throbber

`
`UNITED STATES OF AMERICA
`BEFORE THE
`FEDERAL ENERGY REGULATORY COMMISSION
`
`
`)
`)
`)
`
`
`
`Docket No. RM22-14-001
`
`
`
`Improvements to Generator
`Interconnection Procedures
`and Agreements
`
`
`
`REQUEST FOR REHEARING AND CLARIFICATION
`OF DOMINION ENERGY SERVICES, INC.
`
`Pursuant to Section 313(a) of the Federal Power Act (“FPA”),1 and Rule 713 of the Federal
`
`Energy Regulatory Commission’s (“Commission” or “FERC”) Rules of Practice and Procedure,2
`
`Dominion Energy Services, Inc., on behalf of Virginia Electric and Power Company d/b/a
`
`Dominion Energy Virginia (“DEV”) and Dominion Energy South Carolina, Inc. (“DESC,”
`
`together with DEV, “Dominion Energy” or the “Company”),3 hereby requests rehearing, and seeks
`
`one clarification of the final rule issued in this proceeding on July 28, 2023.4
`
`As discussed in its Initial Comments5 and Reply Comments6 in this proceeding, Dominion
`
`Energy supports common sense reforms to pro forma interconnection processes. Indeed, DESC
`
`
`16 U.S.C. § 825l(a) (2018).
`1
`18 C.F.R. § 385.713 (2023).
`2
`As described herein, both DEV and DESC are operating subsidiaries of Dominion Energy, Inc. For
`3
`the purposes of this request for rehearing, references to “Dominion Energy” shall include Dominion Energy,
`Inc., DEV, and DESC, as well as Dominion Energy Services, Inc., a subsidiary of Dominion Energy, Inc.
`4
`Improvements to Generator Interconnection Procedures & Agreements, Order No. 2023, 184
`FERC ¶ 61,054 (2023) (“Order No. 2023”).
`5
`Improvements to Generator Interconnection Procedures & Agreements, Initial Comments of
`Dominion Energy Services, Inc., Docket No. RM22-14-000 (filed Oct. 13, 2022) (“Dominion Initial
`Comments”).
`6
`Improvements to Generator Interconnection Procedures & Agreements, Reply Comments of
`Dominion Energy Services, Inc., Docket No. RM22-14-000 (filed Dec. 14, 2022) (“Dominion Reply
`Comments”).
`
`

`

`
`
`and DEV (through PJM Interconnection, L.L.C. (“PJM”)) were early adopters of a “first ready,
`
`first served” cluster process. Dominion Energy thus supports the Commission’s efforts to remedy
`
`generator interconnection backlogs and make the process more efficient for future interconnection
`
`customers, while maintaining system reliability. However, the Commission erred by issuing a
`
`generic rulemaking determining all interconnection processes, even those that the Commission
`
`recently accepted, are unjust and unreasonable. Disturbing these processes before they have time
`
`to work would upset the carefully crafted and negotiated reforms and would likely lead to further
`
`delays.
`
`Dominion Energy seeks rehearing on four issues: 1) the Commission did not engage in
`
`reasoned decision making under the Administrative Procedure Act (“APA”) by relying on out-of-
`
`date data and did not consider recent interconnection reforms by PJM and DESC that are similar
`
`to the replacement rate adopted in Order No. 2023 and therefore the Commission’s actions in Order
`
`No. 2023 were arbitrary and capricious; 2) the Commission exceeded its FPA Section 206
`
`authority by declaring all existing interconnection tariffs, including recently accepted reforms by
`
`PJM and DESC that are similar to the replacement rate adopted in Order No. 2023, as unjust,
`
`unreasonable, and unduly discriminatory or preferential without substantial evidence; 3) the
`
`Commission’s decision to eliminate the reasonable efforts standard and impose study delay
`
`penalties on transmission providers and owners is not supported by substantial evidence and is
`
`arbitrary and capricious under the APA; and 4) the Commission’s imposition of a 90-day
`
`compliance deadline for the final rule is contrary to substantial evidence and fails to consider the
`
`alternative timelines presented by commenters. Accordingly, Dominion Energy respectfully
`
`requests rehearing of Order No. 2023. Additionally, Dominion Energy requests clarification about
`
`the timing of effective dates for compliance measures.
`
`2
`
`

`

`
`
`I. BACKGROUND ON DEV AND DESC
`
`DEV is a public service corporation engaged in the generation, transmission, distribution,
`
`and sale of electricity to retail and wholesale customers, and is a subsidiary of Dominion Energy,
`
`Inc., a holding company under the Public Utility Holding Company Act of 2005. DEV furnishes
`
`electric service to approximately 2.5 million retail customers in its approximately 30,000 square
`
`miles of certificated service territory covering parts of Virginia and North Carolina. It does so by
`
`operating a diverse fleet of natural gas, renewable, nuclear, oil, pumped storage, and coal fired
`
`power stations, which collectively provide over 23,000 MW of generation capacity. It also owns
`
`over 6,700 miles of electric transmission facilities.
`
`DEV is organized under the laws of the Commonwealth of Virginia and is a public utility
`
`subject to regulation by the Virginia State Corporation Commission (“VSCC”) and by the North
`
`Carolina Utilities Commission (“NCUC”), whose regulations establish DEV’s retail customer
`
`rates. DEV provides electric service by buying and selling wholesale power in PJM’s energy,
`
`ancillary service, and capacity markets. PJM is a regional transmission organization and
`
`independent system operator (“RTO/ISO”) that DEV joined effective May 1, 2005, after obtaining
`
`prior approval from FERC, the VSCC, and the NCUC. PJM has operational control over DEV’s
`
`transmission assets.
`
`DESC is a public utility engaged in the generation, transmission, distribution, and sale of
`
`electricity to retail and wholesale customers, and is a subsidiary of Dominion Energy, Inc. DESC
`
`is not a member of an RTO. DESC owns and operates facilities for the transmission of electric
`
`energy in interstate commerce and provides transmission service over those facilities pursuant to
`
`the terms of its Commission-approved Open Access Transmission Tariff (“OATT”). DESC owns
`
`or controls approximately 5,650 MW of generation, sells electric energy and capacity at cost-based
`
`3
`
`

`

`
`
`rates within its Balancing Authority Area (“BAA”), and is authorized to sell electric energy and
`
`capacity at market-based rates outside its BAA. DESC’s electric service territory extends into 24
`
`counties covering nearly 17,000 square miles in the central, southern, and southwestern portions
`
`of South Carolina. It also owns approximately 3,250 miles of electric transmission facilities.
`
`DESC supplies natural gas to retail customers in all or part of 35 counties in South Carolina
`
`covering more than 25,000 square miles and it purchases and distributes natural gas in support of
`
`its retail natural gas sales. DESC’s retail electricity and retail natural gas activities are subject to
`
`the jurisdiction of the Public Service Commission of South Carolina (“SCPSC”).
`
`Dominion Energy filed comments on the Notice of Proposed Rulemaking7 seeking
`
`flexibility on a number of the proposals contained therein, and recommending that the Commission
`
`refrain from adopting certain proposals at all, including the IX NOPR’s proposal to eliminate the
`
`reasonable efforts standard.8 Dominion Energy also urged the Commission not to interfere with
`
`transmission providers’ recently adopted interconnection reforms that were already in the middle
`
`of transitioning to a first ready, first served cluster process.
`
`II.
`
`STATEMENT OF ISSUES AND SPECIFICATIONS OF ERROR
`
`Pursuant to Rule 713(c) of the Commission’s Rules of Practice and Procedure,9 Dominion
`
`Energy submits the following statement of issues and specifications of error:
`
`1. Order No. 2023 is arbitrary and capricious under the APA because the Commission’s
`determination that all interconnection tariffs were unjust and unreasonable was not
`supported by substantial evidence and does not constitute reasoned decision making. The
`Commission relied on stale data, did not critically evaluate the statistics it relied upon, and
`ignored more recent information about interconnection reforms that it accepted recently.
`
`Improvements to Generator Interconnection Procedures & Agreements, Notice of Proposed
`7
`Rulemaking, 179 FERC ¶ 61,194 (2022) (“IX NOPR”).
`8
`See generally Dominion Initial Comments; Dominion Reply Comments.
`9
`18 C.F.R. § 385.713.
`
`4
`
`

`

`
`
`5 U.S.C. §§ 706(2)(A), (E); see Motor Vehicle Mfrs. Ass’n of U.S., Inc. v. State Farm Mut.
`Auto. Ins. Co., 463 U.S. 29, 43 (1983) (“State Farm”); S.C. Pub. Serv. Auth. v. FERC, 762
`F.3d 41, 54-55 (D.C. Cir. 2014) (“S.C. Pub. Serv. Auth.”); Emera Me. v. FERC, 854 F.3d
`28-29 (D.C. Cir. 2017) (“Emera Maine”); Fla. Gas Transmission Co. v. FERC, 604 F.3d
`636, 641 (D.C. Cir. 2010) (“Fla. Gas”). Specifically, the Commission did not consider
`that the Commission itself had recently accepted PJM’s and DESC’s interconnection
`reforms (approved by the stakeholders) as just and reasonable, and the reforms are so recent
`that they have not had time to be fully implemented. See PJM Interconnection, L.L.C., 181
`FERC ¶ 61,162 (2022), reh’g denied by operation of law, 182 FERC ¶ 62,055 (2023), order
`on reh’g, 184 FERC ¶ 61,006 (2023) (modifying the discussion and reaching the same
`result); Dominion Energy S.C., Inc., Docket No. ER22-301-000 at 1 (issued Dec. 28, 2021)
`(delegated order). The Commission’s requirement that all transmission providers submit
`compliance filings and re-justify their recently accepted revisions is not proportionate to
`the problem identified. Interstate Natural Gas Ass’n of America v. FERC, 285 F.3d 18, 37
`(2002) (“INGAA”); Assoc. Gas Distributors v. FERC, 824 F.2d 981, 1020 (D.C. Cir. 1987)
`(“AGD”). The Commission’s generic determination is distinguishable from generic
`rulemakings that were upheld in Transmission Access Policy Study Group V. FERC, 225
`F.3d 667, 668 (D.C. Cir. 2000) (“TAPS”), aff’d sub nom. New York v. FERC, 535 U.S. 1
`(2002); INGAA, 285 F.3d at 37 and S.C. Pub. Serv. Auth. 762 F.3d 41.
`2. The Commission exceeded its statutory authority under Section 206 of the FPA by failing
`to make the sufficient factual determination that each of the existing interconnection
`processes are unjust and unreasonable. See Emera Maine, 854 F.3d at 25 (citation omitted)
`(“[A] finding that an existing rate is unjust and unreasonable is the ‘condition precedent’
`to FERC’s exercise of its section 206 authority to change that rate. Section 206, therefore,
`imposes a ‘dual burden’ on FERC. Without a showing that the existing rate is unlawful,
`FERC has no authority to impose a new rate.”). This burden equally applies in a
`rulemaking context. S.C. Pub. Serv. Auth., 762 F.3d 64-65.
`3. Order No. 2023 is arbitrary and capricious under the APA because the Commission’s
`elimination of the reasonable efforts standard and imposition of penalties to transmission
`providers was not supported by substantial evidence. Fla. Gas, 604 F.3d at 641. The
`Commission did not provide sufficient evidence that imposition of penalties on
`transmission providers would remedy the problem or that transmission providers can
`control the timing of interconnection studies. Instead, the Commission made “purely
`conclusory” statements not based on any record evidence. Tarpon Transmission Co. v.
`FERC, 860 F.2d 439, 444 (D.C. Cir. 1998) (“Tarpon”). Thus, the Commission cannot
`demonstrate that it made a “principled and reasoned decision supported by the evidentiary
`record.” Emera Maine, 854 F.3d at 32. Further, it did not adequately address record
`evidence to the contrary of its findings. PPL Wallingford Energy LLC v. FERC, 419 F.3d
`1194, 1199 (D.C. Cir. 2005) (citing Canadian Ass’n of Petroleum Producers v. FERC, 254
`F.3d 289, 299 (D.C. Cir. 2001)).
`
`
`
`
`5
`
`

`

`
`
`4. The Commission did not engage in reasoned decisionmaking supported by substantial
`evidence when it shortened its proposed 180-day compliance period to 90 days. No
`commenter requested a shorter compliance deadline, and several commenters sought a
`longer deadline than the 180-day compliance deadline proposed in the IX NOPR. See
`Greater Bos. Television Corp. v. FCC, 444 F.2d 841, 851 (D.C. Cir. 1970) (an agency must
`give “reasoned consideration to all the material facts and issues” and “engage[] in reasoned
`decision making”); Am. Gas Assn. v. FERC, 389 U.S. App. D.C. 162, 167, 593 F.3d 14, 20
`(D.C. Cir. 2010) (“[R]easoned decisionmaking requires considering [reasonable]
`alternatives.”); Laclede Gas Co. v. FERC, 873 F.2d 1494, 1498, (D.C. Cir. 1989) (“[W]here
`a party raises facially reasonable alternatives to FERC’s decision . . . the agency must either
`consider those alternatives or give some reason, within its broad discretion . . . for declining
`to do so.” (internal citation omitted)); Tarpon, 860 F.2d at 442; Apache Corp. v. FERC,
`627 F.3d 1220, 1222-23 (D.C. Cir. 2010).
`
`III. ARGUMENT
`
`A. The Commission did not meet its APA obligation to provide substantial
`evidence to justify effectuating a generic rulemaking and compliance filing
`requirement in Order No. 2023.
`
`
`
`DEV (through PJM) and DESC are both currently transitioning their interconnection
`
`processes from a “first come, first served” serial process to a “first ready, first served” process
`
`utilizing cluster studies, following Commission acceptance of those significant tariff reforms.
`
`DESC and PJM undertook these reforms to address interconnection queue backlogs and to speed
`
`up interconnection processes. Both sets of reforms sought to address the same problems that the
`
`Commission later identified as its justification for adopting Order No. 2023, and indeed FERC
`
`noted DESC’s process as a basis for several proposals in the IX NOPR and the final rule.10
`
`
`See IX NOPR, 179 FERC ¶ 61,194 at P 21 (acknowledging DESC as transitioning to from the serial
`10
`first-come, first-served study process to a first-ready, first-served cluster study process in outlining the need
`for reform); id. at PP 80, 82 (proposing the allocation of study costs on a split pro rata/per capita basis, the
`same as DESC); Order No. 2023, 184 FERC ¶ 61,054 at P 177 (adopting proposal to make cluster studies
`the required interconnection study method); id. at P 418 (adopting proposal to allocate study costs on a split
`pro rata/per capita basis); id. at P 465 (noting DESC had adopted study timelines similar to those adopted
`in the final rule); see also id. at P 59 (noting that “final rule uses some of these individual and incremental
`improvements [already implemented by early adopters] as a basis for a broad suite of reforms that, in their
`entirety, have not yet been adopted by any region and we believe will ensure that interconnection customers
`are able to interconnect to the transmission system in a reliable, efficient, transparent, and timely manner”).
`
`6
`
`

`

`
`
`Moreover, DESC’s and PJM’s reforms were thoroughly vetted by stakeholders to ensure the
`
`interconnection reforms worked for their particular regions.
`
`PJM filed its interconnection reforms with the Commission on June 14, 2022,11 they were
`
`approved subject to condition on November 29, 2022,12 and the transition component of the rules
`
`became effective January 3, 2023.13 PJM’s transition process only just began on July 10, 2023,
`
`mere days before the Commission issued Order No. 2023.14
`
`The PJM proposal was the result of an approximately 18-month stakeholder process.15 In
`
`the course of the Commission proceeding, PJM was required to provide supplemental information
`
`including information about “how the proposed removal of sections related to reporting and
`
`penalties is consistent with or superior to similar sections of Order No. 890; the specifics of the
`
`revised site control requirements; a project’s eligibility to be processed through the proposed
`
`Expedited Process; and why it is just and reasonable for PJM’s generator interconnection
`
`procedures to exclude a 10 kW Inverter Process and a Fast Track Process.”16 In its order accepting
`
`PJM’s interconnection reforms only 10 months ago, the Commission evaluated PJM’s initial filing,
`
`
`PJM Interconnection, L.L.C., Tariff Revisions for Interconnection Process Reform, Request for
`11
`Commission Action by October 3, 2022, and Request for 30-Day Comment Period, Docket No. ER22-
`2110-000 (filed June 14, 2022) (“PJM Interconnection Reform Filing”).
`12
`PJM Interconnection, L.L.C., 181 FERC ¶ 61,162 (2022), reh’g denied by operation of law, 182
`FERC ¶ 62,055 (2023), order on reh’g, 184 FERC ¶ 61,006 (2023) (modifying the discussion and reaching
`the same result).
`13
`PJM Interconnection, L.L.C., 181 FERC ¶ 61,162 at P 9 (providing for varying effective dates for
`later components of the rules).
`14
`See PJM Interconnection, L.L.C., Notification of Occurrence of Transition Date, Docket No. ER22-
`2110-000 (filed July 11, 2023); see also Transition to New Interconnection Process Begins July 10, PJM
`Inside the Lines (July 6, 2023), https://insidelines.pjm.com/transition-to-new-interconnection-process-
`begins-july-10/.
`15
`Order No. 2023, 184 FERC ¶ 61,054 at P 1749.
`16
`PJM Interconnection, L.L.C., 181 FERC ¶ 61,162 at P 22.
`
`7
`
`

`

`
`
`its supplemental response, and comments and protests from approximately 80 different parties and
`
`then specifically found PJM’s proposed revisions to its interconnection procedures to be “just and
`
`reasonable.”17 At the time of this request for rehearing, PJM has only just begun the transition
`
`process.
`
`Now, through a generic FPA Section 206 factual determination and rulemaking, the
`
`Commission’s order has the effect of declaring that PJM’s interconnection reforms are unjust and
`
`unreasonable. While the Commission speaks in terms of the pro forma LGIP, LGIA, SGIP, and
`
`SGIA when making its determination,18 its compliance obligation extends to all existing processes
`
`and essentially requires them to re-prove the justness and reasonableness of their processes,
`
`creating a remedy that is “disproportionate” to the identified problem.19 The Commission cites no
`
`specific evidence to demonstrate that PJM’s tariff that is currently in effect is unjust and
`
`unreasonable. Indeed—it would be difficult to do so, as PJM has not yet completed its transition
`
`and so there is no data available to determine whether its reformed process is successful. Instead,
`
`the PJM queue delays cited in Order No. 2023 coincide with the previous interconnection tariff,
`
`which used a serial queue process.20 These cited backlogs are the exact reason that PJM
`
`collaborated diligently with stakeholders to develop a solution. PJM expects to clear 62,000 MW
`
`
`PJM Interconnection, L.L.C., 181 FERC ¶ 61,162 at P 34.
`17
`Order No. 2023 184 FERC ¶ 61,054 at P 37 (finding “existing pro forma generator interconnection
`18
`procedures and agreements [to be] unjust, unreasonable, and unduly discriminatory or preferential”).
`19
`Id. at PP 1762-64 (requiring all “transmission providers” to submit compliance filings, noting the
`standard for proposed deviations from the final rule in the compliance filing”); INGAA, 285 F.3d at 37-39.
`20
`Order No. 2023, 184 FERC ¶ 61,054 at P 39 (relying on PJM interconnection wait time data as of
`February 2022); id. at Appendix B Tables 2-5 (all relying on data from the end of calendar year 2022 and
`earlier).
`
`8
`
`

`

`
`
`for connection under the new process by the end of 2024, compared to just 2,000 MW in 2022
`
`under the serial process that the Commission assessed.21
`
`Similarly, DESC filed its package of interconnection reforms in November of 2021, and
`
`they were accepted on December 28, 2021.22 DESC’s transitional process began on June 13, 2022
`
`and is ongoing.23 No protests or adverse comments were filed.24 In its filing DESC pointed to
`
`delays in both its Feasibility Study timelines and on its System Impact Study timelines as driving
`
`the need for its proposed reforms.25 DESC’s filing was based on approximately 12 months of
`
`stakeholder engagement26 and included many—but not all—of the components adopted in Order
`
`No. 2023. DESC’s reforms are working. Since the transitional cluster process began, DESC
`
`timely completed its Phase 1 transitional study for the 26 projects remaining in the transitional
`
`cluster in January of 2023 and completed its Transitional Cluster Phase 2 Study in August 2023.27
`
`
`See Transition to New Interconnection Process Begins July 10, PJM Inside the Lines, (July 6,
`21
`2023), https://insidelines.pjm.com/transition-to-new-interconnection-process-begins-july-10/.
`22
`See Dominion Energy S.C., Inc., Modifications to DESC’s Large Generator Interconnection
`Procedures to Implement Clustering Approach, Docket No. ER22-301-000 (filed Nov. 1, 2021) (“DESC
`Interconnection Reform Filing”); Dominion Energy S.C., Inc., Docket No. ER22-301-000 at 1 (issued Dec.
`28, 2021) (delegated order).
`23
`See Notice of Transition to the Definitive Interconnection Study Process, Notice_of_Transition_to
`_Definitive_Interconnection_Study_Process.pdf (oati.com) (posted to OASIS June 13, 2022); see also
`Dominion Energy S.C., Inc., Informational Report in Compliance with Section 4.5.7 of DESC’s Large
`Generator Interconnection Procedures (“LGIP”) at 3-4, Docket No. ER19-1946-000 (filed May 15, 2023)
`(“DESC initiated a Transitional Cluster Study process on June 13, 2022.”).
`24
`See generally Dominion Energy S.C., Inc., Docket No. ER22-301-000.
`25
`DESC Interconnection Reform Filing, Transmittal Letter at 6-7 (showing that 100% of DESC’s
`Feasibility Studies has exceeded its 45-calendar day deadline, while 100% of DESC’s System Impact
`Studies exceeded its 90-calendar day timeline).
`26
`DESC Interconnection Reform Filing, Transmittal Letter at 9. Following the FERC filing, DESC
`took an additional six months to implement a corresponding process for state-jurisdictional interconnection
`requests.
`27
`See Dominion Energy S.C., Inc., Informational Report in Compliance with Section 4.5.7 of DESC’s
`Large Generator Interconnection Procedures (“LGIP”), Docket No. ER19-1946-000 (filed May 15, 2023).
`
`9
`
`

`

`
`
`Since June 17, 2022, eight requests remain in the transitional cluster at this time.28 DESC began
`
`its 2023 annual cluster process on April 1, 2023.29
`
`APA Section 706(2)(E)30 and FPA Section 313(b)31 require the Commission to base its
`
`decisions on substantial evidence. The Court of Appeals for the District of Columbia Circuit has
`
`also stated that in order for the Commission to regulate rates under FPA Section 206, a
`
`determination that a rate is unjust, unreasonable and unduly discriminatory or preferential must be
`
`supported by substantial evidence.32
`
`Though the Commission is not required to rely on “empirical evidence”,33 the Commission
`
`must rely on substantial, not old, evidence and cannot ignore new circumstances as justification to
`
`determine that existing rates are unjust and unreasonable.34 Similarly, though the Commission
`
`“may rely on ‘generic’ or ‘general’ findings of a systemic problem to support imposition of an
`
`industry wide solution”,35 any finding by the Commission must still be rooted in facts or reasonable
`
`
`See Dominion Energy South Carolina OASIS, Transitional Cluster Interconnection Queue – TC1
`28
`Statue: Phase 2 Study (July 21, 2023), https://www.oasis.oati.com/woa/docs/SCEG/SCEGdocs/
`Transitional_Cluster_Queue_20230731_-_OASIS.pdf (last checked August 22, 2023).
`29
`See Dominion Energy South Carolina OASIS, DESC News Archive at 8 (July 31, 2023),
`https://www.oasis.oati.com/woa/docs/SCEG/SCEGdocs/News_Archive_07.31.2023.pdf.
`30
`5 U.S.C. § 706(2)(E).
`31
`16 U.S.C. § 825l.
`32
`S.C. Pub. Serv. Auth., 762 F.3d at 64-65 (citations omitted) (“To regulate a practice affecting rates
`pursuant to Section 206 [of the FPA], the Commission must find that the existing practice is ‘unjust,
`unreasonable, unduly discriminatory or preferential,’ and that the remedial practice it impasse is ‘just and
`reasonable.’ These findings must be supported by ‘substantial evidence,’ which the court has long held does
`not mean empirical evidence.”).
`33
`Id. at 65.
`34
`See, e.g., Consol. Oil & Gas, Inc. v. FERC, 806 F.2d 275, 279 (D.C. Cir. 1986) (internal quotations
`omitted) (“Under the substantial evidence test, we can uphold the Commission’s decision only if it relies
`on such relevant evidence as a reasonable mind might accept as adequate to support [the] conclusion.”).
`35
`S.C. Pub. Serv. Auth., 762 F.3d at 67.
`
`10
`
`

`

`
`
`economic propositions.36 Moreover, the Commission cannot ignore actual facts if it is to be
`
`considered reasoned decision making. Order No. 2023’s generic findings and replacement rate is
`
`not reasoned decision making as it relates to PJM and DESC because 1) it relies on queue delays
`
`and backlogs that predate PJM’s and DESC’s revised interconnection reforms; and 2) it does not
`
`consider those currently effective interconnection reforms when making the determination that all
`
`interconnection tariffs are unjust and unreasonable.37
`
`To support its determination that rates are unjust, unreasonable, and unduly discriminatory
`
`or preferential,38 the Commission states there is an increase in interconnection requests and
`
`backlogs throughout the country and across all regions of the United States.39 The Commission
`
`specifically cites the 2,274 projects in PJM’s queue as of February 2022 40 and observes that 2,544
`
`studies were delayed at the end of 2022 with 2,211 being in PJM.41 But this evidence represents
`
`the interconnection process prior to PJM’s reforms that were approved on November 29, 2022
`
`and began to be implemented in July of 2023. Similarly, DESC’s interconnection reforms were
`
`approved by letter order on December 28, 2021 and became effective January 1, 2022. DESC has
`
`
`See City of Holyoke Gas & Elec. Dep’t v. FERC, 954 F.2d 740, 743 (D.C. Cir. 1992) (“The
`36
`Commission must support its decision with enough data to enable an adversely affected party and by
`extension a reviewing court, to understand its calculation of the comparison rate upon which it would rely,
`as well as the underlying assumptions.”); S.C. Pub. Serv. Auth., 762 F.3d at 67 at 64-65 (Commission’s
`Section 206 findings in rulemaking context must be supported by substantial evidence, which may be
`empirical evidence or reasonable economic propositions).
`37
`As discussed below, the Court of Appeals for the District of Columbia Circuit has upheld generic
`rulemakings without consideration of specific rates, but such that the analysis is inapposite to the
`Commission’s action in Order No. 2023.
`38
`Order No. 2023, 184 FERC ¶ 61,054 at P 37.
`39
`Id. at PP 38, 39.
`40
`Id. at P 39.
`41
`Id. at P 40 & n.116 (citing interconnection study metrics transmission providers posted in
`compliance with Reform of Generator Interconnection Procedures & Agreements, Order No. 845, 163
`FERC ¶ 61,043 (2018) (“Order No. 845”)).
`
`11
`
`

`

`
`
`gone from seventy projects in its queue under the serial process to eight projects remaining in the
`
`transitional cluster process, and did not receive a single dispute or complaint from interconnection
`
`customers during that process. The Commission does not need to support its decisions with
`
`empirical evidence if it does not exist and can instead rely on reasonable economic propositions;
`
`it cannot ignore, however, the empirical evidence before it. To do so is not reasoned decision
`
`making. “The question of sufficiency of the evidence necessarily turns on sufficiency in relation
`
`to the issue and the findings on which the agency action was based,” and here, relying on stale
`
`processing time data to declare a generic problem was in error.42
`
`In addition to relying on stale evidence, the Commission ignored contrary evidence, to
`
`whit, that PJM and DESC had recently adopted interconnection reforms to address the same
`
`problem Order No. 2023 targets to fix. 43
`
`Although the Commission is able to rely on generic rulemakings to support an industry-
`
`wide solution,44 this authority is not without its limits. Order No. 2023’s mandate is unlike the
`
`wholesale reform of the transmission system through Order No. 888 that was considered in TAPS45
`
`and relied upon by the Commission,46 the expansion and creation of new planning obligations
`
`upheld in S.C. Pub. Serv. Auth.,47 or the requirement FERC issued in INGAA to require gas
`
`pipelines to implement a new requirement “only where operationally feasible[,]” and where FERC
`
`
`Pillai v. Civil Aeronautics Bd., 485 F.2d 1018, 1023, 1024 (D.C. Cir. 1973).
`42
`See PPL Wallingford Energy LLC v. FERC, 419 F.3d 1194, 1199 (D.C. Cir. 2005) (citing Canadian
`43
`Ass’n of Petroleum Producers v. FERC, 254 F.3d 289, 299 (D.C. Cir. 2001) (FERC “failed to respond
`meaningfully” to objections).
`44
`See S.C. Pub. Serv. Auth., 762 F.3d at 67.
`45
`TAPS, 225 F.3d 667.
`46
`Order No. 2023, 184 FERC ¶ 61,054 at P 1766.
`47
`See S.C. Pub. Serv. Auth., 762 F.3d at 67.
`
`12
`
`

`

`
`
`would “shoulder the burden under [Section 5 of the NGA, the corollary of FPA Section 206] to
`
`show the required operational feasibility.”48 Order No. 2023 declares as unjust and unreasonable,
`
`through a generic rulemaking, specific reformed tariffs that substantively address the same issue
`
`and with similar or identical reforms. Such a generic finding is disproportionate to the findings
`
`FERC relies on and to the replacement rate it adopts. The courts have emphasized that where a
`
`problem only exists in isolated pockets, “proportionality between the identified problem and the
`
`remedy is the key.”49 Where an industry-wide solution is imposed for a problem that only exists
`
`in isolated pockets, “the disproportion of remedy to ailment would, at least at some point, become
`
`arbitrary and capricious.”50
`
`The Commission did not specifically consider whether PJM’s, DESC’s, and other similarly
`
`situated transmission providers’ reforms are working or even had a chance to be fully
`
`implemented. Reasoned decision making should at least require the Commission to consider all
`
`relevant information – including information about the efficacy of reforms in existing tariffs that
`
`are attempting to address the same problem the Commission is relying upon to make its FPA
`
`Section 206 determination.51
`
`
`INGAA, 285 F.3d at 37-39.
`48
`See id. (emphasis in original); see also S.C. Pub. Serv. Auth., 762 F.3d at 67 (“Absent such an
`49
`extreme ‘disproportion of remedy to ailment,’ the Commission could reasonably proceed to address a
`systemic problem with an industry-wide solution.”).
`50
`AGD, 824 F.2d at 1019.
`51
`See Greater Bos. Television Corp., 444 F.2d at 851 (an agency must give “reasoned consideration
`to all the material facts and issues” and “engage[] in reasoned decision making”); Tarpon, 860 F.2d at 442
`(“We cannot accept an agency determination unless it is the result of reasoned and principled
`decisionmaking that can be ascertained from the record.”); ANR Pipeline Co., 71 F.3d at 901(“[W]here an
`agency departs from established precedent without a reasoned explanation, its decision will be vacated as
`arbitrary and capricious.”); Tenneco Gas v. FERC, 969 F.2d 1187, 1214 (D.C. Cir. 1992) (“Subsumed in
`the substantial evidence requirement is the expectation that agencies will treat fully ‘each of the pertinent
`factors” and issues before them.’” (quoting Public Serv. Comm'n of New York v. FPC, 511 F.2d 338, 345
`D.C.Cir.1975)).
`
`13
`
`

`

`
`
`Though the courts have held the Commission can address case-by-case discrepancies
`
`between the generic determination and specific tariffs during compliance filings,52 this cannot be
`
`considered an unlimited way for the Commission to avoid its obligations under the APA to rely
`
`on substantial evidence when making its FPA Section 206 decisions. Here, the Commission
`
`recently accepted revisions to PJM’s and DESC’s tariffs to address the same issue that Order No.
`
`2023 attempts to address. The Commission should have to consider those tariffs individually and
`
`not sweep them up in a generic determination based on evidence of queue backlogs made under
`
`previous tariffs and regions.
`
`Relying on stale evidence and ignoring the evidence regarding interconnection reforms that
`
`were recently adopted in PJM and by DESC does not constitute substantial evidence necessary to
`
`support the Commission’s generic FPA Section 206 declaration that all existing rates are unjust,
`
`unreasonable, or unduly discriminatory and preferential. The Commission’s remedy—to require
`
`all transmission providers to either modify their tariffs or

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket