`
`UNITED STATES DISTRICT COURT
`EASTERN DISTRICT OF MICHIGAN
`SOUTHERN DIVISION
`
`Plaintiff,
`
`
`IPS Contracting, Inc.,
`
`
`
`
`
`
`v.
`
`
`
`
`Rivian Automotive, LLC,
`
`
`
`
`
`Defendant.
`______________________________/
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`Civil Case No. 21-10983
`
`Sean F. Cox
`United States District Court Judge
`
`OPINION AND ORDER
`GRANTING DEFENDANT’S PARTIAL MOTION TO DISMISS
`
`This is a civil dispute arising out of a demolition contract. Plaintiff, IPS Contracting, alleges
`
`that they are entitled to scrap material, which Defendant, Rivian Automotive, LLC, has failed to
`
`provide them. Plaintiff alleges that Defendant: (1) breached a contractual agreement; (2) was
`
`unjustly enriched; (3) is liable for promissory estoppel; (4) made an innocent misrepresentation;
`
`and (5) is liable for conversion and statutory conversion. (Am. Compl., ECF No. 6, at PageID 38-
`
`45).
`
`Currently, the matter before the Court is Defendant’s Partial Motion to Dismiss (ECF No.
`
`10). The motion has been fully briefed, and the Court concludes that oral argument is not
`
`necessary. Thus, the Court orders that the motions will be decided without a hearing. See E.D.
`
`Mich. LR 7.1(f).
`
`
`
`For the following reasons, the Court GRANTS Defendant’s motion and DISMISSES
`
`Counts II - VI.
`
`
`
`
`
`
`
`1
`
`
`
`Case 2:21-cv-10983-SFC-APP ECF No. 19, PageID.172 Filed 10/22/21 Page 2 of 10
`
`BACKGROUND
`
`
`
`On March 29, 2021, Plaintiff initiated this action against Defendant in Wayne County
`
`Circuit Court. (ECF No. 1-1). Plaintiff alleges the following claims: breach of contract (Count
`
`One); quantum meruit/unjust enrichment (Count Two); promissory estoppel (Count Three);
`
`innocent misrepresentation (Count Four); conversion (Count Five); and statutory conversion
`
`(Count Six). (Am. Compl., at PageID 38-45).
`
`On May 1, 2021, Defendant removed the matter to this Court pursuant to 28 U.S.C. §§
`
`1332(a), 1441, and 1446. (ECF No. 1). On June 29, 2021, Defendant filed a Partial Motion to
`
`Dismiss pursuant to FED. R. CIV. P. 12(b)(6) requesting the Court dismiss Counts II through VI for
`
`failure to state a claim. (ECF No. 10).
`
`
`
`Because this matter comes before the Court on a motion to dismiss the Amended
`
`Complaint, the following allegations in Plaintiff’s Amended Complaint are taken as true. Ashcroft
`
`v. Iqbal, 556 U.S. 662, 678 (2009).
`
`In January 2017, Defendant “purchased a Plant in order to manufacture its new fleet of
`
`electric vehicles.” Id. at ¶ 7. To produce the electric vehicles, Defendant needed to “demolish,
`
`strip-out and massively reconfigure the Plant, which when purchased, had been filled with paint
`
`booths, multiple assembly line conveyors and other equipment . . . .” Id. at ¶ 8.
`
`On January 16, 2019, Plaintiff submitted a bid to perform the demolition work. Id. at ¶ 10.
`
`Plaintiff alleges that the bid not only stated that the total cost would be “$6,596,920” but it also
`
`“expressly stated” that said bid was contingent upon Plaintiff “receiving title to all scrap and
`
`equipment (i.e., robots, conveyors, panels, scrap metal, etc.).” Id.
`
`
`
`2
`
`
`
`Case 2:21-cv-10983-SFC-APP ECF No. 19, PageID.173 Filed 10/22/21 Page 3 of 10
`
`Defendant accepted Plaintiff’s proposal and “issued a purchase order on January 31, 2019,
`
`in the amount of $6,596,920.” Id. at ¶ 18. Throughout the course of the demolition, Defendant
`
`submitted subsequent purchase orders to the Plaintiff. Id. at ¶ 12-13. The “same language”
`
`regarding the scrap equipment was used in each subsequent purchase order. Id. at ¶ 13. Plaintiff
`
`further alleges that “[t]he inclusion of the transfer of title of the scrap and equipment . . . is
`
`significant and was a material component of [Plaintiff’s] bid estimate.” Id. at ¶ 15. Plaintiff alleges
`
`that “the scrap and equipment . . . has a substantial economic value.” Id. at ¶ 16.
