throbber
Filing # 153564394 E-Filed 07/18/2022 08:34:01 PM
`
`IN THE CIRCUIT COURT OF THE THIRTEENTH JUDICIAL CIRCUIT
`IN AND FOR HILLSBOROUGH COUNTY, FLORIDA
`
`BIRD RIDES, INC.,
`
`Petitioner,
`
` Case No.
`
`vs.
`
`CITY OF TAMPA,
`
`*Petition Filed Pursuant to
` Fla. R. App. P. 9.100(f)
` and 9.190(b)(3)
`
`
`
`Respondents.
`__________________________________/
`
`PETITION FOR WRIT OF CERTIORARI FROM FINAL
`QUASI-JUDICIAL DECISION OF ADMINISTRATIVE BODY
`
`INTRODUCTION1
`
`Petitioner Bird Rides, Inc. ("Bird") seeks a writ of certiorari quashing
`
`the final quasi-judicial decision of Respondent City of Tampa (the "City")
`
`issued June 16, 2022, denying Bird's administrative appeal of the City's
`
`denial of Bird's bid protest. The City's decision is erroneous because (1) it
`
`failed to afford Bird due process throughout the course of its bid protest and
`
`administrative appeal thereof; (2) it departed from the essential requirements
`
`of the law in refusing to consider any of Bird's arguments raised for the first
`
`1 All references to the Appendix to this Petition are by page number (e.g.,
`[A1] references Appendix page 1).
`
`

`

`time in the appeal; and (3) the City's denial was not supported by competent
`
`substantial evidence.
`
`Bird operates electric scooters in cities and counties around the world,
`
`and it has operated in Tampa since January 2019. Earlier this year, seeking
`
`to continue its operations in Tampa, Bird applied for Request for Proposal
`
`#41100521, City of Tampa Shared Micromobility Program Phase II (the
`
`"RFP"). After submitting a proposal, Bird was shortlisted along with three
`
`other proposers: Skinny Labs d/b/a Spin ("Spin"), Neutron Holdings, Inc.
`
`d/b/a Lime ("Lime"), and HELBIZ, FL, LLC ("Helbiz"). The City subsequently
`
`issued a Notice of Intent to Award (the "Notice of Intent"), with Helbiz and
`
`Spin as winners.
`
`However, the City effectively chose to only send the Notice of Intent
`
`the winning proposers—Helbiz and Spin. Critically, Bird and Lime did not
`
`receive copies of the Notice of Intent from the City. Rather, Bird received a
`
`copy of the Notice of Intent from someone else, on the day that bid protests
`
`were due. When Bird raised the lack-of-notice issue and requested a five-
`
`day extension of time to file its bid protest, the City denied the request for an
`
`extension.
`
`When Bird asked for documents to support its challenge, the City failed
`
`to make timely and complete productions in response to Bird's public record
`
`2
`
`

`

`requests. As a result, Bird had no ability to support its substantive arguments
`
`on how the City’s ranking of proposers was erroneous and why Bird should
`
`have been granted a permit.
`
`After the City denied Bird's bid protest, Bird appealed. Pursuant to the
`
`City Code, a City-appointed hearing officer heard and decided the appeal.
`
`The hearing officer denied the appeal (the "Denial"). Despite the City's
`
`having already seriously handicapped Bird's ability to effectively challenge
`
`the City's actions (by failing to provide adequate notice and then failing to
`
`make a timely and adequate production of public records), the hearing officer
`
`went one step further. The hearing officer found that Bird had waived any
`
`arguments not raised in the bid protest, even those arguments that Bird could
`
`not have raised at the time. This decision flies in the face of basic principles
`
`of due process and is directly contrary to Florida law.
`
`Moreover, the record before the hearing officer was devoid of
`
`competent substantial evidence to support the Denial of the appeal, and
`
`replete with competent substantial evidence to support reversal of the City's
`
`decision on the bid protest. While Bird has raised a number of reasons why
`
`the RFP process failed, any one of these would be enough to render the RFP
`
`process arbitrary and capricious. Taken together, it is clear that this Court
`
`3
`
`

`

`must quash the hearing officer's Denial, and City must re-compete the
`
`procurement.
`
`BASIS FOR JURISDICTION
`
`This Court has jurisdiction pursuant to article V, section 5(b) of the
`
`Florida Constitution and Florida Rules of Appellate Procedure 9.100(c)(2)
`
`and 9.190(b)(3). Florida courts utilize petitions for a writ of certiorari in
`
`reviewing quasi-judicial actions of local governments. See Broward Cnty. v.
`
`G.B.V. Int'l, Ltd., 787 So. 2d 838 (Fla. 2001); Bd. of Cnty. Comm'rs of Brevard
`
`Cnty. v. Snyder, 627 So. 2d 469, 474-75 (Fla. 1993).
`
`The City's Denial is a quasi-judicial final decision. See De Groot v.
`
`Sheffield, 95 So. 2d 912, 915 (Fla. 1957) ("[W]hen notice and a hearing are
`
`required and the judgment of the board are contingent on the showing made
`
`at the hearing, then its judgment becomes judicial or quasi-judicial as
`
`distinguished from purely executive."); City of Tampa Code § 2-282(f)(5)(f),
`
`(decision is final).2 It is therefore reviewable by certiorari to circuit court as a
`
`matter of right. See Miami-Dade Cnty. v. Omnipoint Holdings, Inc., 863 So.
`
`2d 195, 198-99 (Fla. 2003) (citing Fla. Power & Light Co. v. City of Dania,
`
`2 Section 2-282 and other provisions of the City Code referenced herein are
`available
`at
`https://library.municode.com/fl/tampa/
`codes/code_of_
`ordinances?nodeId=COOR_CH2AD_ARTVFI_DIV3PUCO_S2-282PRPRPR.
`4
`
`

`

`761 So. 2d 1089, 1092 (Fla. 2000)); G.B.V. Int'l, 787 So. 2d at 843 (noting
`
`"first-tier certiorari review is not discretionary but rather is a matter of right").
`
`STATEMENT OF FACTS
`
`A.
`
`Factual Background.
`
`Bird is a tech-driven mobility company that operates electric scooters
`
`in cities and counties around the world. [A2] Bird was one of the first scooter
`
`companies to operate in Tampa, and was part of the City's scooter pilot
`
`program. [A3] Bird has provided nearly one million eco-friendly rides to
`
`residents and visitors since January 2019. [A1] This certiorari proceeding
`
`involves Bird's proposal to continue its presence in Tampa.
`
`This certiorari proceeding is not the first time that Bird has identified
`
`issues with the City's procurement process for the scooter program. In 2018,
`
`the City issued a Request for Applications ("RFA") for the scooter pilot
`
`program. [A3] Bird applied. Id. After the City initially rejected Bird's
`
`application for not including the City's own RFA materials, Bird filed a protest.
`
`Id. The City's Director of Purchasing denied the protest, and Bird appealed.
`
`Id. Eventually, the City cancelled and re-issued the RFA. Id. Later, the City
`
`accepted Bird, and Bird went on to successfully operate as part of the pilot
`
`program. Id.
`
`5
`
`

`

`The City again encountered issues in 2020, when it issued an initial
`
`RFP for "Phase II" of its scooter program. [A221] Bird applied but was not
`
`selected. [A224] Noting significant irregularities and errors in the RFP, Bird
`
`filed another bid protest, which the City's Director of Purchasing again
`
`denied. Id. Bird challenged the denial. Id. After a contested hearing, Bird
`
`prevailed, the hearing officer reversed the award and instructed the City to
`
`re-compete the procurement. [A233] It is the subsequently re-issued RFP
`
`that forms the basis for this Petition.
`
`B.
`
`The Re-issued Phase II RFP.
`
`On September 3, 2021, the City re-competed the procurement for
`
`Phase II of the scooter program in the RFP #41100521 for "Shared
`
`Micromobility Program Phase II" as to "Single Rider Vehicles (SRV)" e-
`
`scooters (the "RFP"). [A27-97] The RFP included an addendum issued by
`
`the City on September 30, 2021. [A92-97]
`
`1.
`
`Terms of the Phase II RFP
`
`The RFP provided that the City would select the top two proposals,
`
`based on a numerical scoring system. [A32] According to the RFP, a
`
`"Proposal Evaluation Committee will be established to review and evaluate
`
`all proposals submitted . . . on the basis of the information provided and other
`
`evaluation criteria as set forth in this RFP." [A44] The RFP then provides,
`
`6
`
`

`

`that in the end, "the contract will be awarded to the most qualified Successful
`
`Proposer per the evaluation criteria listed below." Id.
`
`The RFP also allocated twenty percent of the overall scoring to an
`
`evaluation of Women/Minority Business Enterprise ("WMBE") and Small
`
`Local Business Enterprises ("SLBE") participation. Id. The RFP stated
`
`"[d]uring the evaluation of proposals for WMBE and SLBE participation, the
`
`Equal Business Opportunity Office [(the "EBO")] will be responsible for
`
`assigning the points under these criteria." [A45] The RFP did not say that a
`
`single staff person in the EBO would be the exclusive evaluator of the EBO
`
`component. See id.
`
`According to the RFP, "one to fifteen rating points may be awarded
`
`when the Proposer is not a City of Tampa certified WMBE/SLBE prime
`
`contractor but utilizes either Underutilized WMBE and/or SLBE certified
`
`firm(s) as sub-contractors/consultants and assigned to perform meaningful
`
`segments of the contractual services detailed herein and documented on the
`
`enclosed MBD Form 10-20." [A62 (emphasis omitted)] The evaluation of
`
`WMBE/SLBE participation includes, but is not limited to, the following
`
`criteria:
`
`• Diversity of WMBE/SLBE subcontractors listed to be utilized (MBD
`
`Form 20);
`
`7
`
`

`

`• Percentage of proposal/scope committed
`
`to WMBE/SLBE
`
`subcontracting;
`
`• The collective factors in determining the total points awarded will be
`
`based on the overall weight of evidence in the proposal that
`
`specified the participation.
`
`[A63]
`
`The EBO has promulgated at least five forms that are relevant here:
`
`• MBD-10, which shows the extent to which subcontractors are
`
`solicited [A51];
`
`• MBD-20, which shows the extent to which subcontractors have
`
`committed [A53];
`
`• MBD-40, which is a form Letter of Intent that says, "A Letter of
`
`Intent is required for each WMBE/SLBE listed on the Schedule
`
`of Subcontractors to be Utilized (MBD 20 Form)" [A57];
`
`• MBD-70, which contains "Procurement Guidelines to Implement
`
`Minority & Small Business Participation" [A61];
`
`• MBD-71, which contains "EBO Guidelines for Evaluation Points
`
`on RFP and CCNA Proposals" [A62].
`
`8
`
`

`

`2.
`
`DemandStar
`
`The RFP also included references to "DemandStar," an online
`
`contracts administration software platform that the City uses, in part, to
`
`facilitate its RFP processes. [A1579] "DemandStar" allows interested
`
`vendors to become a "Watcher" of an RFP, or download an RFP as a "Plan
`
`Holder." [A1580-81] According to the City, "Watchers" and "Plan Holders"
`
`receive notifications when documents are uploaded to the "DemandStar"
`
`system. Id. It is free to be a "Watcher," but there is a fee to become a "Plan
`
`Holder." Id.
`
`The RFP mentioned the DemandStar platform in Section 7.1, its
`
`general conditions section, as follows:
`
`City of Tampa Request for Proposals are issued electronically
`via DemandStar's eProcurement bid distribution system.
`Obtaining Request for Proposals through Demandstar will
`ensure that vendor will have the following capabilities: receipt of
`Request for Proposals electronically, track the status of award
`activity, receive addenda, be certified as a minority vendor to
`meet the City of Tampa's minority certification requirements,
`receive the results of awards and view plans and blueprints
`online electronically. Vendors who obtain specifications and
`plans from sources other than Demandstar are cautioned that
`the Request for Proposal packages may be incomplete.
`
`[A37] The RFP does not say that being a "Plan Holder" on "DemandStar" is
`
`the only way that proposers may be informed of awards, or that "Watchers"
`
`9
`
`

`

`will not receive the same notifications as "Plan Holders." Section 7.1 of the
`
`RFP does not even mention "Plan Holders."
`
`The RFP again mentions DemandStar in sections 7.2 and 7.3, but only
`
`in the context of addenda to the RFP issued prior to the bid opening date:
`
`If it becomes necessary to review or amend any part of the RFP,
`DemandStar will provide notification of the Addendum to all
`prospective Proposers who received an original RFP from
`DemandStar (Those who are on the Plan Holders List). Addenda
`will be posted and disseminated by DemandStar at least five
`days prior to the bid opening date. . . .
`
`the Proposer to Contact
`the responsibility of
`It will be
`DemandStar prior to submitting a proposal to ascertain if any
`addenda have been issued, to obtain all such addenda, and to
`return the executed addenda with the proposal.
`
`[A37 (emphasis added)]; [A38] The RFP does not make any further mention
`
`of DemandStar, much less state that notices of awards will be exclusively
`
`provided to Plan Holders.
`
`Instead of Bird paying a fee to download the RFP and materials from
`
`DemandStar, Bird received the RFP directly from the City. In fact, the City
`
`directly solicited Bird to apply by sending it the RFP and other materials via
`
`email. [A1418] The City also directly solicited Lime. [A1466] When the City
`
`solicited Bird and Lime, no one at the City told Bird and Lime that they would
`
`not receive a copy of the Notice of Intent to Award unless they paid a fee to
`
`10
`
`

`

`"DemandStar"—and that requirement was certainly not part of the RFP.
`
`[A1418, 1466, 1479-80]
`
`Bird registered to receive alerts in DemandStar as a Watcher. [A1581]
`
`Because Bird did not download the RFP directly from DemandStar, it did not
`
`(and could not) register to receive alerts as a Plan Holder. [A1580-81]
`
`The City continued to send Bird and other applicants communications
`
`via email throughout the RFP process. [A1418, 1466, 1479-80] Among other
`
`things, the City emailed addenda to applicants, and did not provide such
`
`addenda exclusively through DemandStar to listed Plan Holders. Id.
`
`C.
`
`The Notice of Intent to Award.
`
`Bird made a timely and complete proposal, along with six other
`
`competitors, including Spin, Lime, and Helbiz. [A236-1075, 1157-1324]
`
`Eventually, the City "shortlisted" four of the applicants: Bird, Spin,
`
`Lime, and Helbiz. [A1573] The shortlisted applicants were allowed to present
`
`to the City in January 2022. [A1473, 1574]
`
`On March 22, 2022, the City issued a Notice of Intent to Award (the
`
`"Notice of Intent"), reflecting that the City's Director of Purchasing, along
`
`with evaluation committee staff, had recommended to award the RFP to
`
`Helbiz and Spin. [A99] The Notice of Intent stated that any protests were due
`
`11
`
`

`

`by 4:30 PM, five business days after the "first posting" of the Notice of Intent.
`
`Id.
`
`The City distributed the Notice of Intent exclusively to registered Plan
`
`Holders in DemandStar (i.e., Helbiz and Spin). [A1418, 1467, 1479-80, 1579-
`
`80] Those registered as Watchers in DemandStar, including Bird and Lime,
`
`did not receive the Notice of Intent. Id. The Notice of Intent was not sent via
`
`email or any other mode of communication. Id. The City did this despite the
`
`fact that it had communicated with Bird almost exclusively via email
`
`throughout the RFP process, including providing Bird with notices, addenda,
`
`and the RFP itself via email. Id. In effect, the City sent the Notice of Intent
`
`only to the successful proposers.
`
`As a result, Bird never received the Notice of Intent from the City.
`
`[A1418] Lime, the only other unsuccessful shortlisted proposer, likewise
`
`never received the Notice of Intent from the City. [A1467]
`
`It was not until the morning of March 29, 2022, that Bird received a
`
`copy of the Notice of Intent from one of the other applicants. [A1417] The
`
`deadline for bid protests expired that same day at 4:30 PM. [A99]
`
`D. Bird's Bid Protest
`
`Upon receiving the Notice of Intent, Bird quickly requested a five-day
`
`extension of time to file the protest, which the City denied. [A20, 1711] Bird
`
`12
`
`

`

`also
`
`filed a
`
`timely public records request
`
`for all correspondence,
`
`submissions, and scoring information regarding the RFP. [A1138] The City
`
`provided Bird with minimal documents that did not satisfy the scope of Bird's
`
`request. Id.
`
`Within hours, and despite the minimal information provided by the City,
`
`Bird was able to scramble and file a bid protest (the "Bid Protest"). [A18-25]
`
`Lime also received a copy of the Notice of Intent on March 29, 2022, but was
`
`unable to submit a bid protest by the close of business. [A1427]
`
`In its Bid Protest, Bird did the best it could—given the limited time and
`
`information—to raise whatever arguments it could muster; but Bird did not
`
`have the time or information to conduct a detailed analysis. Bird raised the
`
`lack of notice, and argued that several aspects of the process were arbitrary
`
`and capricious. [A18-25] Bird argued that the City's Proposal Evaluation
`
`Committee improperly delegated 20% of the evaluation to a single individual
`
`in the EBO. [A21] Bird also argued that certain scores it received should be
`
`thrown out, as they demonstrated that one of the evaluators was biased,
`
`ostensibly after Bird had pushed back on his solicitations to contribute to a
`
`non-profit. Id. Bird further argued that the City arbitrarily awarded additional
`
`points for certain equipment features (i.e., 12-inch versus 10-inch wheels)
`
`based solely on unattributed opinions that lacked any factual basis, and
`
`13
`
`

`

`failed to award it a fair amount of points for its experience with the pilot
`
`program. [A22] Lastly, Bird argued that the RFP and its addenda were
`
`ambiguous in the qualifying WMBE industry category. Id.
`
`E.
`
`The Bid Protest Denial.
`
`On May 5, 2022, the City's Director of Purchasing, Gregory Spearman,
`
`denied Bird's Bid Protest (the "Bid Protest Denial"). [A1076-81] Mr.
`
`Spearman stated in the Bid Protest Denial that Bird's lack of notice of the
`
`Notice of Intent was Bird's own fault, as it did not follow the instructions in
`
`Section 7.1 of the RFP. [A1077] He rejected Bird's challenge to the
`
`delegation of points to a single individual in the EBO because Bird did not
`
`object to the RFP when it was published, and RFP Section 15.2 stated
`
`generally that EBO would assign those points. [A1078]
`
`Mr. Spearman also rejected Bird's assertion of bias by evaluators for
`
`lack of support, and stated that Bird had waived any challenge to outlier
`
`scores because it did not previously raise the RFP's failure to provide a
`
`method to address such scores. Id. Mr. Spearman incorrectly stated,
`
`however, that Bird "refused to participate in" the Keep Tampa Bay Beautiful
`
`initiative. Id.
`
`He further rejected Bird's challenge to the City's wheel size preference,
`
`and noted that, under RFP Section 7.2, any addenda would control in the
`
`14
`
`

`

`event of a conflict with the RFP itself. [A1079-80] Mr. Spearman generally
`
`stated that Bird's challenges were largely to the specifications of the RFP
`
`itself, and therefore should have been raised when the RFP was published.
`
`[A1081]
`
`That same day, Bird requested an extension of time to file its
`
`administrative appeal with the City, but the City immediately denied the
`
`request. [A1627, 1708]
`
`F. Bird's Public Records Requests to the City.
`
`In support of its bid protest, Bird submitted additional public records
`
`requests to the City, but received either an incomplete response or no
`
`response at all. For example, on May 10, 2022, Bird sent a follow-up request
`
`to the City for all "EBO documents in their possession—particularly any
`
`communications with anyone in the EBO." [A1138] The City responded that
`
`all such documents have been produced, even though it had not yet
`
`produced the email transmitting the EBO scores to the procurement
`
`department. [A1141]
`
`G. Bird's Appeal of the Bid Protest Denial.
`
`On May 10, 2022, Bird timely filed a Request for Appeal with the City,
`
`challenging the Bid Protest Denial (the "Appeal"). [A1-17] In its Appeal, Bird
`
`re-raised the arguments in its Bid Protest, and added further detail and
`
`15
`
`

`

`argument. See [A4-5 (raising lack of notice of the Notice of Intent)]; [A5-6
`
`(raising improper delegation to EBO)]; [A10 (raising ambiguity in the
`
`qualifying WMBE industry category)]; [A10-11 (raising wheel diameter
`
`issue)]. It examined in detail the disproportionate scores exhibiting bias, and
`
`explained how they changed the result. [A6-10]
`
`Bird also raised additional issues related to these arguments. It argued
`
`that the EBO process was flawed as a matter of basic arithmetic, as it
`
`compared percentages calculated using different denominators for each
`
`proposer (an apples to oranges comparison), and ignored RFP directions
`
`regarding "TBD" responses. [A11-13] Bird also argued that only one of the
`
`City evaluators used a detailed scoring rubric, and there was at least one
`
`arithmetic error in the scoring. [A13] Accounting for all of these errors, Bird
`
`should have come in second place. [A16]
`
`Bird further argued that there had been a "cone of silence" violation
`
`(i.e., a prohibited communication with the City during the solicitation period)
`
`when a contractor associated with Spin contacted the City during the
`
`evaluation process (thereby disqualifying Spin from a contract), and that the
`
`City failed to provide timely and complete responses to Bird's public records
`
`requests, hampering Bird's ability to appeal. [A16]
`
`16
`
`

`

`H. Hearing on Bird's Appeal
`
`A City-appointed hearing officer, James Mathieu, Jr., heard Bird's
`
`Appeal on June 9, 2022, (the "Hearing Officer"). The Hearing Officer heard
`
`argument from Bird, Lime, Helbiz and the City, and heard testimony from
`
`several witnesses.
`
`1.
`
`DemandStar and the Notice of Intent to Award
`
`Bruno Lopes, Bird's Government Partnerships Senior Manager for the
`
`Southeast U.S., testified for Bird concerning the City's communications.
`
`[A1417-21] He provided unrebutted testimony that all notices from the City
`
`in this RFP process came by email. Id. He stated that when he came aboard
`
`in March 2022, the "cone of silence" was already in effect, but he was
`
`responsible for monitoring the remainder of the process. [A1421]
`
`Sara Shapiro, Lime's Head of Market Development, testified as Lime's
`
`corporate representative. [A1464] She provided unrebutted testimony that
`
`the City's standard practice in this RFP process had been communication
`
`via e-mail, including the RFP, addenda and all other notices apart from the
`
`Notice of Intent. [A1466-67] She also testified that Lime had no reason to
`
`believe the City would deviate from its established communication method.
`
`Id.; [A1479]
`
`17
`
`

`

`The City argued in response that both Lime and Bird were seeking
`
`"preferential" treatment. [A1536-37] The City referred to Bird's arguments as
`
`not being "in good faith," and "not serious arguments," and stated that Bird
`
`was trying to "forensically engineer a position that would be successful for
`
`them." [A1538, 1542, 1550-52]
`
`Ivette Rosario, a Procurement Analyst with the City, confirmed that
`
`only Plan Holders who downloaded the RFP received Notice of the Intent via
`
`DemandStar. [A1579-80] To become a Plan Holder, proposers had to sign
`
`up with DemandStar and download the RFP as a "Plan Holder," which
`
`required payment of a fee. Id. Monitoring the RFP as a Watcher was free. Id.
`
`When the City checked the DemandStar system, it was able to confirm that
`
`Bird was indeed registered with DemandStar and is on the list to receive all
`
`notifications from the City. [A1581] However, Bird did not download the RFP
`
`in the DemandStar system as a Plan Holder of the RFP document, and
`
`therefore was not registered as a Plan Holder. Id.
`
`2.
`
`Public Records Requests
`
`During the hearing, Bird offered unrebutted evidence of the following
`
`public records requests and responses:
`
`18
`
`

`

`March 29, 2022
`Request to Mr.
`Spearman
`April 13, 2022 Follow
`up to Mr. Spearman
`April 18, 2022 Follow
`up to Mr. Spearman
`April 19, 2022
`Request to Gregory
`Hart
`May 8, 2022 Follow up
`to Mr. Hart
`May 10, 2022 Request
`to Mr. Spearman,
`following up on
`request to Mr. Hart
`May 12, 2022 Request
`to Mr. Spearman
`
`Bird has not received all responsive documents,
`including an email just received this week from
`Lime.
`Bird has not received all responsive documents,
`in spite of the City's assurance that it has.
`Bird has not received all responsive documents,
`in spite of the City's assurance that it has.
`Bird never received a response, not even an
`acknowledgment.
`
`Bird never received a response, not even an
`acknowledgment.
`Bird has not received any documents.
`
`Bird has not received a response.
`
`[A1359] The City offered no evidence or testimony to rebut this.
`
`Ms. Rosario testified that the Evaluation Committee Members were
`
`given two rubrics for evaluating the proposals. There was a scoring sheet
`
`prepared by the City that tracked the RFP categories; and there was another
`
`detailed tabulation sheet created by one of the reviewers, Calvin Thornton.
`
`[A1574] According to Ms. Rosario, the detailed tabulation sheet was created
`
`to help all committee members, but it was not required to be turned in. All
`
`members were required to turn in the form prepared by the City (i.e., not Mr.
`
`Thornton's sheet) to evaluate each proposer. [A1573-74]
`
`19
`
`

`

`3.
`
`EBO Evaluation
`
`Gregory Hart, Managing Director for EBO, testified for the City. [A1584]
`
`He addressed Form MBD-20 and stated that the City took the form into
`
`consideration, although it was not signed, attested, or dated. [A1592]
`
`When questioned about the standards and criteria that Mr. Hart applied
`
`to his evaluation of the proposers' MBD-20s, Mr. Hart testified that he used
`
`his personal experience with the subcontractors to make judgment calls
`
`about how seriously the proposers were taking their obligations. Specifically,
`
`he said:
`
`Q. At its core, is this kind of analysis something that anyone in
`the City can just eyeball?
`
`A. Not at all.
`
`Q. And why is that?
`
`A. That is because you're going to want to know the scope of
`the work to be performed, the firms that are vetted and
`validated as being certified as an underutilized company,
`and their particular primary and secondary trade and
`whether or not it aligns with the contract.
`
`And so, you have to understand underutilization under
`disparity rules and how that proposer is utilizing that firm.
`Are they going to be performing core aspects of the work? Like,
`are they going to do scooter repairs? Are they going to provide
`scooter parts? Or, are they simply being secured as a team
`member to provide janitorial services in the office or a hot dog
`stand on opening day of a new scooter apparatus?
`
`20
`
`

`

`So we look at a number of variables to determine the veracity
`and the meaningfulness of the utilization and does it meet the
`City's objective and requirement to address underutilization.
`
`…
`
`Once again, when looking at the scope of services to be provided
`under the contract and the type of firms that -- subconsultants
`and subcontractors to be utilized, we can easily determine
`whether or not that trade discipline has a substantial or a
`meaningful role, be it on the front end of the contract or not at all.
`
`And so, one can conclude with some sort of factual expertise,
`if you will, whether a firm is going to provide a relevant role in the
`contract because of its discipline and how it's going to be used.
`
`[A1589, 1593] (emphasis added). He said that he cannot train others to do
`
`the evaluation he does. See id. He has to "eyeball" the applications. See id.
`
`He testified that he—and he alone—could "eyeball" the names on the list
`
`and determine how many points should be awarded. See id. He said that he
`
`can look at the type and names of the subcontracting firms and "easily
`
`determine" whether they will have a substantial or meaningful role. See id.
`
`I.
`
`The Denial of Bird's Appeal.
`
`Following the hearing, the parties submitted proposed orders to the
`
`Hearing Officer. [A1599-1689]
`
`The Hearing Officer rendered a final decision affirming the Bid Protest
`
`Denial and denying Bird's Appeal of that decision (the "Denial"). [A1690-
`
`1707] The Hearing Officer declined to consider the bulk of Bird's arguments
`
`21
`
`

`

`as not properly preserved. Specifically, he declined to address any of Bird's
`
`new arguments raised in the Appeal, that were not raised in the Bid Protest.
`
`[A1700, 1707] The Hearing Officer held that Section 2-282 of the City Code
`
`excluded "consideration of any new grounds or evidence not included in the
`
`protest." [A1707] This included Bird's arguments concerning the "cone of
`
`silence" violation, its public records requests, and the flaws in the EBO
`
`scores. [A1705] The Hearing Officer also held that any potential violations of
`
`Florida's public records laws was outside his scope of review. [A1706]
`
`The Hearing Officer further held that Bird had waived its argument
`
`concerning DemandStar and lack of due process, incorrectly suggesting that
`
`it was not raised in the Bid Protest. [A1700]; [A20 (challenging service of the
`
`Notice of Intent through DemandStar as infringing on due process)]
`
`Nonetheless, the Hearing Officer held that the City reasonably exercised its
`
`discretion and "did not lull proposers into inaction." [A1700] He found Ms.
`
`Shapiro's testimony for Lime and Mr. Lopes' testimony for Bird "not
`
`persuasive." Id.
`
`The Hearing Officer did consider some issues. He held that there was
`
`no ambiguity as to the qualifying WMBE industry category: "Question 46 of
`
`Addendum No. 1 . . . modified Section 7.9 of the RFP and MBD Form 71,
`
`and clarified that the underutilized WMBE Industry Category was 'Non-
`
`22
`
`

`

`Professional Services.'" [A1697, 1702] He also rejected Bird's bias
`
`allegations as speculative, and held that Bird had presented no evidence to
`
`the contrary. [A1702]
`
`This timely Petition follows.
`
`I.
`
`STANDARD OF REVIEW.
`
`ARGUMENT
`
`Because Bird is entitled as a matter of right to seek review in this Court
`
`from the City's quasi-judicial administrative action, this Court must determine
`
`whether the City (1) afforded Bird procedural due process, (2) observed the
`
`essential requirements of law, and (3) made a decision supported by
`
`competent substantial evidence. G.B.V. Int'l, 787 So. 2d at 843; Sarasota
`
`Cty. v. BDR Invests., L.L.C., 867 So. 2d 605, 607 (Fla. 2d DCA 2004) (citing
`
`Fla. Power & Light Co., 761 So. 2d at 1092)).
`
`The City's Denial must satisfy all three prongs. See G.B.V. Int'l, 787
`
`So. 2d at 843. In other words, Bird need only show that the City failed on one
`
`of these prongs to be entitled to certiorari relief. As demonstrated below,
`
`however, the City failed on all three.
`
`23
`
`

`

`II.
`
`THE CITY DEPRIVED BIRD OF PROCEDURAL DUE PROCESS BY
`(1) FAILING TO PROVIDE BIRD WITH ADEQUATE NOTICE OF ITS
`NOTICE OF INTENT TO AWARD, AND (2) FAILING TO MAKE A
`TIMELY OR COMPLETE PRODUCTION IN RESPONSE TO BIRDS'
`PUBLIC RECORDS REQUESTS IN SUPPORT OF ITS APPEAL.
`
`Procedural due process requires reasonable notice and a fair
`
`opportunity to be heard. Joshua v. City of Gainesville, 768 So. 2d 432, 438
`
`(Fla. 2000); Housing Authority of the City of Tampa v. Robinson, 464 So. 2d
`
`158, 164 (Fla. 2d DCA 1985). The City afforded Bird neither.
`
`The City chose to send the Notice of Intent in such a way that it was
`
`only received by the winning proposers—Helbiz and Spin. [A A1418, 1467,
`
`1479-80, 1579-80] Then, when the lack of notice to Bird and Lime came to
`
`light, the City denied requests for an extension of time and failed to make a
`
`timely and complete production in response to public record requests. [A20,
`
`1138, 1359, 1708, 1711] Having seriously handicapped Bird's ability to
`
`effectively challenge the City's actions, the City then went one step further
`
`and found that Bird waived any arguments not raised in the Bid Protest,
`
`including arguments based on documents the City had not yet produced
`
`despite Bird's requests.
`
`Taken together, these actions have stymied Bird's ability to make a
`
`substantive bid protest, in violation of Bird's procedural due process rights.
`
`See Richard v. Bank of America, N.A., 258 So. 3d 485, 489 (Fla. 4th DCA
`
`24
`
`

`

`2018) ("Generally due process requires fair notice and a real opportunity to
`
`be heard and defend in an orderly procedure before judgment is rendered")
`
`(citation omitted).
`
`A.
`
`The City Failed to Provide Reasonable Notice of the Notice
`of Intent to Award.
`
`The facts here are undisputed: the Notice of Intent was not sent to Bird.
`
`[A1418, 1467, 1479-80, 1579-80] Not only did Bird not receive notice, the
`
`only other unsuccessful bidder (Lime) also did not receive notice, meaning
`
`that only the RFP winners received notice. Id. And, critically, only the winners
`
`knew tha

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket