throbber
Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 1 of 60
`
`IN THE UNITED STATES DISTRICT COURT
`FOR THE DISTRICT OF MONTANA
`HELENA DIVISION
`
`
`ASARCO LLC, a Delaware
`Corporation,
`
`Plaintiff,
`
`v.
`ATLANTIC RICHFIELD
`COMPANY, a Delaware Corporation,
`
`Defendant.
`
`
`
`CV 12–53–H–DLC
`
`FINDINGS OF FACT,
`CONCLUSIONS OF LAW, and
`JUDGMENT
`
`
`
`
`INTRODUCTION
`
`As summarized in the November 19, 2020 Order (Doc. 324) and otherwise
`
`discussed extensively throughout the nine-year life of this case, Plaintiff ASARCO
`
`LLC (“ASARCO”) and Defendant Atlantic Richfield Company’s (“Atlantic
`
`Richfield”)1 smelting and fuming activities in East Helena, Montana (the “Site”)
`
`caused arsenic contamination to the groundwater. 2 (Doc. 269 at 28, 53.) In 2009,
`
`ASARCO entered into complimentary settlement agreements and consent decrees
`
`with the United States and State of Montana to resolve its outstanding
`
`
`1 Atlantic Richfield is the successor in interest to Anaconda Mining Company (“Anaconda”),
`which leased a portion of the East Helena Site from ASARCO and operated a zinc fuming plant
`there from 1927 to 1972. See, e.g., ASARCO LLC v. Atlantic Richfield Company, LLC, 975 F.3d
`859, 862–63 (9th Cir. 2020) (“ASARCO II”).
`2 The Site is designated as a National Priorities List or “Superfund” site. 42 U.S.C. § 9605.
`
`-1-
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 2 of 60
`
`environmental liabilities at various Montana sites, including the Site at East
`
`Helena. ASARCO II, 975 F.3d at 863.
`
`Relevant here, the consent decree between ASARCO and the United States
`
`(the “Decree”) established a custodial trust to fund the cleanup of several
`
`contaminated sites, with the Montana Environmental Trust Group (“METG”) as
`
`the custodial trustee and the Environmental Protection Agency (“EPA”) as the lead
`
`agent for the East Helena Site. Id. Pursuant to the Decree, ASARCO paid $111.4
`
`million3 into the trust for Site cleanup, “accounting for comprehensive damage
`
`done to the Site by all responsible parties.” Id. (See also Doc. 269 at 78); and see
`
`ASARCO LLC v. Atlantic Richfield Co., 866 F.3d 1108, 1115 (9th Cir. 2017)
`
`(“ASARCO I”).
`
`In 2012, ASARCO brought a contribution action under CERCLA4 §§ 107
`
`and 113(f)(3)(B) against Atlantic Richfield. (See generally Doc. 28.) Specifically,
`
`ASARCO sought to hold Atlantic Richfield liable for its equitable share of the
`
`costs that had been incurred for response action at the Site. (Doc. 28 at 2.) After
`
`
`3 Of this amount, $99.294 million was paid for a groundwater remedy to clean up the off-Site
`groundwater; $8.9 million covered costs to “establish the Custodial Trust and to fund the
`Custodial Administrative Account for the purposes of administration of the Custodial Trust, of
`which the proportionate share for the East Helena Site would be $6,403,743”; $706,000 funded
`the United States Department of the Interior natural resource restoration and future oversight
`costs for the Site; and $5 million was allocated to the State of Montana for the Site in
`compensatory natural resource damages. (Doc. 269 at 16–17.)
`4 Comprehensive Environmental Response, Compensation, and Liability Act of 1980, 42 U.S.C.
`§§ 9601–9675.
`
`-2-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 3 of 60
`
`an eight-day bench trial in 2018, the Court first determined that ASARCO
`
`“incurred $111,403,743 in response costs” within the meaning of CERCLA
`
`§ 107—the full amount paid by ASARCO in connection with the Decree. (Doc.
`
`269 at 82.) Second, the Court found Atlantic Richfield responsible for twenty-five
`
`percent of those incurred response costs, i.e., $27,850,936. (Id. at 88.)
`
`On appeal, the Ninth Circuit concluded that the expert testimony ASARCO
`
`proffered—and which the Court found most persuasive—was “steeped in
`
`speculation” and thus insufficient to support finding the full $111.4 million
`
`settlement amount eligible for contribution. ASARCO II, 975 F.3d at 867–68. That
`
`is, ASARCO’s evidence failed to show that the full settlement amount represents
`
`necessary response costs “incurred” at the Site. See id. at 866 (emphasis added).
`
`The appellate court found no error, however, in this Court’s “devising an equitable
`
`allocation of liability for Site cleanup” by pegging Atlantic Richfield’s
`
`responsibility at twenty-five percent of the response costs actually incurred at the
`
`Site. Id. at 868.
`
`Accordingly, this case returned from the Ninth Circuit with the mandate that
`
`the Court “further consider[] [] what necessary response costs were actually
`
`incurred within the meaning of CERCLA.” Id. Atlantic Richfield immediately
`
`moved the Court to enter a final judgment allocating $48.5 million as the amount
`
`-3-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 4 of 60
`
`incurred, based on ASARCO’s “pleadings, the evidence it presented at trial, and
`
`the Court of Appeals’ ruling[.]” (Doc. 314 at 2.) Applying the rule of mandate,
`
`the Court denied the motion. (Docs. 314 at 2; 324 at 10–13.) At the same time,
`
`the Court granted ASARCO’s motion for leave to supplement and amend the First
`
`Amended Complaint. (Docs. 316 at 7; 324 at 13–23.) Consequently, ASARCO’s
`
`prayer for relief would now include (1) contribution on all costs “incurred” since
`
`the 2018 bench trial; and (2) declaratory relief pursuant to 42 U.S.C. § 9613(g)(2)
`
`to recover contribution for future costs when they are actually “incurred.’” (Docs.
`
`324 at 23; 325 at 10–11.) 5
`
`The Court set the matter for an evidentiary hearing on February 4 and 5,
`
`2021 to consider what costs have actually been “incurred” at the Site and are
`
`eligible for contribution. (Doc. 324 at 24–25.) Gregory Evans, Kris McLean, and
`
`Rachel H. Parkin represented ASARCO. Randy Cox, Benjamin Strawn, and
`
`Kenzo Kawanabe represented Atlantic Richfield. The Court admitted about 43
`
`exhibits and heard testimony from three witnesses: Margaret Staub for ASARCO,
`
`and Donald G. Booth and Jennifer E. Roberts for Atlantic Richfield.
`
`Based on the evidence and testimony presented at the post-remand hearing,
`
`
`5 At the post-remand evidentiary hearing, Atlantic Richfield renewed its objection to ASARCO’s
`motion to amend and supplement its Amended Complaint, which the Court overruled for the
`same reasons given in its November 19, 2020 Order. (See Doc. 324 at 23; Hr’g Tr. vol. 1, 10:8–
`22 (Feb. 4, 2021).)
`
`-4-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 5 of 60
`
`and further considering the applicable law and the arguments made at the hearing
`
`and in the parties’ written submissions, the Court makes the following findings of
`
`fact and conclusions of law pursuant to Federal Rule of Civil Procedure 52.
`
`FINDINGS OF FACT
`
`
`Relevant Background6
`
`
`I.
`
`1. While METG serves as trustee of and acts as a fiduciary for the
`
`custodial trust established pursuant to the Decree, the EPA is the lead agent for
`
`cleanup activities at the Site. As lead agent, the EPA is charged with selecting,
`
`approving, and authorizing all work performed and funds expended by METG
`
`from the custodial trust cleanup account for the Site.7
`
`
`
`2.
`
`Since 2009, METG has used money ASARCO paid into the trust to
`
`fund a series of environmental actions intended to address and remediate
`
`contaminated groundwater at the Site. METG’s Site activity is the focus of any
`
`potential allocation responsibility because it is the work being funded by
`
`ASARCO. ASARCO seeks no contribution for any work it performed at the Site.8
`
`
`6 The Court incorporates by reference, as though fully set forth herein, the facts it previously
`found following the 2018 bench trial that formed neither the basis of Atlantic Richfield’s appeal
`nor the Ninth Circuit’s opinion and mandate. (See Docs. 269 at 2–25; 353 at 10 (Atlantic
`Richfield’s suggestion that “[w]here necessary to establish the foundation for additional findings
`reached after the Post-Remand hearing, the Court [may] include[] here many of its previous
`findings based on the evidence at the May/June 2018 trial”).)
`7 Ex. 570 at 8.
`8 Doc. 269 at 21–22.
`
`-5-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 6 of 60
`
`II.
`
`Stipulated Expenditures
`
`3.
`
`Prior to the evidentiary hearing, ASARCO and Atlantic Richfield
`
`stipulated that pursuant to EPA selection, approval, and authorization, METG has
`
`expended the following amounts from the trust account to remediate the Site:
`
`• 2010: $2,899,126;
`• 2011: $3,391,552;
`• 2012: $5,931,873;
`• 2013: $12,417,138;
`• 2014: $7,900,643;
`• 2015: $11,509,178;
`• 2016: $12,678,441;
`• 2017: $1,464,955;
`• 2018: $843,715;
`• 2019: $1,378,766;
`• 2020 (through third quarter): $934,971.9
`
`4.
`
`The Decree allowed that ASARCO could obtain a credit for work it
`
`
`
`performed between February 2009 and the date of the trust account’s funding.
`
`Indeed, ASARCO received such a credit in the amount of $2,959,775.10 While
`
`ASARCO initially urged that this amount, too, constituted a cost eligible for
`
`contribution, it abandoned this argument at the post-remand evidentiary hearing.11
`
`
`9 Doc. 327. The Court recognizes that the sum of these expenditures totals $61,350,358—one
`dollar less than the total amount to which the parties stipulated at the hearing and in their
`respective proposed findings of fact. (See Docs. 353 at 35; 353 at 21.) However, because the
`parties agree, the Court does not disturb the total stipulated amount based on an apparent clerical
`error.
`10 Ex. 403.
`11 Hr’g Tr. vol 2, 348:25–349:11 (Feb. 5, 2021).
`-6-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 7 of 60
`
`5.
`
`ASARCO also paid $8,888,114 (after an $11,885.27 credit against the
`
`funds the Decree obligated it to pay) to “establish a Custodial Trust and to fund the
`
`Custodial Administrative Account for the purposes of administration of the
`
`Custodial Trust.” This administrative expenditure covered various Montana
`
`sites.12 While it initially argued for contribution against this outlay, ASARCO also
`
`abandoned this argument at the post-remand evidentiary hearing.13
`
`6.
`
`ASARCO also paid $5,706,000 for natural resource damages.14
`
`ASARCO presented no evidence or argument related to recovering contribution for
`
`these damages.
`
`7.
`
`Thus, the parties agree that METG has thus far spent $61,350,359
`
`through the custodial trust account for remediation work performed at the Site.15
`
`III. Selection of the Final Remedy
`
`8.
`
`In addition to remediation costs undisputedly expended by METG
`
`before and since the 2018 trial, supra, the parties also agree that the administrative
`
`process has progressed. Specifically, at the time of trial, METG—at the direction
`
`of the EPA— had recently issued its Former ASARCO East Helena Facility
`
`Corrective Measures Study Report (“2018 CMS Report”). However, the 2018
`
`
`
`12 Ex. 403 at 1.
`13 Hr’g Tr. vol. 2, 348:14–24.
`14 Doc. 269 at 17.
`15 Hr’g Tr. vol. 2, 349:19–23, 366:10–13.
`
`-7-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 8 of 60
`
`CMS Report only existed then in draft form and the EPA had not yet approved it or
`
`selected any remedies from it.16
`
`9.
`
`In general, the purpose of a corrective measures study report is to
`
`investigate and evaluate alternative remedies to protect human health and the
`
`environment from hazardous releases at a Superfund site and to restore
`
`contaminated media to EPA-approved standards.17
`
`10. Such is the case here. In the 2018 CMS Report, METG described “the
`
`process by which remedial action alternatives were developed and evaluated in
`
`order to identify a recommended alternative for addressing soil, groundwater,
`
`surface water, and sediment” contamination at the Site.18
`
`11. Evaluating alternative methods in the 2018 CMS Report, METG
`
`specifically analyzed: (1) long-term effectiveness and permanence; (2) toxicity,
`
`mobility and volume reduction; (3) short-term effectiveness; (4) implementability;
`
`(5) cost; (6) community acceptance; and (7) State acceptance.19
`
`12.
`
`In July 2020—more than two years after trial—the EPA conditionally
`
`approved the 2018 CMS Report. 20 In its Statement of Basis for Groundwater,
`
`
`
`16 Hr’g Tr. vol. 1, 36:11–15.
`17 Ex. 976 at 13; Hr’g Tr. vol 1, 36:11–15, 37:14.
`18 Ex. 976 at 13.
`19 Id. at 11.
`20 METG satisfied the conditions required for final approval in an October 8, 2020 addendum
`letter. Ex. 1001 at 1.
`
`-8-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 9 of 60
`
`Surface Water and Soil Corrective Measures (Remedy) Decision at Former
`
`ASARCO East Helena Facility (“Statement of Basis”), the EPA selected from the
`
`remedies described and evaluated in the 2018 CMS Report and identified those
`
`remedies that will serve as the final remedies (collectively, “Final Remedy”) for
`
`the Site.21
`
`13. The Statement of Basis outlines the EPA’s reasoning for this selection,
`
`explaining that the Final Remedy consists of “multiple elements that work together
`
`to protect human health and the environment.”22
`
`14. The Statement of Basis further establishes that, based upon “the
`
`review of the [2018 CMS Report], knowledge of the remedial activities that have
`
`been implemented, and understanding of the contamination present at the [Site],
`
`[the EPA] has concluded that the remedies recommended by [METG] will meet
`
`the cleanup objectives for the Site.”23
`
`15. As part of the Final Remedy, the EPA selected a combination of
`
`interim measures (“IMs”) which have already been implemented, including an
`
`Evapotranspiration Cover, South Plant Hydraulic Controls, Source Removal and
`
`Corrective Management Units, Speiss-Dross Slurry Wall, and Institutional
`
`
`
`21 Ex. 570 at 7, 9.
`22 Id. at 9.
`23 Id. at 9.
`
`-9-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 10 of 60
`
`Controls, and also selected an additional remedy for the slag pile. The Statement
`
`of Basis further provides for ongoing Performance Monitoring and Operations &
`
`Maintenance.24
`
`16. The Statement of Basis is in its final form. The EPA presented to the
`
`public the Final Remedy it selected via the Statement of Basis during a meeting on
`
`December 8, 2020.25
`
`17.
`
`In October 2020, METG released the Former ASARCO East Helena
`
`Facility Corrective Measures Implementation Work Plan (“Work Plan”) in
`
`response to the EPA’s Statement of Basis. The Work Plan was “developed to
`
`implement the decisions set forth and supported in the [Statement of Basis]” and is
`
`intended to “detail all work and related requirements and schedules for the timely
`
`implementation and completion of such corrective action measures.”26
`
`18. The Work Plan “outlines [METG’s] plan to design, construct, operate
`
`monitor, and maintain the final corrective measures” for the Site.27
`
`19. Together, METG’s 2018 CMS Report, the EPA’s Statement of Basis,
`
`and METG’s Work Plan outline the Final Remedy to be implemented for the Site,
`
`identifies costs associated with the implementation of the Final Remedy, and
`
`
`
`24 Id. at 9–10.
`25 Hr’g Tr., vol. 1, 48:21–49–1; Ex. 570 at 1; Ex. 576 at 1.
`26 Hr’g Tr., vol. 1, 39:2–6; Ex. 571 at 8.
`27 Ex. 571 at 8.
`
`-10-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 11 of 60
`
`establishes that the Final Remedy will be protective of human health and the
`
`environment.28
`
`20. At the post-remand hearing, Ms. Staub explained that the Final
`
`Remedy is comprised of “four key elements that are still going to be ongoing.” 29
`
`The Court makes its findings on each element, in turn, below.
`
`A.
`
`Slag Pile
`
`21. The slag pile covers approximately 45 acres, is 120 feet tall at its
`
`highest point, and contains approximately 3,560,000 cubic yards of slag.30 It
`
`continues to be a major source of remaining arsenic contamination to
`
`groundwater.31
`
`22. METG noted in the 2018 CMS Report that the pile “consists of two
`
`types of slag, fumed and unfumed slag, that are generally segregated in the pile due
`
`to the distinct production and disposal time periods. . . . [T]he unfumed slag
`
`contains higher metals concentrations than the fumed slag.” As such, METG
`
`concluded, the unfumed slag “has the higher potential to leach [metals] to
`
`groundwater,” and is therefore “considered the likely source of contaminants
`
`
`28 Hr’g Tr. vol. 1, 38:7–11, 87:19–23; Ex. 570 at 9–10, 85.
`29 Hr’g. Tr. vol. 1, 48:2–17.
`30 Ex. 976 at 51.
`31 Ex. 573 at 1.
`
`-11-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 12 of 60
`
`entering the groundwater beneath the slag pile.”32
`
`23. Although Mr. Booth opined that a remedy for the slag pile is driven
`
`primarily by selenium loading, with the upper lift of unfumed slag on the pile
`
`representing about 75% of remaining selenium in the groundwater,33 Ms. Staub
`
`countered that the slag pile is an ongoing source of both selenium and arsenic to
`
`the groundwater.34
`
`24.
`
`Indeed, the EPA identified arsenic as a driver of the slag pile remedy,
`
`stating in a Fact Sheet released to the public in October 2020 that: “After the
`
`[F]inal [R]emedy is completed—re-grading and capping the ASARCO slag pile to
`
`minimize the last major source of arsenic contamination to the groundwater—
`
`METG will continue to monitor groundwater conditions to make sure that cleanup
`
`goals are being achieved.”35
`
`25. The EPA also noted in this Fact Sheet that “METG recently submitted
`
`[the Work Plan] to EPA outlining its proposal to regrade and cap the ASARCO
`
`slag pile to prevent arsenic (and selenium) from leaching into the groundwater in
`
`East Helena.”36
`
`
`
`32 Ex. 976 at 51.
`33 Ex. 576 at 28; H’rg Tr. vol. 2 at 297:20–599:3.
`34 Hr’g Tr. vol. 1 at 199:16–19.
`35 Ex. 573 at 1.
`36 Ex. 573 at 2; Ex. 571 at 1.
`
`-12-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 13 of 60
`
`26. METG generated and the EPA considered three different slag pile
`
`cover alternatives in the 2018 CMS Report—minimum, medium, and maximum.
`
`For each alternative, METG calculated associated costs, including site demolition,
`
`waste disposal, slag grading, cover soils, Evapotranspiration cover, hydroseeding,
`
`and site preparation costs like mobilization, permitting, stormwater controls, and
`
`closing out the project.37 Using its prior experience and knowledge of past
`
`remediation expenditures at the Site, METG calculated the minimum alternative
`
`for the slag pile cover at $4,536,000, the intermediate alternative at $8,063,000,
`
`and the maximum alternative at $9,863,000.38
`
`27. Ultimately, however, EPA did not select any of the three alternatives
`
`identified in the 2018 CMS Report, and instead—along with METG—successfully
`
`negotiated a deal with a third-party metals broker to remove about 2 million tons of
`
`unfumed slag from the surface layer of the pile.
`
`28. Then, once the broker hauls that material offsite, the Final Remedy
`
`calls for regrading the remaining slag pile—comprised of fumed slag and older
`
`unfumed slag—and capping it with a soil and vegetative cover.39 Because the slag
`
`remaining onsite after the upper lift of unfumed slag is removed will still be
`
`
`37 Ex. 583 at 53–55; Hr’g Tr. vol. 1, 54:19–23.
`38 Hr’g Tr. vol. 1, 58:6–9; Ex. 583 at 53–55.
`39 Ex. 570 at 22, 38; Ex. 576 at 26; Ex. 1027 at 59; Hr’g Tr. vol. 1, 49:9–14; Hr’g Tr. vol. 2,
`292:6–14.
`
`-13-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 14 of 60
`
`regraded and fully covered by a vegetative cover, the evidence that the fumed slag
`
`remains a source of arsenic and other contaminants that will continue to require
`
`corrective measures is underscored.40
`
`29. The Work Plan accounts for EPA’s chosen final remedy as it relates to
`
`the slag pile, calculating a total cost of $7,660,000, which includes both design and
`
`construction expenses.41 Ms. Staub testified that, “by selecting the final remedy
`
`[for the slag pile], [the EPA] committed to costs to implement the remedy.”42
`
`30. Mr. Booth agreed that while nothing is speculative about “the need for
`
`or whether [the Final Remedy] will happen,” he disagreed with the purported
`
`“certainty” surrounding METG’s cost estimates.43
`
`31. Ms. Staub relied on the Work Plan to form the basis of her opinion
`
`that EPA has committed certain costs for the elements of the Final Remedy.44
`
`However, the Work Plan explicitly states that the calculations constitute only a
`
`“[p]reliminary [e]stimate of [c]ost.” The Work Plan goes on to note that its cost
`
`tables “present those costs estimated for the implementation of the final
`
`components of remedy[.]”45
`
`
`40 Ex. 576 at 26–28; H’rg Tr. vol. 1 at 51:5–7.
`41 Ex. 1039 at 39.
`42 Hr’g Tr. vol. 1, 38:7–11.
`43 Hr’g Tr. vol. 2, 331:17–332:8.
`44 Hr’g Tr. vol. 1, 135:2–5.
`45 Ex. 571 at 39 (emphasis added).
`
`-14-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 15 of 60
`
`32. Further, her testimony regarding the EPA’s commitment to the slag
`
`pile’s final remedy notwithstanding, Ms. Staub admitted that at the beginning of
`
`2020, the EPA planned to implement the maximum alternative slag pile cover,
`
`supra at ⁋ 26 (calculated at $9,863,000). However, because zinc prices changed in
`
`the middle of 2020, a fourth remedy—the removal of two million tons of slag
`
`before regrading and capping the remainder—became feasible and was ultimately
`
`selected by the EPA. She went on to agree that if metal prices continued to trend
`
`favorably, more slag than two million tons could be removed.46
`
`33. The Work Plan also indicates that “because unfumed slag removal
`
`activities would impact a significant area of the slag pile footprint, development of
`
`the final grading and cover plan would not start until the unfumed slag removal is
`
`complete.” At the time METG published the Work Plan in October 2020, “the
`
`removal and recovery operation [was] estimated to be approximately 10 years.”47
`
`34. Ms. Staub went on to concede that, while the EPA relied on cost
`
`estimates to establish a Final Remedy, METG is charged with developing detailed
`
`designs necessary for implementation. After that, Ms. Staub explained, “they
`
`[METG] will update their costs.” She admitted that she did not “know whether
`
`they’re [the updated costs] gonna be the same or different” than those estimated in
`
`
`46 Hr’g Tr. vol. 1, 140:8–141:18.
`47 Ex. 1039 at 19.
`
`-15-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 16 of 60
`
`the Work Plan.48
`
`35. And, while the “EPA has announced and selected and published the
`
`[F]inal [R]emedy, and the [F]inal [R]emedy has costs associated with it,” Ms.
`
`Staub agreed that no actual invoices or other contractual obligation are tethered to
`
`the costs estimated by METG in the Work Plan.49 Moreover, she explained that in
`
`“typical engineering practice,” cost estimates in similar circumstances cover a
`
`range of minus thirty to plus fifty percent of the stated cost, and she admitted that
`
`she did not know whether future costs at the Site—including the selected remedy
`
`for the slag pile—could ultimately be thirty percent lower or fifty percent higher
`
`than the costs estimated in the Work Plan.50
`
`36. Similarly, Ms. Roberts,51 confirmed that METG accounts for potential
`
`variations in costs spent versus cost estimates. She explained that METG relies on
`
`a “range of magnitude” (“ROM”) that gauges the level of uncertainty associated
`
`with a given estimate, ranging from ROM 1 (least uncertain) to ROM 5 (most
`
`uncertain). Ms. Roberts testified that at ROM 5, METG adds 100 percent to the
`
`cost estimated by an engineer “to be able to cover that number.” She also
`
`
`48 Hr’g Tr. vol. 1., 145:13–22.
`49 Id. at 133:23–134:10.
`50 Id. at 138:4–139:1.
`51 Ms. Roberts works for Greenfield Environmental Trust Group, Inc., which provides trustee
`services to METG. H’rg Tr. vol. 1, 214:10–13.
`-16-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 17 of 60
`
`explained that METG’s budgeting process accounts for the fact that “for whatever
`
`reason[,] on these [Superfund] sites, as you know, things change rapidly and plans
`
`change.” 52
`
`37.
`
`In sum, while the EPA may have committed to remedial action as it
`
`relates the slag pile, neither Ms. Staub’s testimony nor the Work Plan on which she
`
`relies establishes that the costs associated with implementing the remedy (totaling
`
`$7,660,000)—at this juncture—are anything but estimates of future costs.
`
`B. Corrective Measures Operations and Maintenance
`
`38. The Final Remedy selected by the EPA calls for a Corrective
`
`Measures Operations and Maintenance Plan (“O&M”) for each final corrective
`
`measure “to ensure the measures remain protective over time.” Ms. Staub
`
`explained that O&M involves “a series of inspections, maintenance protocols, and
`
`basically looking at each of the final—the components of the [F]inal [R]emedy to
`
`make sure that they are functioning as designed and to ensure they remain
`
`protective of human health and the environment.”53
`
`39. O&M covers “the entire remedy” at the Site, Ms. Staub explained—
`
`not just one element. Thus, O&M ensures that not only the “four key elements that
`
`are still going to be ongoing” at the Site remain protective, but also that the IMs do,
`
`
`52 Hr’g Tr. vol. 1, 214:10–13; 238:9–239–9; 222:7–8.
`53 Ex. 571 at 21; H’rg Tr. vol. 1, 66:2–7.
`
`-17-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 18 of 60
`
`including: “the ET cover; the south plant hydraulic controls; the corrective action
`
`management units; the slag pile, [and] the slurry wall.” Margaret Staub testified
`
`further that “there’s fencing around the [S]ite that needs to be maintained. There’s
`
`erosional features. There’s erosional control structures. So it’s [O&M] a . . .
`
`pretty hefty job.” 54
`
`40. Ms. Staub went on to explain the importance of O&M in
`
`implementing the Final Remedy: “[I]n order for . . . that remedy to remain
`
`protective of human health and the environment, the remedies need to be
`
`maintained, and you can’t do that unless you’re operating them appropriately and
`
`maintaining them appropriately.”55
`
`41. Pointing to the Work Plan, Margaret Staub opined that EPA has
`
`“committed” to O&M costs pursuant to the Final Remedy at a rate of $305,000 per
`
`year through 2046. At that rate, METG’s Work Plan calculates a total of
`
`$7,930,000 for O&M costs at the Site through 2046.56
`
`42. Mr. Booth agreed that the four key ongoing elements identified by
`
`Ms. Staub—including O&M—constitute actions the METG will take at the Site
`
`and that they are “necessary,” but he opined that the O&M budget through 2046
`
`
`54 Hr’g Tr. vol. 1, 48:2–17, 66:2–16.
`55 Id. at 66:18–23.
`56 Id. at 70:11–15; Ex. 571 at 39; see also Hr’g Tr. vol. 1, 71:13–17 (Ms. Staub explaining her
`understanding that the Work Plan’s calculations were reduced to net present worth).
`-18-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 19 of 60
`
`would be more accurately pegged at lesser amount.57
`
`43. Mr. Booth’s opinion about the Work Plan’s calculation aside, the
`
`Work Plan’s cost table, and as already discussed regarding the slag pile, supra,
`
`indicates that that the $305,000 rate is a “[p]reliminary [e]stimate of [c]ost.”58
`
`44. Furthermore, the Work Plan represents that an O&M plan for each
`
`final remedy “will be prepared” and “will . . . develop contingency and mitigation
`
`procedures for unforeseen conditions, and identify performance requirements for
`
`variances, modifications, or termination of O&M activities.”59 On cross
`
`examination, Ms. Staub admitted that “unforeseen conditions”—like floods—could
`
`affect costs related to O&M.60
`
`45.
`
`Indeed, the Work Plan itself disclaims that the cost table—on which
`
`Ms. Staub relied—constitutes a “preliminary estimate of cost” as it relates to, inter
`
`alia, long term O&M.61
`
`46. Ms. Staub admitted, too, that past O&M costs approved by the EPA
`
`and budgeted for by METG had significantly varied from the amount METG
`
`actually spent on O&M. For example, in 2019, the approved budget for O&M was
`
`
`57 Hr’g Tr. vol. 2, 316:2–23, 313:12–18.
`58 Ex. 571 at 39.
`59 Id. at 21 (emphasis added).
`60 Hr’g Tr. vol. 1, 150:5–16.
`61 Ex. 571 at 14.
`
`-19-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 20 of 60
`
`$896,600, but METG only spent $275,744 on O&M that year. As Ms. Staub put it,
`
`“[t]hat’s a variance of negative $620,855.” Put another way, in 2019, METG spent
`
`more than $600,000 less than had been budgeted and approved for O&M.62
`
`47.
`
`In sum, while the EPA may have committed to O&M from the present
`
`day through 2046, neither Margaret Staub’s testimony nor the Work Plan on which
`
`she relies evidences that the costs associated ongoing O&M (totaling
`
`$7,930,000)—at this juncture—are anything but estimates, albeit well-reasoned
`
`ones.
`
`
`
`C. Corrective Measures Performance Monitoring
`
`48. Corrective Measures Performance Monitoring in the form of
`
`groundwater monitoring has been conducted at and downgradient of the Site since
`
`1984, and the Final Remedy selected by the EPA requires continued groundwater
`
`monitoring to evaluate the performance of the corrective measures over time.63
`
`49. Corrective Measures Performance Monitoring includes, and will
`
`continue to include, collection of groundwater levels and elevations, surface water
`
`elevations, and groundwater and surface water quality sampling at selected
`
`monitoring locations. Further, Corrective Measures Performance Monitoring
`
`includes permit review, review of private well statuses, and review of land use and
`
`
`62 Hr’g Tr. vol. 1., 158: 5–18; see also Ex. 1025 at 9.
`63 Ex. 570 at 22; 571 at 9, 12.
`
`-20-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 21 of 60
`
`land use restrictions.64
`
`50. The contaminants tested at each monitoring well do not vary, and
`
`testing is not limited to a single contaminant. Every well tests for a menu of
`
`contaminants of concern, including but not limited to arsenic, selenium, cadmium,
`
`and zinc, as well as additional analytical parameters. None of the wells test for
`
`only a single contaminant.65
`
`51. Corrective Measures Performance Monitoring began in 2016,
`
`following implementation of IMs, and continues annually for at least a thirty-year
`
`period. The scope of testing, including groundwater monitoring, residential water
`
`supply monitoring, and water level monitoring does not change from year to
`
`year.66
`
`52. Corrective Measures Performance Monitoring must occur to evaluate
`
`the performance of the corrective measures “until MCSs [media cleanup standards]
`
`are met at the points of compliance.”67
`
`53. Corrective Measures Performance Monitoring is necessary to
`
`demonstrate that the final corrective measures are meeting the relevant
`
`performance criteria, that the conditions remain protective of human heath and the
`
`
`64 Ex. 571 at 16; 576 at 10–11.
`65 Hr’g Tr. vol. 1, 75:24–76:5.
`66 Ex. 576 at 16; Ex. 571 at 39; Hr’g Tr. vol. 1, 75:9–23.
`67 Ex. 570 at 22.
`
`-21-
`
`
`
`

`

`Case 6:12-cv-00053-DLC Document 354 Filed 05/26/21 Page 22 of 60
`
`environment, and to determine if a need for additional corrective measures arises.68
`
`Indeed, Mr. Booth agreed that Corrective Measures Performance Monitoring is
`
`important and did not dispute its necessity.69
`
`54. As it does for the other components of the Final Remedy, the Work
`
`Plan also lists the costs for Corrective Measures Performance Monitoring. And, as
`
`it does with the costs associated with O&M, the Work Plan sets out costs for
`
`Corrective Measures Performance Monitoring based on a thirty-year period,
`
`beginning in 2016 and ending in 2046.70
`
`55. Specifically, in the cost table designated as a “[p]reliminary [e]stimate
`
`of [c]ost,” the Work Plan budgets $280,000 per year through 2046 for Corrective
`
`Measures Performance Monitoring. Thus, the amount METG sets out in the Work
`
`Plan for Corrective Measures Performance Monitoring from 2021 through 2046
`
`totals $7,280,000.71
`
`56. Mr. Booth provided his own estimation of the total cost for Corrective
`
`Measures Performance Monitoring going forward until 2046 ($3,041,411).
`
`However, while testifying that his numbers “have the accuracy level of what [he]
`
`would typically call a feasibility study level,” he explained that even his estimate
`
`
`
`68 Ex. 571 at 16; 576 at 25.
`69 Hr’g Tr. vol. 1, 265:2–11.
`70 Ex. 571 at 39.
`71 Id.
`
`-22-
`
`

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket