`Power Generation
`
`
`300 Lakeside Drive
`Oakland, CA 94612
`Mailing Address:
`P.O. Box 28209
`Oakland, CA 94604
`
`
`
`May 21, 2025
`
`Via Electronic Submittal (E-File)
`
`Frank L. Blackett, P.E., Regional Engineer
`Federal Energy Regulatory Commission
`Division of Dam Safety and Inspections
`100 First Street, Suite 2300
`San Francisco, CA 94105-3084
`
`RE: Balch Hydroelectric Project, FERC No. 175-CA
`Balch 1 and 2 Units 1, 2, and 3
`Update to 2025 Outage Schedule – Penstock Dewatering
`
`Dear Frank L. Blackett:
`
`This letter presents an update to Pacific Gas and Electric Company's (PG&E) schedule of planned
`outages in 2026. Dewatering is required at the Balch 1 and 2 Powerhouse Penstock which is part
`of PG&E’s Balch Hydroelectric Project, Federal Energy Regulatory Commission (FERC) No. 175.
`PG&E submitted the 2025 outage schedule to FERC on October 29, 2024. The update includes
`moving two-unit October 2025 outages to January of 2026 and one unit June 2025 outage to
`February of 2026.
`
`Table 1. Current Outage Schedule
`FERC
`No. Region Location
`Description of
`Work Dewatered Start Date End Date
`175 South Balch 2
`Unit 2
`Annual, Runner
`Welding, Repl
`Cooling Water
`System, ISO
`Meters, Repl TGB
`Cooling Coil, PH
`Modernization
`Phase 1
`Penstock 10/2/2025 2/28/2026
`175 South Balch 2
`Unit 3
`Annual, Runner
`Welding, Upgrade
`Cooling Water
`System, ISO
`Meters, Repl TGB
`Cooling Coil, PH
`Modernization
`Phase 1
`Penstock 10/2/2025 2/28/2026
`175 South Balch 1Unit
`1
`Annual, Install
`Sync Check Relay,
`Iso Meters
`Penstock 6/25/2025 6/27/2025
`
`
`
`
`
`
`
`Frank L. Blackett, P.E., Regional Engineer
`May 21, 2025
`Page 2
`
`
`
`
`Table 2. Updated Outage Schedule
`FERC
`No. Region Location
`Description of
`Work Dewatered Start Date End Date
`175 South Balch 2
`Unit 2
`Annual, Runner
`Welding, Repl
`Cooling Water
`System, ISO
`Meters, Repl TGB
`Cooling Coil, PH
`Modernization
`Phase 1
`Penstock 1/5/2026 5/17/2026
`175 South Balch 2
`Unit 3
`Annual, Runner
`Welding, Upgrade
`Cooling Water
`System, ISO
`Meters, Repl TGB
`Cooling Coil, PH
`Modernization
`Phase 1
`Penstock 1/5/2026 5/17/2026
`175 South Balch 1Unit
`1
`Annual, Install
`Sync Check Relay,
`Iso Meters
`Penstock 2/1/2026 2/28/2026
`
`The outage schedule update reflects the need for pre outage work, project design, and material
`procurement. This routine maintenance outage will follow the previously executed procedures that
`have been coordinated with your office.
`
`Please note that this schedule is subject to change based on weather, staffing schedules, water
`conditions, and other factors that may be beyond PG&E's control. PG&E will inform FERC staff of
`all schedule changes that affect the planned outage.
`
`If you have questions or comments regarding this matter, please contact Tiffany Begaye, license
`coordinator at PG&E, at (559) 955-7135.
`
`Sincerely,
`
`
`
`Matthew Joseph
`Supervisor, Hydro License Compliance
`
`
`
`
`
`
`
`
`
`