`
`Once Plaintiff initiated the demolition work, it:
`began to notice that volume of scrap and equipment it had intended to harvest from
`the Plant was substantially less than expected. For example, thousands of tons of
`copper wire were missing, robots that were intended to be removed by [Plaintiff]
`were not present and air filtering equipment had vanished.
`Id. at ¶ 18. The “scrap and equipment” at issue were allegedly going to be used by Plaintiff to
`
`offset the “costs to perform the work in question.” Id. at ¶ 39. The unexplained removal of the
`
`“scrap and equipment was continuous and systematic throughout the life of the project.” Id. at ¶
`
`19.
`
`When Plaintiff told Defendant about the situation, “Defendant’s . . . representatives
`
`responded . . . with feigned concern, or . . . told [Plaintiff] that Plaintiff was not entitled to the
`
`scrap material and equipment.” Id. at ¶ 20. Plaintiff alleges that they were able to “generate some
`
`revenue from the recovery of scrap and equipment” but “it was millions of dollars less than what
`
`was reasonably anticipated.” Id. at ¶ 21. Furthermore, Plaintiff alleges “that several Rivian
`
`employees working at the Plant were actually stealing the scrap and equipment.” Id. at ¶ 22.
`
`Plaintiff has asked Defendant to be reimbursed “for the value of the scrap, material and equipment
`
`that it was denied as a result of [Plaintiff’s] and its employees’ theft and misappropriation.” Id. at
`
`
`
`3
`
`
`
`Case 2:21-cv-10983-SFC-APP ECF No. 19, PageID.174 Filed 10/22/21 Page 4 of 10
`
`¶ 23. Defendant has refused to reimburse Plaintiff. Id. Plaintiff filed this matter in response. (ECF
`
`No. 1).
`
`STANDARD OF REVIEW
`
`
`
`A motion to dismiss tests the legal sufficiency of the plaintiff’s complaint. To survive a
`
`motion to dismiss, the complaint must state sufficient “facts to state a claim to relief that is
`
`plausible on its face.” Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 570 (2007). Claims comprised
`
`of “labels and conclusions, and a formulaic recitation of the elements of a cause of action will not
`
`do.” Id. at 555. “A claim has facial plausibility when the plaintiff pleads factual content that allows
`
`the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.”
`
`Ashcroft v. Iqbal, 556 U.S. 662 (2009).
`
`
`
`Although the Court must accept all well-pleaded factual allegations as true for purposes of
`
`a motion to dismiss, the Court is “not bound to accept as true a legal conclusion couched as a
`
`factual allegation.” Twombly, 550 U.S. at 555. Thus, to avoid dismissal, “a complaint must contain
`
`sufficient factual matter,” accepted as true, to state a claim for relief that is plausible on its face.
`
`Id. at 678. In practice, a complaint must contain either direct or inferential allegations respecting
`
`all the material elements to sustain recovery under some viable legal theory. Lillard v. Shelby
`
`County Bd. of Educ., 76 F.3d 716, 726 (6th Cir. 1996).
`
`
`
`“A complaint should not be dismissed for failure to state a claim unless it appears beyond
`
`doubt that the plaintiff can prove no set of facts in support of his claim which would entitle him to
`
`relief.” Mayer v. Mylod, 988 F.2d 635, 638 (6th Cir. 1993). “The fundamental purpose of pleadings
`
`under the Federal Rules of Civil Procedure is to give adequate notice to the parties of each side’s
`
`
`
`4
`
`
`
`Case 2:21-cv-10983-SFC-APP ECF No. 19, PageID.175 Filed 10/22/21 Page 5 of 10
`
`claims and to allow cases to be decided on the merits after an adequate development of the facts.”
`
`Id.
`
`
`
`“When a court is presented with a Rule 12(b)(6) motion, it may consider the Complaint
`
`and any exhibits attached thereto, public records, items appearing in the record of the case and
`
`exhibits attached to defendant’s motion to dismiss so long as they are referred to in the Complaint
`
`and are central to the claims contained therein.” Weiner v. Klais & Co., 108 F.3d 86, 89 (6th Cir.
`
`1997).
`
`ANALYSIS
`
`Because this Court sits in diversity, the substantive law of Michigan governs the claims of
`
`in this case. Armisted v. State Farm Mut. Auto. Ins. Co., 675 F.3d 989, 995 (6th Cir. 2012).
`
`Defendant argues that Plaintiff’s allegations (Counts II-VI) should be dismissed because
`
`Plaintiff has failed to state plausible claims for: (1) unjust enrichment/quantum meruit; (2)
`
`promissory estoppel; (3) innocent misrepresentation; (4) statutory conversion; and (5) conversion.
`
`(Def’s Br., at PageID.81). The Court will address each claim in turn.
`
`I. Unjust Enrichment/Quantum Meruit (Count II)
`
`
`
`In Count II, Plaintiff alleges a quantum meruit/unjust enrichment claim, in the alternative
`
`to its breach of contract claim in Count I pursuant to FED. R. CIV. P. 8(d).
`
`For a plaintiff to succeed on an unjust enrichment claim, a plaintiff must show that there
`
`was (1) “receipt of a benefit by the defendant from the plaintiff” and (2) “an inequity resulting to
`
`plaintiff because of the retention of the benefit by defendant.” Barber v. SMH (US), Inc., 509
`
`N.W.2d 791, 796 (Mich. App. 1993). If the elements of unjust enrichment are met, the court will
`
`“imply a contract in order to prevent unjust enrichment.” Id. “However, a contract will be implied
`
`
`
`5
`
`
`
`Case 2:21-cv-10983-SFC-APP ECF No. 19, PageID.176 Filed 10/22/21 Page 6 of 10
`
`only if there is no express contract covering the same subject matter. Id. See also Martin v. East
`
`Lansing School Dist., 483 N.W.2d 656, 658 (Mich. App. 1992).
`
`“Alternatively pleading an express contract and implied contract (whether styled as unjust
`
`enrichment or quantum meruit) is allowed when, for instance, there is a dispute between the parties
`
`as to whether an express agreement exists.” Llwellyn-Jones v. Metro Property Group, LLC, 22 F.
`
`Supp. 3d 760, 793 (E.D. Mich. 2014) (citing Cascade Elec. Co. v. Rice, 70 Mich. App. 420, 426-
`
`27 (1976)). “A party is not required to elect to proceed under one theory or the other, but could
`
`seek recovery on the basis either of an express contract, or an implied contract if the trier of fact
`
`found that the express contract did not exist.” Id. Additionally, “the plaintiff also may bring a
`
`breach of contract claim and an unjust enrichment claim in cases where the defendant has ‘kept its
`
`options open, and may deny the existence of the contract.’” Id. (citing Terry Barr Sales Agency,
`
`Inc. v. All-Lock Co., Inc., 96 F.3d 174, 182 (6th Cir. 1996)).
`
`Here, this is not the case. Plaintiff concedes that there is an express agreement that governs
`
`the subject matter in question: “the parties acknowledge the existence of the Demolition Purchase
`
`Agreements, the claim asserted by [Plaintiff] is for the value of the scrap and equipment that it was
`
`to receive as part of its work.” (Pl’s Br., at PageID 134). Therefore, Plaintiff’s unjust
`
`enrichment/quantum meruit claim must be dismissed. “If the parties admit that a contract exists,
`
`but dispute its terms or effect, an action will not also lie for quantum meruit or implied contract.
`
`In other words, alternative pleading of an implied contract claim is only allowed in a contract
`
`setting where a party doubts the existence of a contract.” Advanced Plastics Corp. v. White Consol.
`
`Indus., Inc., 828 F. Supp. 484, 491 (E.D.Mich.1993) (citations omitted).
`
`Plaintiff tries to rely on Son v. Coal Equity, Inc., 122 Fed. App’x 797, 802 (6th Cir. 2004)
`
`to argue that “the course of litigation is unpredictable” and therefore Plaintiff should be allowed
`
`
`
`6
`
`
`
`Case 2:21-cv-10983-SFC-APP ECF No. 19, PageID.177 Filed 10/22/21 Page 7 of 10
`
`to plead both breach of contract and quantum meruit claims. (Pl’s Br., at PageID 135-136).
`
`However, in Son, the facts surrounding the contractual dispute were very different than those at
`
`issue here. Id. In Son, there was an issue as to whether plaintiff was a third-party beneficiary on
`
`the contract. Id. The plaintiff in Son pled both a breach of contract claim and a quantum meriut
`
`claim in the alternative, if it was found that plaintiff was not a third-party beneficiary. Id. The Sixth
`
`Circuit permitted the plaintiff to plead both claims because it acknowledged that the defendant
`
`may later repudiate its concession on the issue. Id. There is no such dispute here. Both parties agree
`
`that Plaintiff and Defendant are parties to the contract and that the contract covers the subject
`
`matter of the dispute.
`
`Therefore, the Court GRANTS Defendant’s motion as to the quantum meruit/unjust
`
`enrichment claim and DISMISSES Count II of the Amended Complaint.
`
`II. Promissory Estoppel (Count III)
`
`
`
`For a defendant to be found liable for promissory estoppel, there must be “a promise that
`
`the promisor should have reasonably expected to induce action . . . on the part of the promisee . . .
`
`which in fact produces reliance . . . under circumstances such that the promise must be enforced if
`
`injustice is to be avoided.” Barber v. SMH (US), Inc., 509 N.W.2d 791, 797 (Mich. App. 1993).
`
`However, “where ... the performance which is said to satisfy the detrimental reliance requirement
`
`of the promissory estoppel theory is the same performance which represents consideration for the
`
`written contract, the doctrine of promissory estoppel is not applicable.” Gen. Aviation, Inc. v.
`
`Cessna Aircraft Co., 915 F.2d 1038, 1042 (6th Cir. 1990).
`
`
`
`In this case, Plaintiff claims to have detrimentally relied on a promise made by Defendant.
`
`(Am. Comp. at PageID 41-42). Here, Defendant promised to transfer title of the scrap material in
`
`question to Plaintiff in exchange for the completion of the demolition work. (Am. Comp. at PageID
`
`
`
`7
`
`
`
`Case 2:21-cv-10983-SFC-APP ECF No. 19, PageID.178 Filed 10/22/21 Page 8 of 10
`
`41). At a glance, Plaintiff’s promissory estoppel claim appears valid: Defendant did promise to
`
`transfer title of the scrap material in question to the Plaintiff, and Plaintiff did rely on that promise
`
`when Plaintiff began the demolition work. Id. However, the performance of the demolition work
`
`represents the consideration written in the express agreements between Plaintiff and Defendant:
`
`“[Defendant] represented and promised that it would pay [Plaintiff] for the labor and materials
`
`utilized in the demolition component of the work Plaintiff performed at the Plant.” (Am. Compl.
`
`at PageID 41). Therefore, the doctrine promissory estoppel is not applicable in this matter. Gen.
`
`Aviation, Inc., 915 F.2d at 1042.
`
`Therefore, the Court GRANTS Defendant’s motion as to the promissory estoppel claim
`
`and DISMISSES Count III of the Amended Complaint.
`
`III. Innocent Misrepresentation (Count IV)
`
`
`
`“A claim of innocent misrepresentation is shown if a party detrimentally relies upon a false
`
`representation in such a manner that the injury suffered by that party injures to the benefit of the
`
`party who made the representation.” Unibar Maint. Serv., Inc. v. Saigh, 283 Mich. App. 609, 769
`
`N.W.2d 911 (Mich. Ct. App. 2009). A party alleging innocent misrepresentation “is not required
`
`to prove that the party making the misrepresentation intended to deceive or that the other party
`
`knew it was false.” M&D, Inc. v. W.B. McConkey, 231 Mich. App. 22, 28 (1989) (citing United
`
`States Fidelity & Guaranty Co. v. Black, 412 Mich. 99, 118 (1981)). “In order to prevail on an
`
`innocent misrepresentation claim, a plaintiff must also show that the plaintiff and defendant were
`
`in privity of contract.” M&D, 231 Mich. App. at 28. “The misrepresentation must relate to a past
`
`or existing fact and not be promissory in nature.” Derderian v. Genesys Health Care Sys., 689
`
`N.W.2d 145, 157 (Mich. App. 2004).
`
`Here, Plaintiff alleges that Defendant made a false statement of fact when Defendant
`
`
`
`8
`
`
`
`Case 2:21-cv-10983-SFC-APP ECF No. 19, PageID.179 Filed 10/22/21 Page 9 of 10
`
`“represented to [Plaintiff] that it would be paid in full, or in the alternative, that [Plaintiff] would
`
`be entitled to receive possession and title to all of the scrap and equipment . . . .” (Am. Comp. at
`
`PageID.42). Plaintiff goes on to allege that this false statement caused Plaintiff to enter into the
`
`agreement at their detriment. Id. This representation refers to a future act (compensating Plaintiff)
`
`that Defendant promised Plaintiff they would do. Therefore, the alleged false statement is
`
`“promissory in nature” and Plaintiff has failed to state a claim of innocent misrepresentation.
`
`Derderian, 689 N.W.2d at 157.
`
`Therefore, the Court GRANTS Defendant’s motion as to the innocent misrepresentation
`
`claim and DISMISSES Count IV of the Amended Complaint.
`
`IV. Statutory Conversion/Conversion (Count V and VI)
`
`
`
`Conversion is “any distinct act of dominion wrongfully exerted over another's personal
`
`property in denial of or inconsistent with his rights therein.” Aroma Wines & Equip, Inc. v.
`
`Columbian Distrib. Services, Inc., 871 N.W.2d 136, 141 (Mich. 2015). Moreover, statutory
`
`conversion is “[a]nother person’s stealing or embezzling property or converting property to the
`
`other person’s own use.” M.C.L. § 600.2919a.
`
`A conversion claim “cannot be brought where the property rights alleged to have been
`
`converted arises entirely from the [plaintiff's] contractual rights.” CH Novi, LLC v. Sun Valley,
`
`Ltd., 16-10297, 2016 WL 1732747, at *2 (E.D. Mich., May 2, 2016). However, it “is possible for
`
`a party’s conduct to result in both a breach of contract and a tort for common law conversion[,] so
`
`long as the defendant’s conduct constituted a breach of duty separate and distinct from the breach
`
`of contract.” Id.
`
`
`
`In this case, Plaintiff alleges that Defendant took “wrongful dominion and control” over
`
`the scrap material in question. (Am. Comp. at PageID.44). However, Plaintiff’s rights to the scrap
`
`
`
`9
`
`
`
`Case 2:21-cv-10983-SFC-APP ECF No. 19, PageID.180 Filed 10/22/21 Page 10 of 10
`
`material in question arise only out of Plaintiff’s contractual rights. Furthermore, besides the
`
`contractual duty Defendant had to plaintiff, Plaintiff’s Amended Complaint does not allege any
`
`other separate and distinct duty between Plaintiff and Defendant. (Am. Comp. at PageID.33-46).
`
`“The law in Michigan is well-settled that an action in tort requires a breach of duty separate and
`
`distinct from a breach of contract.” Brock v. Consol. Biomedical Laboratories, 817 F.2d 24, 25
`
`(6th Cir. 1987). Given that Defendant has no separate and distinct duty, outside of the contractual
`
`duty, to transfer title of the scrap material to Plaintiff, Plaintiff has failed to state a conversion
`
`claim.
`
`
`
`Therefore, the Court GRANTS Defendant’s motion as to the conversion claims and
`
`DISMISSES Counts V and VI of the Amended Complaint.
`
`CONCLUSION
`
`
`
`For the reasons outlined above, the Court GRANTS Defendant’s Partial Motion to Dismiss
`
`and DISMISSES Counts II-VI of the Amended Complaint.
`
`IT IS SO ORDERED.
`
`
`
`
`Dated: October 22, 2021
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`s/Sean F. Cox
`Sean F. Cox
`U. S. District Judge
`
`
`
`
`
`
`
`
`
`10
`
`