`January 4, 2021
`
`
`Via Electronic Submittal (E-File)
`
`
`Mr. Frank L. Blackett, P.E., Regional Engineer
`Federal Energy Regulatory Commission
`Division of Dam Safety and Inspections
`San Francisco Regional Office
`100 First Street, Suite 2300
`San Francisco, CA 94105-3084
`
`RE: Crane Valley Hydroelectric Project, FERC No. 1354-CA
`Outstanding P12D Inspection Recommendations – Status Update and
`Request for Extension of Time
`
`
`
`ENCLOSURE CONTAINS CUI//CEII – DO NOT RELEASE
`
`
`Dear Mr. Blackett:
`
`This letter presents updates on Pacific Gas and Electric Company’s (PG&E) efforts to address
`outstanding independent consultant (IC) recommendations from the eleventh Part 12D safety
`inspection reports for Crane Valley and Manzanita Dams, which are part of the Crane Valley
`Hydroelectric Project, Federal Energy Regulatory Commission (FERC) No. 1354. This letter
`also provides supporting information for IC recommendations that have been addressed and
`requests extensions of time to address recommendations that are not yet resolved.
`
` A
`
` summary table listing the subject IC recommendations, along with the status of PG&E’s
`efforts and updated schedules to address the recommendations, where applicable, is enclosed
`with this letter (Enclosure 1).
`
`Should you have any questions or need further information concerning technical aspects o f
`this matter, please contact PG&E’s dam safety engineer, Mr. Juan Sanchez, at (559) 396-
`9108. For general questions, please contact PG&E’s license coordinator, Mr. Paul Carson, at
`(628) 249-5036.
`
`Sincerely,
`
`
`David L. Ritzman, P.E., G.E.
`Chief Dam Safety Engineer
`
`Enclosure: CONTAINS CUI//CEII – DO NOT RELEASE
`1. 2020.08.25 P1354 P12D Table
`
`
`
`