`OFFICE OF ENERGY PROJECTS
`DIVISION OF DAM SAFETY AND INSPECTIONS
`NEW YORK REGIONAL OFFICE
`19 West 34th Street - Sulte 400
`New York, New York 10001
`
`Office No. (212) 273- 5900
`
`FAX No. (212) 631-8124
`
`In Reply Refer to:
`
`P-2368-ME
`NATDAM # - ME00234
`
`Post Inspection Letter
`
`June 18, 2004
`
`Mr. Mike McGann,P.E.
`Managerof Operations and Maintenance
`WPS New England Generation,Inc.
`142 Lower LyndonStreet
`Caribou, ME 04736
`
`Dear Mr. McGann:
`
`On August 14, 2002, an operation inspection ofthe Squa Pan Project was performed
`by Mr. Harold Kamara of my office. We would like to thank you and yourstaff for the
`courtesy you extended to Mr. Kamara during the inspection. The project structures at thesite
`appeared to be in good condition and no significant deficiencies were noted that require
`immediate remedial action. However, the following deficiencies were observed:
`
`1.
`
`2.
`
`3.
`
`Brush, grass and small trees were noted along the toe of the left
`embankmentand should be removed at both embankmentson a regular
`basis.
`
`Concrete spalling was noted in localized areas of the dam. You noted
`that plans to repair the spalled concrete are under way.
`
`The railing inside the gallery was severely rusted and should be
`replaced.
`
`
`
`Project No. 2368-ME
`
`2
`
`4.
`
`Animal burrows were noted on the right embankmentsection adjacent
`to the downstream retaining wall. The animal burrowsshould befilled
`on a regular basis.
`
`Please provide this office by July 16, 2004 a plan and schedule for addressing the
`noted deficiencies. In addition, we should advise you that we may send additional comments
`that arise as a result of the preparation of the inspection report. If you have any questions
`
`regardingthis letter, please feel free to contact Mr. Kamaraat (212) 273-5916.
`
`