throbber
Case 3:19-cv-21248-BRM-LHG Document 1 Filed 12/10/19 Page 1 of 25 PageID: 1
`
`
`
`FOX ROTHSCHILD LLP
`Formed in the Commonwealth of Pennsylvania
`By:
`Sarah B. Biser (#024661991)
`
`Jeffrey M. Pollock (#015751987)
`Princeton Pike Corporate Center
`997 Lenox Drive
`Lawrenceville, NJ 08648
`Tel: 646.601.7636 / Fax: 212.692.0940
`Attorneys for Plaintiff
`The Trustees of Princeton University
`
`
`
`UNITED STATES DISTRICT COURT
`FOR THE DISTRICT OF NEW JERSEY
`
`
`
`THE TRUSTEES OF PRINCETON
`UNIVERSITY,
`
` Plaintiff,
`
` v.
`
`TOD WILLIAMS BILLIE TSIEN
`ARCHITECTS, LLP; JACOBS
`ARCHITECTS/ENGINEERS, INC.; and
`JACOBS CONSULTANCY INC.,
`
` Defendants.
`
`
`
`
`:
`:
`:
`:
`:
`:
`:
`:
`:
`:
`:
`:
`:
`:
`
`
`
` Civil Action No. ________________
`
`
`
`
`COMPLAINT &
`DEMAND FOR JURY TRIAL
`
`
`(Document Electronically Filed)
`
`Plaintiff, The Trustees of Princeton University (“Princeton” or “Plaintiff”), a private,
`
`non-profit educational institution, brings this Complaint against Defendants Tod Williams Billie
`
`Tsien Architects, LLP (“TWBTA”), Jacobs Architects/Engineers, Inc., and Jacobs Consultancy
`
`Inc. (collectively, “Jacobs” or the “Jacobs Entities”) (the three defendants are referred to
`
`collectively herein as “Defendants”), and states and alleges as follows:
`
`
`Active\105828599.v1-12/10/19
`
`
`
`

`

`Case 3:19-cv-21248-BRM-LHG Document 1 Filed 12/10/19 Page 2 of 25 PageID: 2
`
`
`
`
`
`NATURE OF THE CASE
`
`1.
`
`Defendants are design professionals engaged by, or on behalf of, Princeton to
`
`provide professional design services related to the design and construction of The Andlinger
`
`Center for Energy and the Environment (“Andlinger” or the “Project”). Princeton engaged
`
`TWBTA to serve as the project architect, and TWBTA, in turn, engaged Jacobs as engineering
`
`sub-consultants for the design of the Project as well as other sub-consultants who are not named
`
`herein.
`
`2.
`
`Defendants TWBTA and Jacobs (collectively, the “Design Team”) failed to
`
`perform their professional design responsibilities in accordance with the prevailing standard of
`
`care, resulting in unnecessary and excessive additional costs and extensive project delays.
`
`Further, the Design Team failed to meet the Schedule Milestones set forth in the prime design
`
`contract and failed to design to budget as contractually required and, therefore, breached their
`
`contracts. By this action, Princeton seeks to recover the damages it has incurred as a result of
`
`Defendants’ professional negligence and breach of contract.
`
`3.
`
`Princeton is a non-profit educational institution, existing under the laws of the
`
`THE PARTIES
`
`State of New Jersey, with its principal place of business located at One Nassau Hall, Princeton
`
`University, Princeton, New Jersey 08544.
`
`4.
`
`Upon information and belief, TWBTA is a limited liability partnership organized
`
`under the laws of the State of New York, with its principal place of business located at 222
`
`Central Park South, New York, New York 10019. TWBTA provided architectural services
`
`related to the Project.
`
`
`Active\105828599.v1-12/10/19
`
`-2-
`
`

`

`Case 3:19-cv-21248-BRM-LHG Document 1 Filed 12/10/19 Page 3 of 25 PageID: 3
`
`
`
`5.
`
`Upon information and belief, Jacobs Architects/Engineers, Inc. (“Jacobs
`
`Architects/Engineers”) is a corporation organized under the laws of the State of Delaware, with
`
`its principal place of business located at 777 Main Street, Fort Worth, Texas 76102. Jacobs
`
`Architects/Engineers was a sub-consultant of TWBTA that provided engineering services related
`
`to the Project, specifically with respect to scientific laboratory spaces.
`
`6.
`
`Upon information and belief, Jacobs Consultancy Inc. (“Jacobs Consultancy”) is
`
`a corporation organized under the laws of the State of Texas, with its principal place of business
`
`located at 5995 Rogerdale Road, Houston, Texas 77072 and an office located at 100 Walnut
`
`Avenue, Suite 604, Clark, NJ 07066. Jacobs Consultancy was a sub-consultant of TWBTA that
`
`provided engineering services related to the Project, specifically with respect to scientific
`
`laboratory spaces.
`
`
`
`JURISDICTION AND VENUE
`
`7.
`
`This Court has jurisdiction over the subject matter of this action pursuant to 28
`
`U.S.C. §1332, as there is complete diversity between the parties and the amount in controversy
`
`exceeds $75,000.00, exclusive of interest and costs.
`
`8.
`
`The Court has personal jurisdiction over TWBTA because TWBTA has
`
`contractually consented to such jurisdiction. Article XVII (c) of the agreement to perform
`
`architectural design services for the Project entered into between Princeton and TWBTA, dated
`
`February 12, 2009 (the “Design Contract”) provides for the exclusive jurisdiction in the State or
`
`Federal courts of New Jersey for actions arising under the Design Contract. Further, this Court
`
`has personal jurisdiction over TWBTA because it conducted business in the state and Plaintiff’s
`
`cause of action relates to and arises out of the business that it conducted in the state, and it has
`
`
`Active\105828599.v1-12/10/19
`
`-3-
`
`

`

`Case 3:19-cv-21248-BRM-LHG Document 1 Filed 12/10/19 Page 4 of 25 PageID: 4
`
`
`
`availed itself of New Jersey laws by negotiating the Design Contract and performing the design
`
`services required as Project architect for the Project.
`
`9.
`
`The Court has personal jurisdiction over Jacobs Architects/Engineers because it
`
`has consented to jurisdiction pursuant to Section 8.2 of its agreement with TWBTA, whereby
`
`Jacobs Architects/Engineers agreed to participate in whatever dispute resolution process for this
`
`matter to which TWBTA is a party or participant. In addition, the Court has personal jurisdiction
`
`over Jacobs Architects/Engineers because it conducted business in the state and Plaintiff’s cause
`
`of action relates to and arises out of the business that it conducted in the state, and it has availed
`
`itself of New Jersey laws by performing engineering services required for the Project.
`
`10.
`
`The Court has personal jurisdiction over Jacobs Consultancy because it has
`
`consented to jurisdiction pursuant to Section 8.2 of its agreement with TWBTA, whereby Jacobs
`
`Consultancy agreed to participate in whatever dispute resolution process for this matter to which
`
`TWBTA is a party or participant. In addition, the Court has personal jurisdiction over Jacobs
`
`Consultancy because it conducted business in the state and Plaintiff’s cause of action relates to
`
`and arises out of the business that it conducted in the state, and it has availed itself of New Jersey
`
`laws by performing engineering services required for the Project.
`
`11.
`
`Venue is proper in the District of New Jersey pursuant to 28 U.S.C. §1391(b)(2).
`
`ALLEGATIONS COMMON TO ALL COUNTS
`
`12.
`
`In 2008, Princeton issued an RFP for the design and construction of the Andlinger
`
`Center for Energy and the Environment, a state-of-the-art, 129,000 square foot facility for
`
`research and teaching in the areas of sustainable energy-technology development, energy
`
`efficiency, and environmental protection and remediation. Andlinger would bring together
`
`faculty members from various departments and interdisciplinary centers, including Chemical
`
`
`Active\105828599.v1-12/10/19
`
`-4-
`
`

`

`Case 3:19-cv-21248-BRM-LHG Document 1 Filed 12/10/19 Page 5 of 25 PageID: 5
`
`
`
`Engineering, Electrical Engineering, Civil and Environmental Engineering, Mechanical and
`
`Aerospace Engineering, and the Princeton Institute for Science and Technology of Materials,
`
`among others, in a world-class facility devoted to research and teaching in the areas of energy
`
`and the environment.
`
`13.
`
`On or about February 12, 2009, Princeton engaged TWBTA to perform
`
`architectural design services for the Project pursuant to the Design Contract. A copy of the
`
`contract between Princeton and TWBTA for Design Services for the Andlinger Center for
`
`Energy & Environment, Contract No. FC0003914W, dated February 12, 2009, is attached hereto
`
`as Exhibit A.
`
`14.
`
`In order to perform and complete the design services necessary for the Project,
`
`TWBTA engaged Jacobs Architects/Engineers and Jacobs Consultancy as well as other sub-
`
`consultants.
`
`15.
`
`On or about July 11, 2011, Princeton engaged F.J. Sciame Construction, Inc.
`
`(“Construction Manager”), to act as construction manager to construct the Project.
`
`16.
`
`Project design commenced in 2009. Construction commenced in 2012 and was
`
`substantially completed on January 1, 2016.
`
`The Design Contract
`
`17.
`
`The Design Contract sets forth the terms of the agreement between Princeton and
`
`TWBTA, including setting forth the standard of care.
`
`18.
`
`Article VI(a) of the Design Contract, which established the Standard of Care,
`
`provides that:
`
`Standard of Care. Architect-Engineer shall perform the Services
`hereunder this Agreement in accordance with the standards of skill and
`care generally exercised by other design professionals in the same locale
`acting under similar circumstances and conditions.
`
`
`Active\105828599.v1-12/10/19
`
`-5-
`
`

`

`Case 3:19-cv-21248-BRM-LHG Document 1 Filed 12/10/19 Page 6 of 25 PageID: 6
`
`
`
`19.
`
`Article VI(b) (Project Administration Services) of the Design Contract, which
`
`sets forth TWBTA’s administration obligations, provides that:
`
`Project Administration Services. The Architect-Engineer shall provide
`all project administration services necessary to facilitate the orderly
`progress of
`the Project,
`including attending Project meetings,
`communicating with others as appropriate, monitoring progress and
`issuing progress reports to Princeton University, supervising Architect-
`Engineer’s in-house personnel, directing Architect-Engineer’s Consultants
`and coordinating and managing information flow and decision-making.
`(Emphasis supplied).
`
`20.
`
`Article VI(d) (Project Cost Control) of the Design Contract provides that:
`
`(1) Duty to Design the Project Within the Construction Budget.
`Architect-Engineer shall design the Project so that the Construction Cost
`to construct the Project in accordance with the Construction Documents
`prepared by the Architect-Engineer and its Consultants does not exceed
`the Construction Budget. The Architect-Engineer acknowledges that the
`Construction Budget includes adequate provision for the construction of
`all elements of the Project designed by or specified by the Architect-
`Engineer and its Consultants as contemplated by the Project Description
`attached as Part II of the Contract.
`
`21.
`
`Article VI(f) (Coordinated Services) of the Design Contract, which sets forth
`
`TWBTA’s obligations to coordinate its services and those of its sub-consultants, provides that:
`
`Coordinated Services. The Architect-Engineer acknowledges that it is
`essential that all Services in connection with the Project be coordinated,
`including services provided by Princeton University. The Architect-
`Engineer shall coordinate the services of all its architects, engineers, Basic
`Consultants and Specialized Consultants for the Project, shall review and
`check all drawings and specifications prepared by architects, engineers,
`Basic Consultants and Specialized Consultants for the Project, and shall
`make modifications as necessary, to assure that they are integrated into a
`coordinated and complete set of documents prior to each submission. In
`addition, the Architect-Engineer shall coordinate its Services with services
`provided by Princeton University and Princeton University’s in-house
`architects.
`
`22.
`
`Article VII(f) (Construction Documents Phase Services) of the Design Contract
`
`provides, at Article VII(f)(3), that:
`
`
`Active\105828599.v1-12/10/19
`
`-6-
`
`

`

`Case 3:19-cv-21248-BRM-LHG Document 1 Filed 12/10/19 Page 7 of 25 PageID: 7
`
`
`
`Drawings. Drawings shall document the scope of work and details for the
`project, and shall be coordinated both internally, with the Consultants, and
`with the specifications. Construction Documents shall, in accordance with
`the Standard of Care set forth in Article VI(a), be in compliance with those
`codes, ordinances, statutes, regulations and laws applicable to the
`Architect-Engineer’s Services, except
`to
`the extent expressly and
`specifically stated in detail in writing by Architect-Engineer at the time of
`such submission.
`
`23.
`
`Article VII(h) (Construction Phase Services – Administration of the
`
`Construction Contract) of the Design Contract, which sets forth the requirements for
`
`TWBTA’s services during the Construction Phase, provides, among other things, that TWBTA
`
`shall:
`
`(i) administer the contract between Princeton and the Contractor in
`accordance with the Construction Documents;
`
`(ii) respond to requests for information by way of sketches or other
`supplemental instructions without causing construction delays and within
`the time agreed to between Contractor and the Architect-Engineer, but
`shall not result in construction delays; and
`
`(iii) revise the Construction Documents due to, among other things, a
`reasonable number of Princeton’s proposed changes to the Construction
`Documents.
`
`24.
`
`Article VII(h)(4)(ii) (Due to Architect-Engineer’s Error) of the Design Contract
`
`also provides, in relevant part, that changes to Construction Documents caused by TWBTA’s
`
`error, omission or failure to coordinate must be made promptly and at no additional cost to
`
`Princeton:
`
`[i]f the Construction Documents must be changed to correct Architect-
`Engineer’s error, omission, or failure to coordinate the drawings and
`specifications comprising
`the Construction Documents, Architect-
`Engineer will make the change promptly upon becoming aware of the
`need for a correction, as part of its Basic Services, and at no additional
`cost to Princeton University. Architect-Engineer will work with Princeton
`University and the Contractor to minimize the impact of the resulting
`changes on the cost of the Project and the Construction Schedule.
`
`
`Active\105828599.v1-12/10/19
`
`-7-
`
`

`

`Case 3:19-cv-21248-BRM-LHG Document 1 Filed 12/10/19 Page 8 of 25 PageID: 8
`
`
`
`25.
`
`Article VII(h)(10) (Submittals) of the Design Contract provides, in relevant part,
`
`that TWBTA shall review all submittals, including shop drawings, product data, and samples,
`
`within ten (10) days of receipt of first submissions and subsequent submittals of same, and that
`
`the shop drawing review process shall not be used by the Architect-Engineer to enhance or
`
`modify the design of the project. Article VII(h)(10) provides:
`
`Submittals. The Architect-Engineer shall review and/or approve the
`Contractor’s submittals such as shop drawings, product data and samples.
`The Architect-Engineer’s action shall be taken within ten (10) working
`days of receipt of first submissions and subsequent submittals, unless a
`shorter period is agreed to with respect to particular submittals. Review of
`such submittals is not conducted for the purpose of determining accuracy
`and completeness of other details such as dimensions and quantities or for
`substantiating instructions for installation or performance of equipment or
`systems by the Contractors, all of which remain the responsibility of the
`Contractor. The Architect-Engineer’s review shall not constitute approval
`of safety precautions or programs, or of construction means, methods,
`techniques, sequences or procedures. The Architect-Engineer’s approval
`of a specific item shall not indicate approval of an assembly of which the
`item is a component. When professional certification of performance
`characteristics of materials, systems or equipment is required by the
`Construction Documents, the Architect-Engineer shall be entitled to rely
`upon such certification to establish that the material, systems or equipment
`will meet
`the performance criteria required by
`the Construction
`Documents. The shop drawing review process shall not be used by the
`Architect-Engineer to enhance or modify the design of the project.
`
`26.
`
`Article VII(d), (e), (f), (g), and (h) of the Design Contract further required
`
`TWBTA to provide its services in accordance with customary milestones broken down between
`
`the design phase, bidding and negotiation phase, and construction phase as follows:
`
`During the Schematic Design Phase, TWBTA would submit
`(i)
`Schematic Design Documents
`that
`included, among other
`things,
`preliminary architectural, mechanical, electrical, civil, and landscape
`designs within the prescribed Construction Budget of $102,290,000.00 for
`Princeton’s review and approval;
`
`During the Design Development Phase, TWBTA would submit
`(ii)
`Design Development Documents that included, among other things,
`architectural, mechanical, electrical, civil, and landscape designs that
`
`
`Active\105828599.v1-12/10/19
`
`-8-
`
`

`

`Case 3:19-cv-21248-BRM-LHG Document 1 Filed 12/10/19 Page 9 of 25 PageID: 9
`
`
`
`established the final scope of each discipline for Princeton’s review and
`approval;
`
`(iii) During the Construction Documents Phase, TWBTA would submit
`Construction Documents
`that
`included, among other
`things, fully
`coordinated drawings documenting the scope and detail for the Project;
`
`(iv) During the Bidding and Negotiation Phase TWBTA would, among
`other things, assist Princeton in evaluating and awarding bids to
`contractors to construct the Project; and
`
`During the Construction Phase, TWBTA would, among other
`(v)
`things, review contractor submittals including shop drawings, respond to
`questions from the contractor concerning the design, prepare further
`sketches and direction to the contractor, attend project meetings, review
`the contractor’s applications for payment, and regularly visit the site and
`review the progress and quality of construction, and report back to
`Princeton.
`
`27.
`
`Article VI(e)(3) (Consultant Agreements) of the Design Contract requires
`
`TWBTA to include a provision in its subcontracts with consultants, like the Jacobs Entities,
`
`expressly designating Princeton as a third-party beneficiary of those subcontracts, stating, in
`
`relevant part:
`
`Consultant Agreements. Architect-Engineer, shall upon request, provide
`to Princeton University complete and correct copies of Architect-
`Engineer's agreement with each Consultant, including amendments
`thereto. Architect-Engineer shall enter into an agreement with each
`Consultant pursuant to which the Consultant assumes toward the
`Architect-Engineer all of the obligations that the Architect-Engineer
`assumes toward Princeton University under the Contract. In addition, each
`contract shall include the following provisions:
`
`An agreement by the Architect-Engineer and Consultant
`(i)
`that Princeton University is a third-party beneficiary of the
`agreement, entitled to enforce any rights thereunder for its benefit,
`and that Princeton University shall have the same rights and
`remedies vis-à-vis such Consultants that the Architect-Engineer
`may have, including, but not limited to, the right to be
`compensated for any loss, expense or damage of any nature
`whatsoever incurred by Princeton University, resulting from any
`breach of such agreements by the Consultant, any breach of
`representations arising out of such agreements and any negligent
`
`
`Active\105828599.v1-12/10/19
`
`-9-
`
`

`

`Case 3:19-cv-21248-BRM-LHG Document 1 Filed 12/10/19 Page 10 of 25 PageID: 10
`
`
`
`error or omission of such Consultant in the performance of any of
`its professional services obligations under such agreements; . . . .
`
`28.
`
`The Design Contract, at Article XI (Time of Performance), also required that
`
`TWBTA perform its Services in accordance with the Milestone Design Schedule:
`
`29.
`
`Time is of the essence for this Contract. The Architect-Engineer shall perform its
`
`services under the Contract in accordance with the Milestone Design Schedule set forth below
`
`and the Design and Construction Schedule as described in Article VI(c).
`
`Project Phase
`Schematic Design Phase
`
` SD Drawings Complete
`
`Milestone Dates
`December 25, 2009
`
`October 23, 2009
`
` SD Complete/Approval to Proceed to DD
`
`January 22, 2010
`
`Design Development Phase
`
`Construction Documents Phase
`
` 50% Documents Complete
`
` 85% Documents Complete
`
`October 13, 2010
`
`September 14, 2011
`
`February 4, 2011
`
`June 17, 2011
`
` 100% Documents Complete
`
`September 14, 2011
`
` GMP Agreement
`
`Bidding & Negotiation Phase
`
`Construction Phase
`
`Close-Out Phase
`
`
`October 7, 2011
`
`November 4, 2011
`
`February 27, 2015
`
`March 2, 2016
`
`30.
`
`Finally, the Design Contract calls for TWBTA to indemnify Princeton for
`
`TWBTA’s negligent acts. Article XII(h)(1) (Indemnification) of the Design Contract states, in
`
`relevant part:
`
`
`Active\105828599.v1-12/10/19
`
`-10-
`
`

`

`Case 3:19-cv-21248-BRM-LHG Document 1 Filed 12/10/19 Page 11 of 25 PageID: 11
`
`
`
`To the fullest extent permitted by the laws of the State of New Jersey . . .
`the Architect-Engineer (the “Indemnitor” for purposes of interpreting this
`Paragraph) agrees to indemnify and hold harmless, and pay for the defense
`of Princeton University, its trustees, officers and employees, and any
`affiliated or related entities . . . against all claims, loss, liability, damage,
`costs and expenses, including reasonable attorney’s fees, that are alleged
`to have occurred in whole or in part arise as a result of, but only to the
`extent caused by and in proportion to, the negligent acts or omissions of
`the Indemnitor, its agents, consultants, employees, or representatives.
`(Emphasis omitted).
`
`The Design Team’s Unsatisfactory Performance
`
`
`
`
`
`31.
`
`From the outset, TWBTA failed to properly and efficiently coordinate its work
`
`with that of its sub-consultants and to manage the work of its sub-consultants.
`
`32.
`
`TWBTA’s failure to coordinate its subconsultants and failure to properly manage
`
`the design process in a timely manner delayed the completion of the design, and the
`
`administration of the construction. TWBTA’s failures plagued the Project, causing Princeton to
`
`incur additional costs and suffer project delays.
`
`33.
`
`Further, over the course of the design process, the Design Team repeatedly
`
`submitted designs that exceeded the construction budget for the Project. In fact, the initial
`
`design submission exceeded the design to budget by over fifty percent (50%). The Design
`
`Development submission and 50% and 85% construction documents were also over budget.
`
`34.
`
`Submission of grossly over-budget designs required additional rework and
`
`extensive value engineering at each design milestone including Schematic Design, Design
`
`Development, 50% Construction Documents and 85% Construction Documents to achieve a
`
`construction budget that was acceptable to Princeton.
`
`35.
`
`Over the course of the Construction Document Phase, drawings, specifications,
`
`and other work product prepared by the Design Team were routinely incomplete and deficient.
`
`TWBTA Failed to Submit Complete Documents
`
`
`Active\105828599.v1-12/10/19
`
`-11-
`
`

`

`Case 3:19-cv-21248-BRM-LHG Document 1 Filed 12/10/19 Page 12 of 25 PageID: 12
`
`
`
`In Accordance with Contract Milestones
`
`Over the course of the Construction Document Phase, TWBTA’s drawings,
`
`36.
`
`specifications, and other work product were routinely incomplete, deficient and late.
`
`37.
`
`TWBTA failed to meet the following key Contract Milestones:
`
`
`
`% Complete
`
`Contract Milestone
`
` Schematic Design Phase
`
`December 25, 2009
`
` SD Drawings Complete
`
`October 23, 2009
`
` SD Complete/Approved to Proceed to DD
`
`January 22, 2010
`
` Design Development Phase
`
`October 13, 2010
`
` 85% Documents Complete
`
`June 17, 2011
`
` 100% Documents Complete
`
`September 14, 2011
`
` GMP Agreement
`
`October 7, 2011
`
`
`
`38.
`
`Instead, TWBTA issued their Construction Documents as follows:
`
`% Complete
`
`Contract Milestone
`
`Date of Submission
`
`Design Documents Complete
`
`-
`
`-
`
` 85% Documents Complete
`
`June 17, 2011
`
`August 12, 2011
`
` 100% Documents Complete – First Release
`
`September 14, 2011
`
`January 13, 2012
`
`100% Documents Complete – Second Release
`
`September 14, 2011
`
`June 15, 2012
`
` GMP Agreement
`
`October 7, 2011
`
`March 12, 2012
`
`
`
`39.
`
`As set forth above, on August 12, 2011, the Design Team submitted drawings and
`
`specifications to Princeton that the Design Team claimed to be 85% complete (and upon which
`
`the Construction Manager’s guaranteed maximum price (“GMP”) was to be based). The Design
`
`
`Active\105828599.v1-12/10/19
`
`-12-
`
`

`

`Case 3:19-cv-21248-BRM-LHG Document 1 Filed 12/10/19 Page 13 of 25 PageID: 13
`
`
`
`Team’s missing details and coordination resulted in the issuance by TWBTA of eleven (11) Bid
`
`Addenda and four (4) Construction Addenda before the end of 2011. As a result, Princeton was
`
`forced to require the Construction Manager to delay the buyout of certain key trade
`
`subcontractors to provide more time for the Design Team to complete its work.
`
`40.
`
`After the submission on August 12, 2011, TWBTA issued the following bid
`
`addenda:
`
`a.
`
`b.
`
`c.
`
`d.
`
`e.
`
`f.
`
`Bid Addenda 1–3
`
`Bid Addenda 5–8
`
`Bid Addenda 4
`
`Bid Addenda 9
`
`Bid Addenda 10
`
`Bid Addenda 11
`
`
`
`
`
`
`
`
`
`
`
`
`
`9/27/11
`
`9/30/11
`
`10/6/11
`
`10/31/11
`
`11/7/11
`
`12/2/11
`
`41.
`
`Prior to construction TWBTA issued the following construction addenda:
`
`a.
`
`b.
`
`c.
`
`d.
`
`Construction Addendum 1
`
`9/26/11
`
`Construction Addendum 2
`
`9/27/11
`
`Construction Addendum 3
`
`10/12/11
`
`Construction Addendum 4
`
`9/26/11
`
`42.
`
`Like the 85% set, the 100% Construction Documents package that TWBTA
`
`issued on January 13, 2012 were not complete. The drawings were missing details and
`
`coordination. Thus, after this package was issued, TWBTA issued more construction addenda:
`
`a.
`
`b.
`
`c.
`
`Construction Addendum 6 & 7
`
`2/14/12
`
`Construction Addendum 8
`
`
`
`2/17/12
`
`Construction Addendum 12 & 13
`
`3/01/12
`
`
`Active\105828599.v1-12/10/19
`
`-13-
`
`

`

`Case 3:19-cv-21248-BRM-LHG Document 1 Filed 12/10/19 Page 14 of 25 PageID: 14
`
`
`
`43.
`
`Princeton could not finalize the GMP with the Construction Manager until March
`
`12, 2012 – five months after the scheduled milestone. Construction commenced on or about
`
`February 27, 2012.
`
`44.
`
`The 100% Construction Documents were still not complete. TWBTA issued the
`
`following construction addenda after the GMP was executed:
`
`a.
`
`b.
`
`c.
`
`d.
`
`e.
`
`f.
`
`g.
`
`Construction Addendum 9
`
`Construction Addendum 14
`
`Construction Addendum 10
`
`Construction Addendum 5
`
`Construction Addendum 11
`
`Construction Addendum 16
`
`Construction Addendum 15
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`3/14/12
`
`3/23/12
`
`4/20/12
`
`5/01/12
`
`5/03/12
`
`5/22/12
`
`6/01/12
`
`45.
`
`Princeton’s numerous admonitions to TWBTA to complete the drawings properly
`
`were not heeded. TWBTA issued a final consolidated drawing set that included these addenda
`
`on June 15, 2012 (the “Consolidated Set”), which was also labeled as the 100% Construction
`
`Documents. The Design Team issued one last construction addendum four months after the
`
`Consolidated Set was issued – Construction Addendum 8 – on October 10, 2012.
`
`46.
`
`Yet, the revised set of 100% Construction Documents was still incomplete --
`
`resulting in significant rework and redesign by the Design Team on an on-going basis during the
`
`Construction Phase of the Project.
`
`47.
`
`Contrary to the express provisions of the Design Contract, TWBTA and the
`
`Design Team often used trade subcontractor shop drawings, in particular, mechanical trades’
`
`shop drawings, as an opportunity to revise the design and finish incomplete or incorrect designs
`
`contained in the construction drawings.
`
`
`Active\105828599.v1-12/10/19
`
`-14-
`
`

`

`Case 3:19-cv-21248-BRM-LHG Document 1 Filed 12/10/19 Page 15 of 25 PageID: 15
`
`
`
`The Design Team Issued 87 ASIs That Required Revisions
`to More Than a Thousand Drawings
`
`
`
`48.
`
`The failure of TWBTA and the Jacobs Entities to properly, timely, and fully
`
`complete the project design resulted in the Design Team’s issuance of scores of Architect’s
`
`Supplemental Information notices (each an “ASI”) to the Construction Manager. In fact, the
`
`Design Team used ASIs and Addendum - over the one-year time period subsequent to the
`
`submission of 85% Construction Documents - to complete the design work, including
`
`coordination among the subconsultant disciplines.
`
`49.
`
`After the so-called 100% Construction Documents were issued, TWBTA issued
`
`approximately eighty-seven (87) ASIs from June 15, 2012 until June 21, 2017. These ASIs
`
`fundamentally revised and modified the 100% set of Construction Documents, and contained
`
`revisions that captured missing or incorrect details and missing design coordination required for
`
`the construction of the Project. Moreover, seven (7) of the ASIs were revised and resubmitted
`
`with even more design revisions.
`
`TWBTA’s Incomplete and Deficient Work
`Resulted in No Less than 462 Change Orders
`
`
`
`50.
`
`The impact of the cascade of ASIs and other design changes was extensive. The
`
`ASIs and the Design Team’s other incomplete or deficient work resulted in the issuance of no
`
`less than four hundred and sixty-two (462) out of the Project’s six hundred and fifty-four (654)
`
`Change Order Requests (“CORs”) to the Construction Manager.
`
`51.
`
`Of the four hundred and sixty-two (462) design related CORs, four hundred and
`
`thirty-eight (438) CORs are related to TWBTA’s and/or Jacobs’ errors and omissions; seventeen
`
`(17) CORs are related to additional Building Information Modeling (“BIM”) services as a result
`
`of design revisions; and seven (7) CORs are related to delays that the Design Team caused.
`
`
`Active\105828599.v1-12/10/19
`
`-15-
`
`

`

`Case 3:19-cv-21248-BRM-LHG Document 1 Filed 12/10/19 Page 16 of 25 PageID: 16
`
`
`
`52.
`
`Thus, Princeton has been damaged in an amount no less than $3,400,000 (the
`
`“Errors and Omissions Costs”) resulting from the four hundred and thirty-eight (438) CORs
`
`related to the Design Team’s errors and omissions. The Design Team is responsible for these
`
`Errors and Omissions Costs, which would not have been incurred had the Design Team delivered
`
`a set of fully detailed and complete coordinated drawings from the outset of the Project.
`
`
`
`Additional BIM Services & Costs
`
`53.
`
`The Design Contract required that TWBTA deliver a full model of the Project
`
`using Building Information Modeling (“BIM”). The Design Contract specifically provides, in
`
`relevant part, in Part II, Project Description (at page 4 - 5):
`
`Building Information Modeling
`
`The selected Architect will implement a design and documentation
`process that is fully coordinated with all consultants. It is highly desired
`that the Architect will utilize three-dimensional, real-time, dynamic
`building modeling software to increase productivity in building design and
`construction. The process is to produce a Building Information Model
`(BIM), which encompasses building geometry, spatial relationships,
`geographic information, and quantities and properties of the building
`components. It is anticipated that the Architect will work with Princeton
`University at the earliest inception of the project to establish an acceptable
`BIM standard for the project.
`
`54.
`
`The original BIM coordination
`
`that
`
`the Construction Manager and
`
`its
`
`subcontractors carried out required extensive revisions by the Construction Manager and
`
`mechanical subcontractors because of the incomplete drawings and volume of revisions received
`
`from the Design Team.
`
`55.
`
`The ASIs that TWBTA issued after issuance of the Consolidated Set resulted in
`
`seven (7) change order requests to Princeton by the Construction Manager for revisions required
`
`to the BIM Construction Model. These changes order were as follows:
`
`(i)
`
`CO 44
`
`
`
`MMC Contractors
`
`
`
`$ 4,521
`
`
`Active\105828599.v1-12/10/19
`
`-16-
`
`

`

`Case 3:19-cv-21248-BRM-LHG Document 1 Filed 12/10/19 Page 17 of 25 PageID: 17
`
`(ii)
`
`CO 171A R1
`
`Barham Group
`
`(iii) CO 171B R1
`
`(iv) CO 171C A
`
`
`
`
`
`MMC Contractors
`
`
`
`
`
`
`
`$ 523,224
`
`$ 263,639
`
`Unity International Group
`
`$ 212,077
`
`(v)
`
`CO 171C BR1
`
`Unity International Group
`
`$ 196,203
`
`(vi) CO 233B
`
`(vii) CO 249 R1
`
`Total:
`
`
`
`
`
`
`
`
`
`Sciame
`
`Majek
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`$ 156,606
`
`$ 7,681
`
`$1,363,951
`
`56.
`
`Thus, the ASIs, which fundamentally changed elements of the desi

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket