throbber
UNITED STATES OF AMERICA
`BEFORE THE
`FEDERAL ENERGY REGULATORY COMMISSION
`
`
`Building for the Future Through Electric
`Regional Transmission Planning and Cost
`Allocation and Generator Interconnection.
`
`
`
`
`
`
`
`)
`)
`)
`
`
`
`Docket No. RM21-17-000
`
`COMMENTS FOR PROTECTING CONSUMERS FROM SOCIALIZED
`TRANSMISSION CHARGES THAT DO NOT BENEFIT THEM, FROM SUBSIDIZING
`NETWORK UPGRADES NEEDED FOR GENERATION INTERCONNECTIONS, AND
`FROM PAYING FOR POTENTIAL UNNEEDED AND COSTLY SUPPLEMENTAL
`TRANSMISSION PROJECTS
`BY
`OFFICE OF THE OHIO CONSUMERS’ COUNSEL
`
`
`
`
`
`
`
`
`
`
`
`Bruce Weston
`Ohio Consumers’ Counsel
`
`Larry Sauer
`Deputy Consumers’ Counsel
`
`Office of the Ohio Consumers’ Counsel
`65 East State Street, 7th Floor
`Columbus, Ohio 43215
`(614) 466-1312 – Telephone
`Larry.sauer@occ.ohio.gov
`
`
`
`
`
`October 12, 2021
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`

`

`
`
`
`
`I.
`
`TABLE OF CONTENTS
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`PAGE
`
`
`
`INTRODUCTION ...............................................................................................................1
`
`A.
`
`B.
`
`C.
`
`The cost causation/beneficiary pays approach to allocating the costs of new
`transmission investment best makes sure that transmission rates charged to
`consumers are just and reasonable. ..........................................................................4
`
`The Order No. 2003 approach to allocating network upgrade costs related to
`generation interconnections remains the most reasonable means of making sure
`new generation is properly sized and located. .......................................................10
`
`FERC should open a separate investigation into reforming PJM’s supplemental
`transmission project and local transmission planning processes to protect
`consumers from potential unnecessary and excessive charges. .............................12
`
`II.
`
`CONCLUSION ..................................................................................................................15
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`i
`
`
`
`

`

`
`
`UNITED STATES OF AMERICA
`BEFORE THE
`FEDERAL ENERGY REGULATORY COMMISSION
`
`
`Building for the Future Through Electric
`Regional Transmission Planning and Cost
`Allocation and Generator Interconnection.
`
`
`
`
`
`
`
`)
`)
`)
`
`
`
`Docket No. RM21-17-000
`
`COMMENTS FOR PROTECTING CONSUMERS FROM SOCIALIZED
`TRANSMISSION CHARGES THAT DO NOT BENEFIT THEM, FROM SUBSIDIZING
`NETWORK UPGRADES NEEDED FOR GENERATION INTERCONNECTIONS, AND
`FROM PAYING FOR POTENTIAL UNNEEDED AND COSTLY SUPPLEMENTAL
`TRANSMISSION PROJECTS
`BY
`OFFICE OF THE OHIO CONSUMERS’ COUNSEL
`
`
`
`I.
`
`INTRODUCTION
`
`Consumers should not be required to pay for transmission projects from which they
`
`receive no benefit such as not receiving power from those transmission lines or interconnected
`
`power plants. Likewise, consumers should not be required to subsidize power plant grid
`
`connection costs that do not benefit them. The Office of the Ohio Consumers’ Counsel (“OCC”),
`
`the statutory representative of residential retail consumers in Ohio, urges the Federal Energy
`
`Regulatory Commission (“FERC”) to keep two fundamental rate principles in mind as it
`
`embarks on its inquiry in this Advanced Notice of Proposed Rulemaking (“ANOPR”)
`
`proceeding. A central inquiry in this proceeding is who should pay for the new investment in the
`
`electric transmission grid that will be needed to deliver power from renewable wind and solar
`
`resources to consumers across the nation. First, the courts have long-required, and continue to
`
`require today, that the costs of transmission investment be allocated to those who caused the
`
`costs to be incurred and/or those who will benefit from those facilities. Second, subsidization of
`
`any investment, including the Network Upgrades needed to allow the interconnection of new
`
`
`
`1
`
`

`

`generation to the electric transmission grid, is not compatible with competitive markets. In
`
`addition, subsidizing power plant interconnections will not send accurate price signals regarding
`
`the most efficient and cost-effective location for generation resources in today’s regional
`
`markets. The reasoning behind these fundamental rate principles remains valid even in today’s
`
`changing environment marked by the rapid growth in renewable resource investments.
`
`Under Ohio Revised Code Chapter 4911, OCC represents the interests of approximately
`
`4.5 million Ohio residential utility customers in proceedings before state and federal
`
`administrative agencies and the courts. Ohio is a retail choice state that allows electric customers
`
`to choose their energy supplier. Both the retail marketers and the Ohio default service auctions
`
`that procure power for those Ohio consumers who do not switch to a retail marketer depend on
`
`the PJM markets for power supplies and for index pricing. Thus, Ohio consumers depend on the
`
`competitiveness of PJM’s markets to protect them against unjust and unreasonable rates for
`
`electricity supplies. To protect Ohio consumers from excessive rates and charges, the integrity
`
`of PJM’s markets must be maintained. This includes the objective that consumers should not be
`
`required to subsidize any portion of their electric services costs. Realizing FERC’s objective of
`
`competitive pricing in PJM’s markets is critical for states like Ohio that have embraced retail
`
`competition in the provision of generation services.
`
`FERC’s primary obligation is to provide consumers a “complete, permanent, and
`
`effective bond of protection from excessive rates and charges.”1 In recent years, the charges Ohio
`
`consumers pay for transmission service has increased by 50% or more due to significant
`
`increases in transmission investment in the state. Since 2017, less than 25% of that new
`
`investment has been associated with the large regional transmission projects needed for
`
`
`1 NextEra Energy, 167 FERC ¶ 61,096 at P 12, citing Atl. Ref. Co. v. Pub. Serv. Comm’n, 360 U.S. 378, 388 (1959).
`
`
`
`2
`
`

`

`reliability or economic efficiency. Instead, the vast majority is related to local projects planned
`
`by transmission utilities with little or no oversight by state or federal authorities. These facilities
`
`are known as Supplemental Transmission Projects. In just Ohio, over $8.5 billion has been
`
`approved for these projects in just four years (2017 through 2020).2 These costs are not shared
`
`with the entire PJM region; Ohio customers are required to pay these increased costs.
`
`FERC’s inquiry in the ANOPR raises the specter of additional significant increases in
`
`transmission rates being imposed on consumers to build out FERC’s vision of the transmission
`
`grid of the future. In order to fulfill FERC’s statutory obligation to protect consumers from
`
`excessive rates and charges, any proposed policies or rules stemming from this proceeding
`
`should reflect three fundamental objectives:
`
`1.
`
`2.
`
`3.
`
`Transmission planning, cost allocation and generation interconnection policies
`must be based on the actual transmission needs of consumers and rely on
`competitive solicitations for proposals in order to minimize costs for consumers,
`
`The cost of new investment should be allocated to those who cause the costs to be
`incurred or who benefit from the investment, as determined using a methodology
`that could be revisited annually to reflect the changing needs in the region, and
`
`Consumers should not be required to subsidize any Network Upgrades that would
`not be needed “but for” generator interconnections to the grid, nor should they be
`required to subsidize state-specific policy goals that provide no benefits to
`consumers in other states.
`
`
`OCC also requests that FERC initiate a separate proceeding to impose more regulatory oversight
`
`for Supplemental Transmission Projects and the local transmission planning process in PJM
`
`Interconnection, L.L.C. (“PJM”). This action is needed to make sure that no new transmission
`
`investment – whether local or regional facilities – can evade FERC’s regulatory oversight and
`
`
`2 Public Utilities Commission of Ohio (“PUCO”), Docket No. 21-0796-GE-UNC, Ohio Power Siting Board Draft
`Report, p. 5, September 24, 2021.
`
`
`
`3
`
`

`

`PJM’s competitive solicitation requirements, in particular for Supplemental Transmission
`
`Projects.
`
`A.
`
`The cost causation/beneficiary pays approach to allocating the costs of new
`transmission investment best makes sure that transmission rates charged to
`consumers are just and reasonable.
`
`OCC acknowledges FERC’s interest in reassessing the cost allocation methods used by
`
`various Regional Transmission Organizations (“RTOs”) and Independent Transmission
`
`Operators (“ISOs”) given the changing nature of the generation resources in the nation today. As
`
`FERC notes in the ANOPR, “the electricity sector is transforming as the generation fleet shifts
`
`from resources located close to population centers to resources, including renewables, that may
`
`often be located far from load centers.” ANOPR at P 3. However, FERC should recognize that
`
`the nation’s increasing reliance on or desire for intermittent renewable resources does not signal
`
`a need for changing the equitable and economically sound principle that the rates consumers pay
`
`for power should be based on the cost of providing that service or the benefits received from that
`
`service. The current cost causation/beneficiary pays approach to allocating transmission
`
`investment costs in PJM best satisfies the Congressional mandate in Section 205 of the Federal
`
`Power Act, 16 U.S.C. § 824d, that rates be just and reasonable for monopoly transmission
`
`services.
`
`It is axiomatic that the cost of new investment in the transmission grid must be paid by
`
`those causing the costs to be incurred and/or those benefiting from those investments. The
`
`courts have consistently ruled that “[A]ll approved rates [must] reflect to some degree the costs
`
`actually caused by the customer who must pay them.”3 The United States Court of Appeals for
`
`
`3 KN Energy, Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992); Transmission Access Policy Study Group v.
`FERC, 225 F.3d 667, 708 (D.C. Cir. 2000); Pacific Gas & Elec. Co. v. FERC, 373 F.3d 1315, 1320-21 (D.C. Cir.
`2004).
`
`
`
`4
`
`

`

`the Seventh Circuit (“Seventh Circuit”) applied this formative rate principle in a 2009 opinion
`
`reversing FERC’s order accepting PJM’s proposal to use a broad, cost-spreading approach,
`
`known as the postage stamp method, to allocate the costs associated with large regional
`
`transmission lines located in the eastern region of PJM to all consumers in the PJM region, even
`
`those on the far western edge of the region. In rejecting FERC’s approval of a cost allocation
`
`method that would have allocated a significant portion of the costs associated with large new
`
`transmission lines needed to serve consumers in eastern PJM to consumers in the western portion
`
`of PJM’s footprint, the Seventh Circuit found that:
`
`FERC is not authorized to approve a pricing scheme that requires a group
`of utilities to pay for facilities from which its members derive no benefits,
`or benefits that are trivial in relation to the costs sought to be shifted to its
`members. “Not surprisingly, we evaluate compliance with this
`unremarkable principle by comparing the costs assessed against a party to
`the burdens imposed or benefits drawn by that party.”4
`
`The Seventh Circuit reasoned that “[t]o the extent that a utility benefits from the costs of new
`
`facilities, it may be said to have ‘caused’ a part of those costs to be incurred, as without the
`
`expectation of its contributions the facilities might not have been built, or might have been
`
`delayed.”5 Based on the evidence in that case, the Seventh Circuit found that “the likely benefit”
`
`to consumers in the western region of PJM was “zero” given that FERC attributed “the need for
`
`new transmission capacity in PJM to the threat of "degraded reliability in Eastern PJM.”6
`
`While the Seventh Circuit required FERC to consider the relative costs and benefits to
`
`consumers in determining cost allocation outcomes, it did not require FERC “to calculate
`
`
`4 Illinois Commerce Comm’n v. FERC, 576 F.3d 470, 476 (7th Cir. 2009) (“Illinois Commerce Comm’n I”), citing
`Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004); Alcoa Inc. v. FERC, 564 F.3d
`1342, 1346-47 (D.C. Cir. 2009); and Sithe/Independence Power Partners, L.P. v. FERC, 285 F.3d 1, 4-5 (D.C. Cir.
`2002). The Court also cited to FPA Section 205.
`
`5 Illinois Commerce Comm’n I, 576 F.3d. at 476.
`
`6 Id. at 477.
`
`
`
`5
`
`

`

`benefits to the last penny, or for that matter to the last million or ten million or perhaps hundred
`
`million dollars.”7 It required only that FERC have “an articulable and plausible reason to believe
`
`that the benefits are at least roughly commensurate with those utilities' share of total electricity
`
`sales in PJM's region.”8 The Seventh Circuit acknowledged that FERC could presume that
`
`everyone benefits from high-capacity transmission facilities because those facilities can increase
`
`the reliability of the entire network,9 but determined that FERC could not use that presumption to
`
`evade its responsibility to compare the costs assessed against a party to the burdens imposed or
`
`benefits drawn by that party.10
`
`In contrast to its ruling in Illinois Commerce Comm’n I, the Seventh Circuit in a different
`
`case upheld FERC’s acceptance of a Midwest Independent System Operator, Inc. (“MISO”)
`
`proposal to allocate the costs of multi-value project consisting of high voltage transmission lines
`
`on a region-wide, postage stamp basis. Citing Illinois Commerce Comm’n I, the Seventh Circuit
`
`stated that “[t]he Federal Power Act requires that the fee be ‘just and reasonable,’ 16 U.S.C. §
`
`824d(a), and therefore at least roughly proportionate to the anticipated benefits to a utility of
`
`being able to use the grid.”11 The Seventh Circuit relied on evidence in that case demonstrating
`
`that “[m]ost [wind farms] are in the Great Plains, because electricity produced by wind farms
`
`there is cheaper despite the longer transmission distance; the wind flow is stronger and steadier
`
`and land is cheaper because population density is low (wind farms require significant amounts of
`
`
`7 Id., citing Midwest ISO Transmission Owners v. FERC, supra, 373 F.3d at 1369 ("we have never required a
`ratemaking agency to allocate costs with exacting precision"); Sithe/Independence Power Partners, L.P. v. FERC,
`supra, 285 F.3d at 5.
`
`8 Illinois Commerce Comm’n I, 576 F.3d at 477.
`
`9 Id.
`
`10 Id.
`
`11 Illinois Commerce Comm’n v. FERC, 721 F.3d 764 (7th Cir. 2013) (“MISO Illinois Commerce Comm’n”).
`
`
`
`6
`
`

`

`land).”12 The Seventh Circuit Court found that the proposed large multi-value project lines
`
`would provide reliability benefits to consumers throughout the region.
`
`One year after the Seventh Circuit’s ruling in MISO Illinois Commerce Comm’n, the
`
`Seventh Circuit had an opportunity to revisit its ruling in Illinois Commerce Comm’n I when
`
`several parties to the PJM proceeding on remand appealed FERC’s order continuing to approve
`
`of the postage stamp approach to allocating the costs of the eastern region high voltage
`
`transmission lines. The Seventh Circuit again rejected FERC’s PJM cost recovery ruling
`
`regarding the potential regional reliability benefits associated with the high voltage lines located
`
`on the eastern side of the PJM region, finding that FERC made no effort to quantify the
`
`reliability benefits presumed to be received by consumers on the western side of PJM region.13
`
`The Seventh Circuit Court distinguished its ruling in the appeal from the MISO proceeding,
`
`finding that:
`
`Contrast our wind-power decision, Illinois Commerce Commission v.
`FERC, 721 F.3d 764 (7th Cir. 2013), which upheld postage-stamp pricing
`of the transmission lines required to bring western wind-generated
`electrical power to the 562*562 MISO utilities. There was evidence that
`the lines would not yield highly disparate benefits to the utilities asked to
`contribute to their costs. See id. at 774-75. Indeed, the Commission had
`determined that the benefits from the new lines would be spread almost
`evenly across all the utilities. Midwest Independent Transmission System
`Operator, Inc., 133 FERC P 61221, ¶¶ 54-56 (Dec. 16, 2010). It made no
`such determination in the present practical matter; all it did was express a
`hope that things might turn out that way. 14
`
`These rulings require FERC to find that the costs of new transmission projects are at least
`
`roughly commensurate with the benefits to be received by the consumers charged with those
`
`costs. To the extent that new transmission investment is needed to bring renewable energy to a
`
`
`12 MISO Illinois Commerce Comm’n, 721 F.3d at 771.
`
`13 Illinois Commerce Comm’n v. FERC, 756 F.3d 556 (7th Cir. 2014) (“Illinois Commerce Comm’n II”).
`
`14 Illinois Commerce Comm’n II, 756 F.3d at 561-62.
`
`
`
`7
`
`

`

`discrete location in any RTO or ISO region, the costs of those projects must be allocated to the
`
`consumers in the location receiving those benefits.
`
`In this ANOPR, FERC seeks comment on the proposed policy of broadly spreading the
`
`costs of new transmission investment needed to move wind and solar power across vast regions
`
`of the country. The Seventh Circuit rulings mandate that the costs of such new investment must
`
`be roughly commensurate with the benefits to be received by the consumers who will bear these
`
`costs. While this concept is universally accepted by most stakeholders in the industry today, the
`
`determination of those benefits for any given project is much more controversial.
`
`For example, to the extent new transmission investment may be needed to bring off-shore
`
`wind power to on-shore cities located on the eastern seaboard in PJM, it is highly unlikely that
`
`consumers in Ohio would benefit from those lines or that power. The Seventh Circuit rulings
`
`would require that the costs of such investment be allocated solely to the eastern PJM customers
`
`those projects would serve and benefit. That is, it is unlikely that the electrons from the offshore
`
`wind on the Atlantic Ocean would reach Ohioans. To the extent Ohio consumers receive none of
`
`that power and none of the reliability benefits from the new transmission investment, they should
`
`not be burdened with the costs of those projects.
`
`In any proposed rulemaking that follows this ANOPR, FERC must keep in mind that
`
`simply spreading the costs of new transmission needed to move renewable power to discrete
`
`locations within an RTO on a postage-stamp (or rate-socialization) basis will not result in just
`
`and reasonable rates for all consumers. Notwithstanding the Seventh Circuit’s 2013 ruling
`
`upholding MISO’s cost-spreading proposal for certain large multi-value projects, that same
`
`Court one year later still found unlawful PJM’ proposal to use the postage stamp approach to
`
`
`
`8
`
`

`

`disproportionately shift to consumers in western PJM the costs of transmission projects needed
`
`to serve eastern PJM consumers.15
`
`FERC also should continue to use the “but for” approach to determining the beneficiaries
`
`of large new transmission lines needed to move power from remotely-located renewable
`
`resources long distances to serve consumers in densely populated cities. To the extent existing
`
`transmission facilities in Ohio are reliable and sufficient to serve Ohio needs without large inter-
`
`regional lines, the cost of lines needed to move vast amounts of wind or solar power from the
`
`western edge of PJM to the east coast cities should not be allocated to Ohio consumers. Power
`
`flow models such as PJM’s distribution factor approach to determining beneficiaries for new
`
`lines may provide the requisite factual basis for allocating new transmission investment costs to
`
`consumers. FERC should not socialize the costs to consumers of large transmission lines built
`
`primarily to move large amounts of renewable generation from the east to the west in PJM or
`
`between or among various RTOs.
`
`Nor should FERC speculate as to where future generation may locate. FERC should not
`
`require subsidization for transmission lines on the theory that the line may be needed to serve
`
`future generation that may, or may not, be built. Cost allocation decisions must be made on the
`
`basis of current or near-term transmission needs. The changing nature of the types of resources
`
`serving future loads should not be an excuse to burden all consumers through a postage-stamp
`
`approach to allocating costs for facilities that may never benefit them or to move power from
`
`generation resources that may never be built.
`
`
`
`
`
`
`15 Illinois Commerce Comm’n II, 756 F.3d at 565.
`
`
`
`9
`
`

`

`B.
`
`The Order No. 2003 approach to allocating network upgrade costs related to
`generation interconnections remains the most reasonable means of making
`sure new generation is properly sized and located.
`
`FERC seeks comment on whether to revise its current approach adopted in Order No.
`
`200316 of either initially allocating the costs associated with Network Upgrades that are needed
`
`to interconnect a new generator to the transmission system to that generator, and then crediting
`
`those upfront payments back over a 20-year period. Alternatively, FERC proposes using a
`
`participant funding approach in RTO regions that assigns all of the costs of any needed Network
`
`Upgrades required to interconnect a generator to the transmission grid to the first generator
`
`whose project causes the need for those upgrades.17 FERC implemented the crediting policy to
`
`provide the transmission owners with a source of funds to construct interconnection-related
`
`Network Upgrades. By doing so, FERC alleviated delay in construction of those facilities, and to
`
`provide interconnection customers with “a strong incentive to make efficient siting decisions,
`
`and in general, to make good faith requests for interconnection service.”18 A strong incentive for
`
`properly locating new generating resources remains as important for the renewable resources
`
`contemplated by the ANOPR as it was for the natural gas-fired resources contemplated in Order
`
`No. 2003. Changing the current policy to require that the costs of Network Upgrades, which
`
`may not be needed but for the interconnection of one or two generating plants, be allocated to all
`
`consumers in the RTO/ISO region would require consumers to subsidize the development of
`
`generating plants. Any such policy would fail to send the proper incentives for sound
`
`investments that underlie Order No. 2003.
`
`
`16 Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003, Final Rule, 104
`FERC ¶ 61,103 (2003); order on reh’g, Order No. 2003-A, 106 FERC 61,220 (200_); order on reh’g, Order No.
`2003-B, 109 FERC ¶ 61,287 (2004); order on reh’g, Order No. 2003-C, 111 FERC ¶ 61,401 (2005).
`
`17 ANOPR at PP 102, 105; see also Order No. 2003, 104 FERC ¶ 61,103 at PP 694-95.
`
`18 ANOPR at P 103, citing Order No. 2003-A, 106 FERC ¶ 61,220 at P 613.
`
`
`
`10
`
`

`

`Subsidies are inherently incompatible with competitive market outcomes, distort
`
`economic price signals, and are fundamentally bad for consumers. All consumers are harmed
`
`when the competitive market for electricity is laden with subsidized generation. Subsidies do not
`
`work in markets because they distort pricing and undermine competition by displacing more
`
`cost-effective resources, to the detriment of consumers.19
`
`FERC expresses concern (ANOPR at P 112) that failure to broadly allocate the costs of
`
`Network Upgrades needed for generation interconnection could result in certain subsequent
`
`interconnecting power plants being free riders and not paying their fair share for use of those
`
`interconnection facilities. This situation can be better addressed than requiring consumers to
`
`subsidize the interconnection of these generating plants.
`
`First, FERC and the involved RTO always should be making sure that the Network
`
`Upgrades needed for any generating project are properly sized for the generator or generators to
`
`be connected. The size of the upgrades should be based on definitive load studies of known
`
`interconnection projects. RTOs should not be building out the transmission system on expected
`
`consumer needs or anticipated generation interconnections. Transmission Providers should be
`
`building for generators in the queue that they know will be developed. FERC should not be
`
`embarking on a “if you build it, they will come” approach to transmission planning. Such an
`
`approach is destined to leave consumers paying for inefficient, overbuilt, unnecessary or gold-
`
`plated transmission systems.
`
`
`19 Grid Reliability and Resilience Pricing, Docket No. RM18-1-000, DOE Staff Report at 14 n.q.
`
`
`
`11
`
`

`

`Second, FERC could require annual reassessments of cost allocation determinations.20
`
`Transmission Providers could undertake annual reassessments of whether other generators that
`
`have interconnected to the system where the Network Upgrades were funded by the first
`
`generator on the system are in fact using those Network Upgrades. To the extent they are, FERC
`
`could direct the Transmission Provider to use an approach that would annually reassess the
`
`beneficiaries of the generation interconnection upgrades. The same is true for any new customer
`
`demand growth that are added in the area where the Network Upgrades were constructed, or in
`
`situations where the RTO has determined that the Network Upgrades are now providing benefits
`
`to existing customers around the upgrades. Both approaches avoid the distorted investment
`
`signals inherent in a subsidization approach and both better comport with the cost
`
`causation/beneficiary pays precedent.
`
`C.
`
`FERC should open a separate investigation into reforming PJM’s
`supplemental transmission project and local transmission planning processes
`to protect consumers from potential unnecessary and excessive charges.
`
`FERC seeks comment on “whether there is sufficient clarity on the roles and
`
`responsibilities between state and federal regulators regarding the local transmission planning
`
`criteria and the development of local transmission facilities (e.g., “Supplemental Transmission
`
`Projects” in PJM).”21 FERC also requests that stakeholders comment on “whether such
`
`transmission facilities require additional oversight and whether additional coordination among
`
`state and federal regulators would be beneficial.22 OCC appreciates this inquiry into the
`
`
`20 To the extent an RTO engages in participant funding and allocates the incremental capacity transfer rights
`associated with the Network Upgrades funded solely by the interconnecting generator to that generator, an approach
`of annually redetermining cost allocations would also require an annual redetermination of capacity transfer rights.
`
`21 ANOPR at P 171.
`
`22 Id.
`
`
`
`12
`
`

`

`regulatory gap that exists between the planning processes for regional and local transmission
`
`facilities in RTOs, and in PJM in particular.
`
`Order No. 89023 established guiding principles for reforming the transmission planning
`
`process for both regional and local transmission facilities, including the requirement for a
`
`transparent method for reviewing planned new regional and local investment, and for a method
`
`of allocating the costs associated with regional facilities.24 In somewhat of a regulatory “Catch
`
`22,” although FERC delegated its regulatory oversight authority for regional and local
`
`transmission planning to PJM, many of the local Supplemental Transmission Projects, evade
`
`regulatory oversight. This is because PJM reviews local projects only to determine whether they
`
`will affect regional reliability, but not for the actual need for the project, cost of service, or the
`
`cost-effectiveness of the proposed solution to the identified local transmission need. Nor does
`
`the state of Ohio Power Siting Board review these projects for need, prudence, or cost efficiency.
`
`Currently, more than 75% of the costs of new transmission projects in PJM escape review
`
`by both regional and local regulatory authorities. Yet these transmission projects remain a
`
`monopoly service for which consumers must pay. Region-wide in PJM, these local
`
`Supplemental Projects in 2020 totaled more than $4.3 billion, far outstripping the $1.7 billion in
`
`region-wide, baseline reliability RTEP projects overseen by PJM and FERC. In Ohio, 97.6% of
`
`the estimated costs for proposed new transmission for the state in 2020, i.e., $1.09 billion in
`
`investment out of $1.11 billion in total investments in the state was associated with Supplemental
`
`
`23 Preventing Undue Discrimination and Preference in Transmission Service, Order No. 890, 118 FERC ¶ 61,119
`(Order No. 890), order on reh’g, Order No. 890-A, 121 FERC ¶ 61,297 (2007); order on reh’g, Order No. 890-B,
`123 FERC ¶ 61,299 (2008)(“Order No. 890-B); order on reh’g, Order No. 890-C, 126 FERC ¶ 61,228 (2009) (Order
`No. 890-C).
`
`24 Order No. 890 at PP 106, 140-141.
`
`
`
`13
`
`

`

`Projects that escape any regulatory review.25 The same trend existed in 201926 and 2018.27
`
`These Supplemental Transmission Project expenditures only include those over $5 million. To
`
`comprehensively address the escalating transmission charges in Ohio and PJM and to protect
`
`consumers from unnecessary and excessive charges, FERC should open an inquiry in a separate
`
`proceeding to make certain that there is regulatory oversight for utility investment in
`
`Supplemental Transmission Projects in PJM.
`
`Absent action by FERC, these projects will continue to evade regulatory review, leaving
`
`them prone to review only in after-the-fact prudence reviews in transmission rate proceedings.28
`
`These after-the-fact prudence reviews are an ineffective and inefficient means of making sure
`
`that transmission projects are needed and cost-effective and that consumers pay only just and
`
`reasonable rates for transmission service.
`
`Of relevance for Ohioans is the fact that on September 24, 2021, the Ohio Power Siting
`
`Board (“OPSB”) released a Draft Report29 to the Ohio General Assembly refusing, despite
`
`
`25 2020 Ohio State Infrastructure Report at Slides 3, 17, 20-31 (April 2021), available at https://www.pjm.com/-
`/media/library/reports-notices/state-specific-reports/2020/2020-ohio-state-infrastructure-report.ashx.
`
`26 2019 Ohio State Infrastructure Report at 3, 19-20, 23-37 (May 2020) prepared by PJM Interconnection, L.L.C.,
`available https://www.pjm.com/-/media/library/reports-notices/state-specific-reports/2019/2019-ohio-state-
`infrastructure-report.ashx?la=en.
`
`27 2018 Ohio State Infrastructure Report at Slides 3, 18-19, 21-32 (May 2019) prepared by PJM Interconnection,
`L.L.C., available at https://www.pjm.com/-/media/library/reports-notices/state-specific-reports/2018/2018-ohio-
`state-data.ashx?la=en.
`
`28 The Ohio Power Siting Board recently opened an inquiry into whether its enabling legislation should be revised to
`grant it broader oversight over the need for and costs of local transmission projects in the state. Ohio Power Siting
`Board Staff Draft Report to the General Assembly Regarding the Power Transmission System at 6, In the Matter of
`the Ohio Power Siting Board’s Report to the General Assembly Regarding the Power Transmission System, PUCO
`Case No. 21-796-EL-UNC (Sept. 24, 2021), available at
`http://dis.puc.state.oh.us/DocumentRecord.aspx?DocID=ea0feda0-8145-4c4c-accc-18417850c90c (“OPSB Staff
`Draft Report”). However, the current proposal by the Ohio Power Siting Board’s Staff is to rely solely on FERC
`and PJM for these reviews.
`
`29 Id. at P. 10.
`
`
`
`14
`
`

`

`OCC’s recommendations,30 to review for cost, need, and prudency local Supplemental
`
`Transmission Projects. In response to the Draft Report, OCC again recommended that, among
`
`other things, the OPSB must review for cost and prudency all Supplemental Transmission
`
`Projects rated at 69kV and above. Specifically, OCC noted that over $5.8 billion31 in
`
`Supplemental Transmission Projects have been approved in Ohio in just four years (2017
`
`through 2020) and nearly all these projects will escape regulatory review.32 If Ohio’s regulators
`
`continue to refuse to review Supplemental Transmission Projects for cost, need, and prudency,
`
`FERC must step up to close this regulatory loophole.

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket