`January 7, 2021
`
`
`Jan Nimick
`Vice President
`Generation
`
`
`
`Generation
`12840 Bill Clark Way
`Auburn, CA 95602
`
`805-208-6224
`E-Mail: Jan.Nimick@pge.com
`
`Via Electronic Submittal (E-File)
`
`
`Mr. Frank L. Blackett, P.E., Regional Engineer
`Federal Energy Regulatory Commission
`Division of Dam Safety and Inspections
`San Francisco Regional Office
`100 First Street, Suite 2300
`San Francisco, CA 94105-3084
`
`RE: Overdue Items: Status Update
`Potter Valley Hydroelectric Project, FERC Project No. 77
`Mokelumne River Hydroelectric Project, FERC Project No. 137
`Balch Hydroelectric Project, FERC Project No. 175
`Pit 3, 4, and 5 Hydroelectric Project, FERC Project No. 233
`Bucks Creek-Grizzly Hydroelectric Project, FERC Project No. 619
`DeSabla-Centerville Hydroelectric Project, FERC Project No. 803
`Phoenix Hydroelectric Project, FERC Project No. 1061
`Battle Creek Hydroelectric Project, FERC Project No. 1121
`Crane Valley Hydroelectric Project, FERC Project No. 1354
`Rock Creek-Cresta Hydroelectric Project, FERC Project No. 1962
`Haas-Kings River Hydroelectric Project, FERC Project No. 1988
`Upper North Fork Feather River Hydroelectric Project, FERC Project No. 2105
`McCloud-Pit Hydroelectric Project, FERC Project No. 2106
`Poe Hydroelectric Project, FERC Project No. 2107
`Spring Gap-Stanislaus Hydroelectric Project, FERC Project No. 2130
`Chili Bar Hydroelectric Project, FERC Project No. 2155
`Drum-Spaulding Hydroelectric Project, FERC Project No. 2310
`Pit 1 Hydroelectric Project, FERC Project No. 2687
`Helms Pumped Storage Hydroelectric Project, FERC Project No. 2735
`
`
`Dear Mr. Blackett:
`
`This letter presents an update on the status of Pacific Gas and Electric Company’s (PG&E)
`overdue items identified in the Federal Energy Regulatory Commission’s (FERC) letters to
`PG&E dated July 20, September 16, and November 24, 2020 for the above-listed projects.
`The status of each overdue item is provided in enclosure 1.
`
`These letters have underscored the importance of timely response in FERC
`correspondence and PG&E is taking several steps to address all of the overdue and
`coming due items including:
`
`
`
`
`Mr. Frank L. Blackett, P.E.
`January 7, 2021
`Page 2
`
`
`
`•
`
`•
`
`• Developed a multi-phase action plan to establish and maintain compliance with
`regulatory filings.
`• Performed two cause evaluations to investigate the reason for these overdue items
`to exist.
`Implementing corrective actions including increasing resources for our License
`Compliance and Dam Safety teams.
`Issued procedures to provide guidance and expectations on responding to
`regulatory correspondence.
`• Established governance that ensures that any compliance deviation (including
`overdue items) is captured in our Corrective Action Program.
`• Developing tools, metrics, and goals to give transparency to leaders and workers
`for tracking compliance work to completion.
`• Performed independent internal (PG&E), and external (Dam Safety Advisory
`Board), reviews of the 68 overdue items to evaluate risk significance and verify
`PG&E's plan to prevent recurrence.
`
`
`The PG&E plan and schedule for the overdue items included in the subject letters is
`included in Enclosure 1 that presents a summary table listing the FERC referenced 68
`overdue items, along with the status of PG&E’s efforts and updated schedules to address
`these items. By way of this letter, PG&E respectfully requests an Extension of Time (EOT)
`for those items identified in the column designated, “Extension of Time Being Requested
`w/ this Letter" of Enclosure 1.
`
`Should you have any technical questions concerning this matter, please contact PG&E’s
`Chief Dam Safety Engineer, Mr. David Ritzman, P.E. at (415) 264-1795. For general
`questions, please contact the Director of Risk and Compliance, Russell Prentice, at (805)
`305-5665.
`
`Sincerely,
`
`
`
`Jan Nimick
`Vice President, Power Generation
`
`Enclosure:
`1. Status Update Table on Overdue Items
`
`
`
`
`
`
`
`
`
`ENCLOSURE1
`ENCLOSURE 1
`
`
`
`FERC Item
`No.
`
`FERC Project
`No.
`
`OVERDUE ITEMS DESCRIPTION
`
` MOST RECENT
`CORRESPONDENCE
`
`ORIGINAL
`DUE DATE
`
`FINAL
`DOCUMENTS
`PG&E STATUS - 1/7/2021
`FILED (DATE)
`
`EXTENSION OF
`TIME REQUEST
`FILED (DATE)
`
`EXTENSION OF
`TIME BEING
`REQUESTED
`W/THIS LETTER
`
`ENCLOSURE 1 - STATUS OF FERC ITEM RESPONSES
`
`2019 EAP Status Reports: Response to
`FERC's 7/16/20 Comments
`
`7/16/2020
`
`8/30/2020
`
`Completed: Filed documents to
`close.
`
`12/22/2020
`
`1
`
`77, 137, 175,
`233, 619, 803,
`1061, 1121,
`1403, 1962,
`1988, 2105,
`2106, 2130,
`2155, 2310,
`2687, 2735
`
`2
`
`3
`
`10-Year Spillway Radial Gate Inspection Reports (GIRs)
`77, 137, 1962
`Scott Dam, Tiger Creek Dam, Rock Creek
`and 2310
`Dam and Lake Fordyce Dam
`1962, 2105,
`Cresta Dam, Belden Dam and Pit 1 Dam
`and 2687
`
`9/22/2020^
`
`10/2/2020
`
`9/22/2020^
`
`10/30/2020
`
`77 2019 FERC Annual Dam Safety Inspection:
`Plan & Schedule
`Scott Dam: 2014 Part 12D
`Recommendations (R-8, R-13, R-39, R-66, R-
`70): Updated Plan & Schedule
`
`1/16/2020
`
`3/3/2020
`
`11/27/2019 &
`3/6/2020^
`
`5/2/2020
`
`Potter Valley
`4
`
`5
`
`6
`
`7
`
`Balch
`
`77
`
`77
`
`77
`
`12/30/2020
`
`Completed: Filed documents to
`close.
`Completed: Cresta Dam and Belden
`Dam submittals completed
`(12/30/2020 and 12/29/2020).
`Ongoing: Pit 1 completed field
`inspection in December 2020 and
`currently finalizing report.
`
`12/18/2020
`
`Completed: Filed documents to
`close.
`Ongoing: Pending completion of 7th
`Board of Consultants Meeting in Q1
`of 2021, will file updated schedule
`with final reports of site-specific
`probable maximum precipitation and
`flood studies.
`
`4/30/2021
`
`4/30/2021
`
`1
`
`SSPMP/PMF BOC 3/4/20 conference call:
`Response to FERC comments on
`Preparation Package
`Scott Dam: 2019 Part P12D: Updated STID
`Section 3 (R-27)
`
`4/30/2020
`
`6/14/2020
`
`Completed: Filed documents to
`close.
`
`10/19/2020
`
`9/2/2020^
`
`9/30/2020
`
`Completed: Filed documents to
`close.
`
`12/14/2020
`
`
`
`
`
`FERC Item
`No.
`
`FERC Project
`No.
`
`OVERDUE ITEMS DESCRIPTION
`
` MOST RECENT
`CORRESPONDENCE
`
`ORIGINAL
`DUE DATE
`
`FINAL
`DOCUMENTS
`PG&E STATUS - 1/7/2021
`FILED (DATE)
`
`EXTENSION OF
`TIME REQUEST
`FILED (DATE)
`
`EXTENSION OF
`TIME BEING
`REQUESTED
`W/THIS LETTER
`
`ENCLOSURE 1 - STATUS OF FERC ITEM RESPONSES
`
`8
`
`9
`
`10
`
`11
`
`175
`
`175
`
`175
`
`175
`
`2019 Part 12D Recommendations Balch Div.
`(R-1, R-2, R-8, R-10, R-11); Balch AB (R-1, R-
`9, R-10): STID Revisions Updated Plan &
`Schedule
`2019 Part 12D Erodibility Assessment
`Reports Balch Div. & AB (R-6): Updated Plan
`& Schedule
`2019 Part 12D Balch Div. (R-7, R-13, R-14);
`Balch AB (R-7, R-11, R-12): Results of Data
`Collection Efforts
`Balch Div. (R-12): Results of
`Documentation Review
`PMF & Wind-Wave Studies
`12
`233, 1121,
`Evaluation of Potential effects of
`2106, 2688
`Overtopping effects and a plan & Schedule
`for Mitigation against any adverse effects
`
`2/5/2020 &
`2/10/2020^
`
`4/30/2020
`
`Completed: Filed documents to
`close.
`
`12/31/2020
`
`2/5/2020 &
`2/10/2020^
`
`2/5/2020 &
`2/10/2020^
`
`2/5/2020 &
`2/10/2020^
`
`5/31/2020
`
`Ongoing: Filed EOT request.
`
`9/30/2020
`
`Ongoing: Filed EOT request.
`
`9/30/2020
`
`Ongoing: Filed EOT request.
`
`12/24/2020
`
`12/24/2020
`
`12/24/2020
`
`5/29/2020
`
`7/13/2020
`
`Ongoing: Conducting engineering
`review and developing plan and
`schedule requirements consistent
`with 2019 PFMA and 5/29/2020 FERC
`letter.
`
`Ongoing: Conducting substantial
`revisions to plan and schedule based
`on 5/29/2020 FERC letter outlining
`recommended updates to 2019
`PFMA.
`
`13
`
`233, 1121,
`2106, 2688
`
`Seven items due within 90 days of FERC
`acceptance of studies
`
`12/20/2019^
`
`8/27/2020
`
`2019 Annual Spillway Gate Operation Certificates
`14
`233, 2106,
`2019 annual spillway gate operation certs:
`2687
`Response to Comments
`
`9/10/2020
`
`10/25/2020
`
`Completed: Filed documents to
`close.
`
`12/30/2020
`
`Pit No. 3, 4 and 5
`15
`233
`
`16
`
`233
`
`Pit 3 Dam: Fault 3432 PFMA Workshop
`Report
`Pit 3 & 5 Diversion Dam: Plan & schedule
`for damaged downstream areas
`
`5/31/2019^
`
`6/30/2020
`
`8/13/2020
`
`9/27/2020
`
`Ongoing: Final PFMA report
`undergoing internal review.
`Ongoing: Analysis required to
`complete prior to update of plan and
`schedule.
`
`6/30/2021
`
`6/30/2021
`
`4/30/2021
`
`4/30/2021
`
`2
`
`
`
`FERC Item
`No.
`
`FERC Project
`No.
`
`OVERDUE ITEMS DESCRIPTION
`
` MOST RECENT
`CORRESPONDENCE
`
`ORIGINAL
`DUE DATE
`
`FINAL
`DOCUMENTS
`PG&E STATUS - 1/7/2021
`FILED (DATE)
`
`EXTENSION OF
`TIME REQUEST
`FILED (DATE)
`
`ENCLOSURE 1 - STATUS OF FERC ITEM RESPONSES
`
`17
`
`233
`
`DeSabla Centerville
`18
`803
`19
`803
`20
`803
`
`21
`
`22
`
`23
`
`24
`
`803
`
`803
`
`803
`
`803
`
`25
`
`803
`
`Phoenix
`26
`
`1061
`
`Battle Creek
`
`Pit 5 Open Channel: Plan & Schedule for
`completing recommendations from the
`Focused Spillway Assessment
`(no response received to FERC’s 8/18/20
`letter).
`
`Round Valley Dam: Revised DPP*
`Philbrook Dam: Revised DPP*
`DeSabla Forebay Dam: Additional
`information for temporary erosion
`measures on downstream face*
`DeSabla Forebay Dam: Selected alternative
`for long-term erosion mitigation on
`downstream face*
`Hendricks Head Dam: Repair Plan to
`address seep
`
`Round Valley Dam: Plan & Schedule for
`Focused Spillway Assessment
`recommendations
`(no response received to FERC’s 7/14/20
`letter)
`Philbrook Dam: Memorandum/a regarding
`subterranean water flow and plan and
`schedule for completing recommendations
`from the Focused Spillway Assessment
`
`Resource agency documentation for the
`Phoenix Powerhouse Ground Grid Safety
`Improvements
`
`Round Valley Dam: Log Boom Construction
`Package
`
`5/26/2020^
`
`7/31/2020
`
`7/14/2020
`
`8/28/2020
`
`8/18/2020
`
`10/2/2020
`
`Ongoing: Analysis required to
`complete prior to update of plan and
`schedule.
`
`4/2/2109
`5/2/2019
`10/23/2019
`
`5/17/2019
`6/17/2019
`12/7/2019
`
`Ongoing: Filed EOT request.
`Ongoing: Filed EOT request.
`Completed: Filed documents to
`close.
`
`12/29/2020
`12/29/2020
`
`11/30/2020
`
`6/26/2019^
`
`4/15/2020
`
`Ongoing: Filed EOT request.
`
`11/30/2020
`
`5/29/2020^
`
`6/30/2020
`
`Ongoing: Revised construction
`package under development for final
`internal review prior to approval.
`
`Ongoing: Revised construction
`package under development for final
`internal review prior to approval.
`Ongoing: Plan and schedule
`undergoing internal review.
`
`7/14/2020
`
`8/28/2020
`
`Ongoing: Plan and schedule
`undergoing internal review.
`
`8/5/2020
`
`9/19/2020
`
`Completed: Filed documents to
`close.
`
`12/31/2020
`
`EXTENSION OF
`TIME BEING
`REQUESTED
`W/THIS LETTER
`
`4/30/2021
`
`4/30/2021
`
`4/30/2021
`
`4/30/2021
`
`4/30/2021
`
`3
`
`
`
`FERC Item
`No.
`
`FERC Project
`No.
`
`OVERDUE ITEMS DESCRIPTION
`
` MOST RECENT
`CORRESPONDENCE
`
`ORIGINAL
`DUE DATE
`
`FINAL
`DOCUMENTS
`PG&E STATUS - 1/7/2021
`FILED (DATE)
`
`EXTENSION OF
`TIME REQUEST
`FILED (DATE)
`
`EXTENSION OF
`TIME BEING
`REQUESTED
`W/THIS LETTER
`
`ENCLOSURE 1 - STATUS OF FERC ITEM RESPONSES
`
`27
`
`28
`
`29
`
`30
`
`1121
`
`1121
`
`1121
`
`1121
`
`Coleman Intake Siphon No. 1: Final
`Construction Report for Automated Trash
`Rake Project
`Coleman Forebay: Results of 2019
`Subsurface Investigation results and plan
`and schedule for completing seepage and
`stability analyses
`Salmon and Steelhead Restoration Project
`Phase 1B: Final Construction Report*
`
`12/31/19
`
`1/8/2021
`
`Ongoing: Filed EOT request.
`
`1/6/2021
`
`3/28/2019 &
`12/30/2019^
`
`1/31/2020
`
`Ongoing: Plan and schedule
`undergoing internal review.
`
`1/14/2020^
`
`2/10/2020
`
`Completed: Filed documents to
`close.
`
`1/5/2021
`
`Macumber Dam: 2020 Spillway Toe
`Evaluation Report
`
`7/28/2017
`
`10/31/2020
`
`Ongoing: Evaluation report
`undergoing internal review.
`
`Crane Valley
`31
`
`1354
`
`Crane Valley Dam: Status update and plan
`and schedule for completing the outlet
`tower retrofit design
`
`5/28/2019^
`
`4/30/2020
`
`Ongoing: Filed EOT request.
`
`1/4/2021
`
`Rock Creek Cresta
`32
`1962
`
`Rock Creek Cresta Dam: 2019 FERC annual
`dam safety inspection: Plan and schedule
`for addressing the follow-up items
`
`3/12/2020
`
`4/27/2020
`
`Ongoing: Plan and schedule
`undergoing internal review.
`
`Haas-Kings
`33
`
`34
`
`35
`
`1988
`
`1988
`
`1988
`
`Wishon Dam Part 12D (R-10): Updated plan
`and schedule to provide STID Section 4
`revision
`Courtright Dam P12D (R-7): Feasibility study
`for modifying the parapet wall manways
`
`Courtright Dam Part 12D (R-8): Results of
`data collection efforts as a first step to
`evaluating the potential for overtopping
`
`2/7/2020^
`
`4/30/2020
`
`Completed: Filed documents to
`close.
`
`12/29/2020
`
`2/10/2020^
`
`9/30/2020
`
`Ongoing: Filed EOT request.
`
`2/10/2020^
`
`9/30/2020
`
`Ongoing: Filed EOT request.
`
`12/29/2020
`
`12/29/2020
`
`2/26/2021
`
`2/26/2021
`
`4/30/2021
`
`4
`
`
`
`FERC Item
`No.
`
`FERC Project
`No.
`
`OVERDUE ITEMS DESCRIPTION
`
` MOST RECENT
`CORRESPONDENCE
`
`ORIGINAL
`DUE DATE
`
`FINAL
`DOCUMENTS
`PG&E STATUS - 1/7/2021
`FILED (DATE)
`
`EXTENSION OF
`TIME REQUEST
`FILED (DATE)
`
`EXTENSION OF
`TIME BEING
`REQUESTED
`W/THIS LETTER
`
`ENCLOSURE 1 - STATUS OF FERC ITEM RESPONSES
`
`36
`
`37
`
`38
`
`39
`
`1988
`
`1988
`
`1988
`
`1988
`
`McCloud Pit
`40
`
`2106
`
`Wishon Dam Part 12D (R-7): Investigation
`and evaluation report for the LLO butterfly
`valve seat ring bolt failure
`
`Wishon Dam Part 12D (R-8): Feasibility
`Study for modifying Parapet Wall Manways
`
`Wishon Dam Part 12D (R-11): Results of
`data collection efforts as a first step to
`evaluating the potential for overtopping
`
`Courtright & Wishon Dams: Plan and
`schedule to address Focused Spillway
`Assessment Report recommendations
`
`Iron Canyon Dam: Final Construction
`Report for Iron Canyon Right Abutment
`Storm Damage Repair
`
`41
`
`42
`
`43
`
`44
`
`45
`
`2106
`
`2106
`
`2106
`
`2106
`
`2106
`
`Iron Canyon Dam: Geotechnical Data
`Report for Iron Canyon Post-Construction
`Instrumentation Installation*
`Pit 7 Dam: Updated structural analysis and
`plan and schedule for completing an
`alternatives analysis for retrofit of the
`spillway radial gates
`Pit 6 Dam: Updated structural analysis and
`plan and schedule for completing an
`alternatives analysis for retrofit of the
`spillway radial gates
`McCloud Spillway: Alternatives analysis
`report and status update to support
`remediation
`Pit 6 Dam: Final Construction Report for
`Spillway Apron Repair Project
`
`2/7/2020^
`
`9/30/2020
`
`Ongoing: Filed EOT request.
`
`12/29/2020
`
`2/7/2020^
`
`9/30/2020
`
`Ongoing: Filed EOT request.
`
`2/7/2020^
`
`9/30/2020
`
`Ongoing: Filed EOT request.
`
`12/29/2020
`
`12/29/2020
`
`9/16/2020
`
`10/31/2020
`
`Ongoing: Contracting additional
`analysis support for plan and
`schedule development.
`
`11/30/2019
`
`11/15/2020
`
`Completed: Filed documents to
`close.
`
`12/30/2020
`
`6/24/2019
`
`11/1/2019
`
`Ongoing: Report undergoing
`internal review.
`
`12/31/2019^
`
`6/30/2020
`
`Completed: Filed requested
`documents.
`
`12/30/2020
`
`12/31/2019^
`
`10/31/2020
`
`Completed: Filed requested
`documents.
`
`12/30/2020
`
`4/30/2021
`
`2/26/2021
`
`9/11/2020
`
`10/31/2020
`
`Ongoing: Alternatives analysis
`report undergoing internal review.
`
`2/26/2021
`
`9/3/2020^
`
`1/1/2018
`
`Completed: Filed documents to
`close.
`
`12/28/2020
`
`5
`
`
`
`FERC Item
`No.
`
`FERC Project
`No.
`
`OVERDUE ITEMS DESCRIPTION
`
` MOST RECENT
`CORRESPONDENCE
`
`ORIGINAL
`DUE DATE
`
`FINAL
`DOCUMENTS
`PG&E STATUS - 1/7/2021
`FILED (DATE)
`
`EXTENSION OF
`TIME REQUEST
`FILED (DATE)
`
`ENCLOSURE 1 - STATUS OF FERC ITEM RESPONSES
`
`Poe
`
`46
`
`2107
`
`Spring Gap Stanislaus
`47
`2130
`
`48
`
`2130
`
`Drum Spaulding
`49
`2310
`
`50
`
`2310
`
`51
`
`2310
`
`2019 FERC annual dam safety inspection:
`Plan and schedule for addressing the follow-
`up items
`
`Strawberry Dam: Part 12D (R-6): Updated
`stability analyses of the spillway
`
`Relief & Strawberry Dams: Plan and
`schedule to address Focused Spillway
`Assessment Report recommendations. (no
`response received to FERC’s 9/16/20 letter)
`
`Rock Creek & Wise FB: 49 .Plan and
`schedule for addressing follow-up items No.
`16 and 17 , respectively) from the 2018
`FERC annual dam safety inspection: (no
`response received on these items from
`FERC’s 11/6/18 follow-up letter).
`
`L. Spaulding Dam 1: Evaluation of the
`feasibility of installing a weir to measure
`seepage through the left abutment (Tenth
`Part 12D recommendation R- 8): Due by
`1/31/20, according to PG&E’s 2/22/19
`letter.
`Halsey AB: Focused Spillway Assessment:
`Plan and schedule to address
`recommendations from and FERC
`comments: Due by 2/22/20 (no response
`received to FERC’s 1/8/20 letter).
`
`4/6/2020
`
`5/21/2020
`
`Ongoing: Plan and schedule
`undergoing internal review.
`
`12/31/2018^
`
`4/30/2020
`
`Ongoing: Filed EOT request.
`
`12/29/2020
`
`9/16/2020
`
`10/31/2020
`
`Ongoing: Contracting additional
`analysis support for plan and
`schedule development.
`
`11/6/2018
`
`12/21/2018
`
`2/22/2019^
`
`1/31/2020
`
`Rock Creek Ongoing: PG&E will
`investigate the oak tree and provide
`a specific evaluation of the subject
`oak tree, along with a plan and
`schedule if necessary, for FERC
`review by 4/30.
`Wise FB Complete: Vegetation
`removed.
`Completed: Filed documents to
`close.
`
`12/18/2020
`
`1/8/2020
`
`2/22/2020
`
`Ongoing: Developing
`documentation to address
`recommendations and plan and
`schedule if necessary to meet them.
`
`EXTENSION OF
`TIME BEING
`REQUESTED
`W/THIS LETTER
`
`4/30/2021
`
`4/30/2021
`
`4/30/2021
`
`4/30/2021
`
`6
`
`
`
`FERC Item
`No.
`
`FERC Project
`No.
`
`OVERDUE ITEMS DESCRIPTION
`
` MOST RECENT
`CORRESPONDENCE
`
`ORIGINAL
`DUE DATE
`
`FINAL
`DOCUMENTS
`PG&E STATUS - 1/7/2021
`FILED (DATE)
`
`EXTENSION OF
`TIME REQUEST
`FILED (DATE)
`
`ENCLOSURE 1 - STATUS OF FERC ITEM RESPONSES
`
`52
`
`2310
`
`53
`
`2310
`
`54
`
`55
`
`2310
`
`2310
`
`56
`
`2310
`
`57
`
`2310
`
`Halsey FB 1: Focused Spillway Assessment:
`Plan and schedule to address
`recommendations from and FERC
`comments: Due by 2/22/20 (no response
`received to FERC’s 1/8/20 letter).
`
`Fordyce, Spaulding 2 & Drum AB: 2019.
`Response to FERC comments on the 2019
`annual spillway gate operation certificates:
`Due by 3/14/20 (no response received to
`FERC’s 1/29/20 letter).
`
`Upper Peak Lake: Seismic stability and
`deformation analysis (Eleventh Part 12D
`recommendation R-3): Due by 3/31/20,
`
`
`
`
`
`Fordyce: Response to FERC comments on
`the structural analysis of the rear valve
`house wall: Due by 5/1/20 (no response
`received to FERC’s 3/17/20 letter).
`
`Fuller Lake Dam: Assess the appropriate
`monitoring frequency for obtaining
`accurate readings of Weir YB-12A: Due by
`5/9/20 (no response received to FERC’s
`3/25/20 letter).
`Upper Peak Lake Dam: Assess seepage flow
`monitoring options following rehabilitation
`of the spillway and masonry wall: Due by
`5/9/20 (no response received to FERC’s
`3/25/20 letter).
`
`1/8/2020
`
`2/22/2020
`
`Ongoing: Developing
`documentation to address
`recommendations and plan and
`schedule if necessary to meet them.
`
`1/29/2020
`
`3/14/2020
`
`Completed: Filed documents to
`close.
`
`12/29/2020
`
`2/19/2019^
`
`3/31/2020
`
`Ongoing: Filed EOT request.
`
`8/27/2020
`
`3/17/2020
`
`5/1/2020
`
`Ongoing: PG&E obtaining
`engineering contract support to
`complete plan and schedule required
`for response.
`
`3/25/2020
`
`5/9/2020
`
`Ongoing: Assessment undergoing
`internal review.
`
`3/25/2020
`
`5/9/2020
`
`Ongoing: Report undergoing
`internal review.
`
`EXTENSION OF
`TIME BEING
`REQUESTED
`W/THIS LETTER
`
`4/30/2021
`
`2/26/2021
`
`2/26/2021
`
`2/26/2021
`
`7
`
`
`
`FERC Item
`No.
`
`FERC Project
`No.
`
`OVERDUE ITEMS DESCRIPTION
`
` MOST RECENT
`CORRESPONDENCE
`
`ORIGINAL
`DUE DATE
`
`FINAL
`DOCUMENTS
`PG&E STATUS - 1/7/2021
`FILED (DATE)
`
`EXTENSION OF
`TIME REQUEST
`FILED (DATE)
`
`ENCLOSURE 1 - STATUS OF FERC ITEM RESPONSES
`
`58
`
`2310
`
`59
`
`2310
`
`60
`
`2310
`
`61
`
`2310
`
`62
`
`2310
`
`Meadow Lake Dam: Supplement to
`Liquefaction Sensitivity Seismic Stability
`Study: (Tenth Part 12D recommendation R-
`7): Due by 6/8/20 (no response received to
`FERC’s 4/24/20 letter).
`
`Spaulding Lake Dam #3: Report justifying
`PG&E’s determination that there is no need
`to upgrade the weirs downstream: (Ninth
`Part 12D recommendation R- 1.3.4.5): Due
`by 6/8/20 (no response received to FERC’s
`4/24/20 letter).
`
`Wise FB Dam: Hydraulic sensitivity analysis:
`(Fourth Part 12D recommendation R-1):
`Due by 6/8/20 (no response received to
`FERC’s 4/24/20 letter).
`
`Wise FB Dam: Plan and schedule for
`upgrading the instrumentation and
`monitoring systems, adding an automatic
`shutoff at the intake, and/or improving the
`downstream spill channel: (Fifth Part 12D
`recommendations R-4, R-6, and R- 7,
`respectively): Due by 7/31/20, according to
`PG&E’s 3/29/19 letter
`
`Halsey FB Dam 1: Review of the static
`stability analysis for the right abutment
`section: (Eighth Part 12D recommendation
`R-11): Due by 8/28/20, according to PG&E’s
`3/29/19 letter.
`
`4/24/2020
`
`6/8/2020
`
`Ongoing: Study undergoing internal
`review.
`
`4/24/2020
`
`6/8/2020
`
`Ongoing: Report undergoing
`internal review
`
`4/24/2020
`
`6/8/2020
`
`Ongoing: Analysis undergoing
`internal review.
`
`3/29/2019^
`
`7/31/2020
`
`Ongoing: Plan and schedule
`undergoing internal review.
`
`3/29/2019^
`
`8/28/2020
`
`Ongoing: Analysis undergoing
`internal review.
`
`EXTENSION OF
`TIME BEING
`REQUESTED
`W/THIS LETTER
`
`2/26/2021
`
`2/26/2021
`
`2/26/2021
`
`2/26/2021
`
`2/26/2021
`
`8
`
`
`
`FERC Item
`No.
`
`FERC Project
`No.
`
`OVERDUE ITEMS DESCRIPTION
`
` MOST RECENT
`CORRESPONDENCE
`
`ORIGINAL
`DUE DATE
`
`FINAL
`DOCUMENTS
`PG&E STATUS - 1/7/2021
`FILED (DATE)
`
`EXTENSION OF
`TIME REQUEST
`FILED (DATE)
`
`ENCLOSURE 1 - STATUS OF FERC ITEM RESPONSES
`
`63
`
`64
`
`2310
`
`2310
`
`65
`
`2310
`
`66
`
`2310
`
`Halsey FB Dam 2: Deformation Analysis of
`the Modified Embankment are valid: Due
`by 8/29/20 (no response received to FERC’s
`7/15/20 letter).
`Halsey FB Dam 2: Internal video inspection
`report for the subdrain system: (Eighth Part
`12D recommendation R-6): Due by 9/30/20,
`according to PG&E’s 3/29/19 letter.
`
`Halsey FB Dam1: Review of existing
`information regarding subsurface
`conditions and the liquefaction
`susceptibility of the foundation materials:
`(Eighth Part 12D recommendation R-1):
`Due by 11/1/20, according to PG&E’s
`2/28/20 letter.
`Wise FB: Review of existing information
`regarding subsurface conditions and the
`expected seismic performance of the
`foundation materials: (Fifth Part 12D
`recommendation R-10): Due by 11/1/20,
`according to PG&E’s 2/28/20 letter.
`
`7/15/2020
`
`8/29/2020
`
`Ongoing: Analysis undergoing
`internal review.
`
`3/29/2019^
`
`9/30/2020
`
`2/28/2020^
`
`11/1/2020
`
`Ongoing: COVID19 impact to
`inspections schedules associated
`with subdrain system. Updating
`timeline to reflect delay and resulting
`plan and schedule associated with
`findings.
`Ongoing: Analysis completed,
`developing report for independent
`consultant review and comment.
`
`2/28/2020^
`
`11/1/2020
`
`Ongoing: Analysis completed,
`developing report for independent
`consultant review and comment.
`
`67
`
`2687
`
`Pit 1 FB Dam: Plan and schedule for
`addressing comments from the Ninth Part
`12D report : Due by 6/12/20 (no response
`received to FERC’s 4/28/20 letter).
`
`4/28/2020
`
`6/12/2020
`
`Ongoing: Implementing actions to
`address comments.
`
`EXTENSION OF
`TIME BEING
`REQUESTED
`W/THIS LETTER
`
`2/26/2021
`
`6/30/2021
`
`6/30/2021
`
`6/30/2021
`
`2/26/2021
`
`9
`
`
`
`FERC Item
`No.
`
`FERC Project
`No.
`
`OVERDUE ITEMS DESCRIPTION
`
` MOST RECENT
`CORRESPONDENCE
`
`ORIGINAL
`DUE DATE
`
`FINAL
`DOCUMENTS
`PG&E STATUS - 1/7/2021
`FILED (DATE)
`
`EXTENSION OF
`TIME REQUEST
`FILED (DATE)
`
`EXTENSION OF
`TIME BEING
`REQUESTED
`W/THIS LETTER
`
`ENCLOSURE 1 - STATUS OF FERC ITEM RESPONSES
`
`68
`
`2687
`
`Pit 1 FB Dam: Supplemental spillway
`inspection report and plan and schedule for
`completing the recommendations from the
`Focused Spillway Assessment : Due by
`10/30/20 (no response received to FERC’s
`9/15/20 letter).
`
`9/15/2020
`
`10/30/2020
`
`Completed: Filed documents to
`close.
`
`1/7/2021
`
`10
`
`