177-005
`Docket No. 1§ 110-200-002
`Docket No. IS10-547-000
`
`Docket No. IS09-176-004
`Docket No. IS07-41-005
`Docket No. 1808-53-005
`Docket No. IS10-52-001
`Docket No. OR10-3-001
`Docket No. IS10-490-000
`Docket No. IS11-3-000
`
`Docket No. I$10-54-001
`Docket No. IS10-496-000
`
`Docket No. IS09-348-006
`Docket No. [S09-395-006
`Docket No. [810-204-004
`Docket No. IS10-491-003
`
`Docket No. IS09-384-006
`Docket No. 1810-205-005
`Docket No. [S10-476-003
`
`

`

`
`
`Docket No. IS09-348-004,ef al.
`
`.
`
`-2-
`
`ExxonMobil Pipeline Company
`ExxonMobil Pipeline Company
`ExxonMobil Pipeline Company
`ExxonMobil Pipeline Company
`
`;
`
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`Unocal Pipeline Company
`
`Docket No. 1S09-391-00
`Docket No. IS09-177-007
`Docket No. IS 10-200-004
`Docket No. IS10-547-002
`
`Docket No. IS09-176-006.
`Docket No. IS07-4 1-607
`Docket No. IS08-53-007 |
`Docket No. IS10-52-003
`Docket No, OR10-3-004
`Docket No. IS 10-490-002
`Docket No. IS11-3-002
`
`Koch Alaska Pipeline Company, L.L.C.
`Koch Alaska Pipeline Company, L.L.C.
`
`Docket No. 1S10-54-003
`Docket No. I$10-496-003 .
`
`OPINION NO. 544
`
`ORDER ONINITIAL DECISION
`
`(Issued November 20, 2015)
`
`This order addresses briefs on and opposing exceptions to an Administrative Law
`i.
`Judge’s Initial Decision’ regarding 2009 and 2010rate filings on the Trans Alaska
`Pipeline System (TAPS). As discussed below, the Commission generally affirms the
`Initial Decision while granting exceptions regarding the remedy for imprudence and
`litigation costs.
`
`L.
`
`General Background
`
`TAPSconsists of a 48-inch diameter oil pipeline andits related facilities. The
`2.
`pipeline is about 800 miles long and transports commingled crude oil produced from
`different fields on the Alaska North Slope (ANS)from Prudhoe Bayto the Port of
`Valdez. TAPS is owned by the Carriers.? Each Carrier possesses an entitlement toits
`
`1 BP Pipelines (Alaska) Inc., 146 FERC 63,019 (2014)(Initial Decision).
`
`At the time ofthe 2009 and 2010 rate filings issue in this proceeding, the TAPS
`Carriers consisted of BP Pipelines (Alaska) Inc. (BP), ConocoPhillips Transportation
`Alaska, Inc. (ConocoPhillips), ExxonMobil Pipeline Company (ExxonMobil), Koch
`(continued...)
`
`

`

`
`
`“Docket No. IS09-348-004, etal.
`
`-3-
`
`|
`
`percentage ownership share of the pipeline’s capacity, and each Carrier posts its own
`tariffs and has its own customers. The TAPS system is operated by Alyeska Pipeline
`Service Company (Alyeska). Alyeska is jointly owned by the Carriers in direct
`proportion to their ownership of TAPS.*
`
`3.. The Carriers madeaseries ofrate filings which have been consolidated with this |
`
`
`
`proceeding. The filings were protested, and the Commission accepted and suspendedthe
`filings subject to refund and the outcomeof hearing procedures.* On February 27, 2014,
`the Presiding Judge issued an Initial Decision. On May 16, 2014,the Carriers, Anadarko
`Petroleum Corporation (Anadarko), the State ofAlaska (Alaska), Koch,° and
`.
`Commission Trial Staff (Trial Staff) filed briefs on exceptions. On July 25, 2014, the
`Carriers, Anadarko, Alaska, Trial Staff, and Flint Hills Resources Alaska, LLC (Flint
`Hills) filed briefs opposing exceptions.®
`
`Alaska Pipeline Company, LLC (Koch), and Unocal Pipeline Company (Unocal)
`(collectively, Carriers), Koch and Unocal provided final notice oftheir withdrawal from
`TAPS effective as of August 1, 2012. Koch has completed its exit, and Unocal is in the
`process, subject to applicable governmental approvals, of completing the transfer ofits
`TAPSinterests to the remaining Carriers.
`
`4 At its peak in 1998, TAPSthroughput averaged over 2 million barrels per day
`(bpd), while at the close of this record throughput averaged under 620,000 bpd. Carrier
`affiliates transport 95 percent ofthe throughput on the TAPS pipeline.
`
`* E.g., BP Pipelines (Alaska) Inc., 127 FERC J 61,316 (2009). TheInitial
`Decision contains an extensive procedural history describing the nature and timing of
`these filings. 146 FERC { 63,019 at PP 22-61.
`
`* Kochalso joined the Carriers’ brief, butfiled its own brief on exceptions.
`* Also, May 16, 2014, the Association of Oil Pipelines and the Interstate Natural
`Gas Association of America (collectively, AOPL/INGAA)filed a motion requesting
`leave to file an amicus brief supporting certain exceptions to the Initial Decision. On
`June 2, 2015, Anadarko filed an answer opposing AOPL/INGAA’s motion. The
`Commission denies AOPL and INGAA’s motion because theparties’ filings in this
`proceeding have provided a full analysis ofthe issues before the Commission. Mo.
`Interstate Gas, LLC, 142 FERC § 61,195, at P 2, order on reh’g, 144 FERC J 61,220
`(2013).
`
`.
`
`

`

`
`
`Docket No. IS09-348-004,egal.
`
`-
`
`_4-
`
`IL
`
`Prudence of the SR Project
`
`On exceptions, the Carriers assert that the Initial Decision erred by holding that the
`4.
`Strategic Reconfiguration Project (SR Project) was imprudently sanctioned for
`construction.’ Alaska, Anadarko, and Trial Staff filed briefs opposing exceptions urging
`the Commission to affirm the Initial Decision’s holding that the SR Project expenditures
`were imprudent. For the reasons discussed below, the Commission affirms the Initial
`Decision and holds that the SR Project was imprudent.*
`
`A.
`
`Description of the SR Project
`
`The SR Project was the largest modification to TAPS since the pipeline’s
`5.
`construction in the mid-1970s. TAPS was originally constructed with 11 pump stations,
`but only TAPS pumpstations Nos. 1, 3, 4, and 9 remain in use due to declining
`throughput. The SR Project involved replacing the four remaining pump stations with
`new pumps driven by variable-speed electric motors as opposed to the existing gas and
`diesel turbines. The SR Project also replaced the existing control systems in order to
`automate the pumpstations. At the time the SR Project began, the Carriers believed that
`the existing gas turbines could remain operational well into the future; however, the
`Carriers believed that the SR Project could reduce personnel and major maintenance
`expenses by $1.1 to $1.4 billion over a 20 year period.”
`
`|
`
`;
`
`” The Carriers do not challenge the Initial Decision’s holding that the SR Project
`was imprudently implemented, which would disallow $153.6 million under the Initial
`Decision’s holding. Carriers Brief on Exceptions at 4 (citing Initial Decision, 146 FERC
`{ 63,019 at P 1461).
`
`8 As an alternative to the prudence ruling, the ID foundthat — even if costs for the
`SR Project were prudently incurred — the SR Project was not “used and useful.” Initial
`Decision, 146 FERC 4 63,019 at PP 1587-1588. Given that the Commission is upholding
`the Initial Decision’s conclusion that the SR Project was imprudent, the Commission
`need not reach the alternative ruling.
`Eg, Ex. SOA-473 at 1; Ex. SOA-2] at 1; Ex. SOA-282 at 1; Ex. ATC-19 at 109; |
`Ex. ATC-147 at 22; Tr. 7980-7981; Ex. SOA-17 at 16; Ex. ATC-898 at 11-12; Ex. ATC-
`20 at 22.
`
`" E.g., TAPS Carriers’ Brief on Exceptionsat 1-2.
`
`

`

`
`
`Docket No. 1S09-348-004, efal. oT
`
`-5-
`
`Beginning in the 1990s, the Carriers and Alyeskainitiated a number ofstudies
`6.
`exploring different options for upgrading the existing TAPS System." In November
`2001, Dick Rabinow (President of ExxonMobil) and BilHowitt (AlyeskaSenior Vice
`President) advised consideration of a new “electrification option” using electric powered
`motors at all pumpstations.”!” Consistent with this recommendation, conceptual
`engineering began in February 2002 to evaluate two upgrade options: (a) the
`electrification proposal and (b) a hybrid option upgrading controls and automating the
`existing gas turbine infrastructure. The conceptual engineering process included an
`August 2002 report by General Electric Industrial Systems (GE), an August 2002 report
`by JTG Technologies (JTG), Alyeska’s October 2002 “Electrification versus Hybrid
`Decision Document,” and Alyeska’s “2003 Long Range Plan” to the Carriers.” Based
`on the conceptual engineering process, the Carriers elected to proceed with preliminary
`_ engineering for the electrification option.
`
`In order to oversee the SR Project, the Carriers formed in October 2002 the SR
`7.
`Project Team directed by John Barrett.“ In December 2002, the Carriers approved AFE
`$020 which authorized $7 million for preliminary engineering ofthe SR Project.'* The
`SR Project Team retained SNC-Lavalin Constructors Inc. (SNC-Lavalin) and Hinz
`Automation as the preliminary engineering contractors. These companies produced a
`Preliminary Engineering Design Report in November 2003.’ On December 18, 2003,
`Alyeska submitted AFE $020for project sanction of $242 million and the SR Project was
`projected to be completed by the end of 2005. The Carriers approved the Project, and in
`March 2004,the project transitioned from preliminary engineering to implementation."”
`
`"! These studies included: (a) the Alyeska Control and Telecommunication Long
`Range Plan (1994), (b) the Bailey Report (1997), (c) the Reinvestment Strategy Study
`(1999), (d) the VECO Report (1999), (e) Authorization for Expenditure F180 (AFE
`F180) (2000), and (g} Kenonic Controls Report (2000).
`
`” Carriers Brief on Exceptions at 28 (Ex. ATC-19 at 43-48; Ex. ATC-20 at 24-27).
`
`13 7g. 29 (Ex. ATC-147; Ex. ATC-148; Ex. ATC-154; Ex. ATC-153).
`
`"4 fd at 31 (citing Ex. ATC-24).
`15 Fd (citing Ex. ATC-165).
`
`16 id (citing Ex. ATC-208 through Ex. ATC-216).
`
`17 Id. at 33 (citations omitted). Contemporaneous with the submission of AFE
`$020, Alyeska separately submitted AFEs to upgrade the facilities and control systems at
`the ramp down stations no longer in use. Ex. SOA-73; Ex. SOA-76; Ex. SOA-80. The
`costs and savings of these other projects were considered in the “all in” electrification
`.
`(continued...)
`
`

`

`
`
`Docket No. IS09-348-004,ez al.
`
`-6-
`
`“In August 2004,“Alyeska submitted to the Carriers AFE S020, Supplement 1 secking
`additional funding of $26.5 million related to electric power at pumpstations 1 and 9.8
`
`It soon became clear that additional expenditures would be necessary due to
`8.
`inadequate engineering supporting theinitial increase.” In November 2005, the Carriers
`approved AFE $020 Supplement2 authorizing an additional $168.1 million.” However,
`the cost escalation continued.
`In September 2006, Alyeska submitted AFE S020
`. Supplement-3 for an additional $80.3 million dollars.” The Carriers did not approve
`AFE $020 Supplement 3 and, in order to control the escalating costs, the Carriers
`required subsequent funding requeststo be on a pump station by pumpstation basis. 7? In
`February 2007, Alyeska submitted a request for an addition $6.36 million related to
`Pump Station 9 in AFE $920.2 In May 2007, Alyeska submitted AFE $320 requesting
`an additional $39.3 million to finish pump station 3.“ In December 2007, Alyeska
`submitted a funding request for an additional $66.5 million to complete AFE $420 for
`pumpstation 4.*5 At the close ofthe record in this proceeding, SR Project facilities at
`pumpstations 3, 4, and 9 had entered into service, but the upgrades at pump station 1
`were not expected to enter into service until 2014.The total estimated project cost had
`reached $786 million.””
`
`.
`
`case that was included in Alyeska’s AFE 8020 economic analysis (Ex. ATC-238 at 15,
`21-22), but the work at these other pump stations did not involve the installation of new
`pumps andelectric motors.
`;
`18 Rx. ATC-279; Ex. SOA-358; Ex. ATC-24 at 28-29; Ex. ATC-27 at 39.
`
`? Fg, Ex. SOA-166 at 1; Ex. SOA-219 at 1.
`
`20 Carriers Brief on Exceptions at 34 (citing Ex. ATC-327; Ex. ATC-328).
`
`71 Rx. SOA-63 at 2.
`
`”? Carriers Briefon Exceptions at 153-54 (citing Ex. ATC-18 at 43).
`
`5 Ex ATC-378.
`
`4 Ex. SOA-121 at 2.
`
`5 Carriers Brief on Exceptions at 152 n.156 (citations omitted).
`
`6 bx, ATC-18 at 50.
`
`27 By. SOA-546 at 7.
`
`

`

`
`
`Docket No. I809-348-004,et al.
`
`.
`
`-7-
`
`B._Initial Decision
`
`The Initial Decision determined that the SR Project was imprudently sanctioned
`9.
`and imprudently implemented. The Initial decision noted that Larkspur Associates
`(Larkspur), 2 cost estimating company hired by the Carriers to evaluate preliminary
`engineering,had warned the Carriers that the pre-sanction cost estimates were
`inaccurate.” Along similar lines, the Initial Decision cited to internal emails prior to SR
`Project sanction in which Alyeska and Carrier employees expressed concerns aboutthe
`SR Project engineering and cost estimates.” The Initial Decision also concludedthat the
`flawed SR Project planning wastied to a rushed schedule that did not allow time for
`adequate engineering™ andthe selection of an inexperienced project manager.*’ The
`Initial Decision further explained that the SR Project cost estimates were based upon
`misconceptions, finding that the Carriers (a) incorrectly assumed the SR Project wasa_s-
`greenfield project as opposed to a higher cost brownfield project,*” (b) incorrectly
`"
`believed that the SR Project would allow the Carriers to avoid certain expenditures to
`comply with Alaska building codes,*? (c) incorrectly assumed that the variable speed stiff
`shaft motors were previously used, tested technology,>‘ and (d) imprudently failed to
`finalize power sources for pumpstations | and 9 at sanction.”
`The Initial Decision also
`stated that its imprudence finding was corroborated by post-sanction documents
`concluding that the Carriers had not planned the SR Project sufficiently prior to sanction
`and at the time of subsequent funding authorizations.
`10.
`TheInitial Decision rejected the justifications offered by the Carriers for the SR
`Project. The Initial Decision criticized the Carriers for relying upon their engineering
`
`78 F.g., Initial Decision, 146 FERC 63,091 at PP 608 — 613, 667, 750, 771, 840 —
`$41, 873, 913, 1228.
`”? Id. PP 540-554, 632-638, 652.
`* Id. PP 393, 497, 503, 690-698. 1454.
`31 fd PP 107, 502, 659, 1016, 1110, 1442.
`
`3 Id. PP 653, 656, 658, 744, 902-903.
`
`53 Id. PP 648.
`
`* Id. PP 1086.
`
`-
`
`5 Id PP 727, 898, 1456.
`
`

`

`
`
`Docket No. 1S09-348-004,ef al.
`
`~
`
`me ge
`
`contractor SNC-Lavalin, which lacked Alaskaexperience.* The Initial Decision
`dismissed the Carriers reviews of the pre-sanction cost estimates as superficial."” The
`Initial Decision dismissed the Carriers’ reliance upon various third party reviews which
`the Carriers argue supported the project sanction, including (2) a report by Independent
`
`ecAnalysts (IPA), aconsulting firm hiredbythe Carrierstoreview the SRProject,
`TO)
`(d) a letterfrom the AlaskaAttorney General,”
`and (e) conceptual engineering
`a report by Argonne National Laboratories, (c) a report from Joint Pipeline Office
`reports from GE and JTG Technologies.*! Furthermore, the Initial Decision rejected the
`Carriers’ argument that they reasonably projected SR Project savings resulting from
`reductions in personnel ‘or maintenance costs.“? The Initial Decision also criticized the
`- Carriers’ expenditureoffunds subsequentto sanction inAFE $020 Supplement 2 and
`thereafter.
`11.
`On exceptions, the Carriers challenge these holdings as discussed below. Trial
`Staff, Alaska, and Anadarko urge the Commissionto affirm the Initial Decision.
`Cc.
`Discussion
`
`%
`
`The Commission affirms the Initial Decision’s holding that the SR Project was
`12,
`imprudent. To determine the prudence of an investment, the Commission evaluates
`whether a “reasonable utility manager” would have made the same investment under the
`same circumstances.** A prudence inquiry addresses whether the pipeline conducted
`reasonable evaluation of the costs and benefits prior to incurring a financial
`
`36 Td. PP 660-663, 1045-1049, 1061,1082.
`
`37 Id. PP 663, 862-869, 1045-1048, 1061.
`
`38 Id PP 763-764, 876, 913.
`
`39 Id PP 762-764.
`
`“0 id. PP 645 1.375.
`
`*! id. PP 364 — 375, 444, 447, 458.
`
`“2 Id. PP 1388 — 1405.
`
`“3 New EnglandPower Co., 31 FERC { 61,047, at 61,084 (1985), order on
`reh’g, 32 FERC { 61,112, affdsub nom., Violet v.FERC, 800 F.2d 280 (ist Cir. 1986).
`
`

`

`
`
`Docket No. I809-348-004,et al.
`
`-9-
`
`commitment.“ A prudence determination is based upon what the pipeline knew or
`should have known at the time a decision was made.”
`The prudence standard ensures
`that ratepayers are not required to pay for “unnecessary costs.nfs
`13.
`The regulated entity has the burden ofproofto establishprudence. However, in
`order to ensure that rate cases are manageable, a presumption ofprudence applies until
`the challenging party “creates a serious doubt as to the prudence ofan expenditure...
`Serious doubt must-be more than a “bare allegation ofimprudence,” but this threshold
`may not be so demanding that it effectively reverses the statutory burden ofproof.
`Once such serious doubt has been raised, the pipeline has “the burdenof dispelling these
`doubts and proving the questioned expenditure to have been prudent.””
`
`14.
`The Commission holds that Anadarko, Alaska, and Trial Staffhave raised serious
`doubt about the Carriers’ prudence in approving the SR Project. As discussed above,
`prudent management requires considering the costs and benefits prior to initiating a
`project.” Implicit in this obligation is the responsibility to develop cost estimates based
`upon sufficiently complete engineering, planning, and scope to make the cost-benefit
`analysis meaningful. Significant evidence suggests that the Carriers sanctioned the SR.
`Project based upon a cost estimate they should have known was inaccurate. As a result,
`there is serious doubt whether the Carriers performed a reasonable cost-benefit analysis
`prior to sanctioning the SR Project. In the face ofthis serious doubt, the Carriers have
`failed to justify the prudence of the SR Project costs. Accordingly, for the reasons stated
`below, the Commission affirms the holding that the SR Project was imprudent and that
`the Carriers should be denied full recovery ofthe SR Project costs.
`
`_
`
`“ Entergy Servs., Inc., 130 FERC { 61,023, at P 52 (2010); Iroquois Gas
`Transmission Sys., L.P., 87 FERC J 61,295, at 62,170 (1999) (prudence inquiry involves
`comparing ex ante savings to ex ante costs).
`45 New England, 31 FERC at 61,084.
`
`“6 Td. at 61,083.
`
`“ Iroquois, 87 FERCat 62,168.
`48 1d Anaheim, Riverside, Banning, Colton,
`809 (D.C.Cir. 1981).
`
`© Anaheim, 669 F.2d at 809.
`
`«& Azusa, Cal. vy. FERC, 669 F.2d 799,
`
`- © Entergy, 130 FERC 4 61,023 at P 52; Iroquois, 87 FERC at 62,170.
`
`

`

`
`
`Docket No. IS09-348-004,etal.
`
`-10-
`
`. Serious Doubt Exists Regarding,the SR Project
`1.
`The record supports the allegations of serious doubt regarding the prudence of the
`15.
`SR Project. As discussed below, the Carriers should have known that the SR Project cost
`estimates were inaccurate because (a) prior to SR Project’s authorization or sanction,
`Larkspur, a cost estimating company, warned that the SR Project cost estimates awaiting
`approval and sanction were unrealistic; (b) prior to SR Project sanction, internal Carriers
`emails warned ofthe poor quality of the preliminary engineering used to develop SR
`Project cost estimates; (c) an overly aggressive schedule and underqualified SR Project
`. Manager created risks that the preliminary engineering cost estimates would be flawed;
`(d) conspicuous misconceptions and unrealistic assumptions afflicted the SR Project
`design forming the basis of the cost estimate; (e) Carriers’ internal assessments concluded
`that they sanctioned the SR Project based uponinsufficient up-front planning and
`undefined scope; and (f) the Carriers concluded that subsequent SR Project funding
`authorizations were also based upon incomplete engineering and poor planning. The
`Commission finds this evidence far exceeds the threshold for establishing serious doubt
`regarding the SR Project’s prudence.
`
`a.
`
`Pre-Sanction Warnings from Larkspur
`
`Serious doubt regarding the SR Project’s prudence was raised by the December
`16.
`2003 andJ;anuary 2004 Larkspur reports, which warned the Carriers ofpotential
`indccuracies in the cost estimates used to sanction the SR Project. Hired by Carziers to
`- evaluate the SR Project cost estimates prior to SR Project sanction, Larkspur”! provideda
`December 2003 report informing the Carriers that the SR Project’s preliminary
`engineering cost estimates did not fall within 15 percent accuracy. The report expressed
`“major concemsthat the project as currently designed could be built for the current
`estimate value.”** Larkspur further warnedthat the project’s scope was “not clearly
`defined in detail” and that there was a “high degree of certainty that additional scope”
`would be required.
`
`Although the Carriers claim they responded to the December 2003 report, the
`17.
`Carriers failed to assuage Larkspur’s concerns. In its second report issued in January
`2004, Larkspur rereiterated doubts that the current project design could be built for the
`. projected costs. Additionally, Larkspur stated that “[a]lthough the current scope ofthe
`>! Larkspur is a cost estimating company with experience on Alaska’s
`North Slope.
`
`52 Ex, SOA-222at 3, 13.
`
`3 By, SOA-223 at 14.
`
`

`

`
`
`Docket No. 809-348-004,et al.
`
`-ll-
`
`project is changing rapidly since the original estimate was published, manyif not all of
`the potential cost issues stated in this report still apply to the project.°>* Larkspur
`requested a meeting with the SR Project Team, stating that it was “very important”to
`discuss these findings. Despite this request, there is no evidence that such a meeting
`transpired, and there-is no evidence of subsequent interaction-with Larkspur related to the .
`December 2003 and January 2004 reports. Larkspur’s warnings and the Carriers’
`failure to address those warnings support serious doubt regarding the SR Project’s
`' prudence because they indicate that the Carriers should have known that the preliminary
`erigineering cost estimates were inaccurate.
`
`b.
`
`Pre-Sanction Warnings from Carriers’ Staff
`
`Serious doubt regarding the SR Project’s prudenceis also supported by concerns
`18..
`raised by Alyeska’s employees prior to sanction. As SNC-Lavalin finalized its
`preliminary engineering report in 2003, Alyeska senior rotating equipment engineer
`Jerry DeHaas c

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket