throbber
Case 2:04-cv-02652-JS-ARL Document 589 Filed 09/29/17 Page 1 of 7 PageID #: 15283
`
`MEMORANDUM & ORDER
`04-CV-2652(JS)(ARL)
`
`
`
`UNITED STATES DISTRICT COURT
`EASTERN DISTRICT OF NEW YORK
`---------------------------------------X
`SCIENTON TECHNOLOGIES, INC.,
`
`
`
`
`
`Plaintiff,
`
`
`-against-
`
`
`
`COMPUTER ASSOCIATES INTERNATIONAL,
`INC.,
`Defendant.
`
`
`
`
`
`---------------------------------------X
`APPEARANCES
`For Plaintiff:
`Alexander Orlowski, Esq.
`Dennis P. Stolle, Esq.
`
`
`
`
`Lynn C. Tyler, Esq.
`Matthew S. Barr, Esq.
`
`
`
`
`
`
`
`
`Robert Dean MacGill, Esq.
`Barnes & Thornburg LLP
`
`
`
`
`11 South Meridian Street
`Indianapolis, Indiana 46204
`
`
`
`
`
`
`
`
`Panagiota Betty Tufariello, Esq.
`
`
`
`
`The Law Offices of P.B. Tufariello, P.C.
`
`
`
`
`25 Little Harbor Road
`
`
`
`
`Mt. Sinai, New York 11766
`For Defendant:
`Jonathan N. Francis, Esq.
`
`
`
`
`Michael D. Schissel, Esq.
`
`
`
`
`Anthony D. Boccanfuso, Esq.
`
`
`
`
`Carmela T. Romeo, Esq.
`
`
`
`
`Erik Christopher Walsh, Esq.
`
`
`
`
`Pamela Addison Miller, Esq.
`
`
`
`
`Arnold & Porter LLP
`
`
`
`
`399 Park Avenue
`
`
`
`
`New York, New York 10022
`
`
`
`
`Kevin Patrick Mulry, Esq.
`
`
`
`
`Sarah M. Baird, Esq.
`
`
`
`
`John P. McEntee, Esq.
`
`
`
`
`Farrell Fritz, P.C.
`
`
`
`
`1320 RXR Plaza
`
`
`
`
`Uniondale, New York 11556
`
`

`

`Case 2:04-cv-02652-JS-ARL Document 589 Filed 09/29/17 Page 2 of 7 PageID #: 15284
`
`SEYBERT, District Judge:
`
`
`In the fall of 2015, a jury delivered a verdict in favor
`of Scienton Technologies, Inc. (“Scienton” or “Plaintiff”) finding
`Computer Associates International, Inc. (“CA” or “Defendant”)
`liable on Scienton’s claims for unfair competition and
`misappropriation of an idea for two CA products, eTrust 20/20
`(“20/20”) and eTrust Security Command Center (“SCC”). The Court
`then entered judgment in favor of CA and against Scienton for lack
`of subject matter jurisdiction based on standing arguments. The
`Second Circuit Court of Appeals entered a mandate that, among other
`things, reversed this ruling and remanded the case for
`consideration of Scienton’s Motion for New Trial on Compensatory
`Damages Only. (Docket Entry 551.) For the following reasons, the
`Court DENIES Scienton’s motion.
`BACKGROUND
`The Court assumes the parties’ familiarity with the
`facts chronicled in previous orders. (See generally May 17, 2016
`Order, Docket Entry 573.) Pertinently, the jury awarded Scienton
`$956,000 in damages for both 20/20 and SCC. (Verdict Sheet, Court
`Exs., Docket Entry 547, at 1-8.) Scienton’s expert, Mohan Rao,
`Ph.D, calculated $60,803,997 in damages for both products, (Rao’s
`Approach, Docket Entry 553-1, at 2), and CA’s expert, Larry
`Johnson, calculated $1,933,564 in damages for both products based
`on a two-year head start and an adjusted profit margin, (Johnson’s
`
`2
`
`

`

`Case 2:04-cv-02652-JS-ARL Document 589 Filed 09/29/17 Page 3 of 7 PageID #: 15285
`
`Approach, Docket Entry 553-2). In light of the disparity between
`the jury’s verdict and the expert calculations, Scienton argues
`that the jury’s verdict was “arbitrary” and “against the weight of
`the evidence.” (Pl.’s Br., Docket Entry 552, at 2–5.) Scienton
`requests a two-day trial involving two witnesses: Dr. Rao and Mr.
`Johnson. (Pl.’s Aug. 2017 Ltr., Docket Entry 585, at 2.)
`DISCUSSION
`As the Second Circuit has explained, a jury verdict
`should stand unless it was “seriously erroneous or a miscarriage
`of justice.” Raedle v. Credit Agricole Indosuez, 670 F.3d 411,
`417–18 (2d Cir. 2012) (internal quotation marks and citation
`omitted). In making this inquiry, the Second Circuit accords a
`“high degree of deference . . . to the jury’s evaluation of witness
`credibility,” id., and “‘considerable deference to the factual
`findings of . . . [the] jury,’” Zeno v. Pine Plains Cent. Sch.
`Dist., 702 F.3d 655, 671 (2d Cir. 2012) (quoting Blissett v.
`Coughlin, 66 F.3d 531, 536 (2d Cir. 1995)). Indeed, the
`“calculation of damages is the province of the jury,” Ismail v.
`Cohen, 899 F.2d 183, 186 (2d Cir. 1990), so “the jury’s verdict
`[must] stand unless it was palpably and grossly inadequate,” Rivera
`v. City of N.Y., 594 F. App’x 2, 7 (2d Cir. 2014); ; see also DLC
`Mgmt. Corp. v. Town of Hyde Park, 163 F.3d 124, 134 (2d Cir. 1998)
`(“A court considering a Rule 59 motion for a new trial . . . should
`only grant such a motion when the jury’s verdict is egregious.”)
`
`3
`
`

`

`Case 2:04-cv-02652-JS-ARL Document 589 Filed 09/29/17 Page 4 of 7 PageID #: 15286
`
`(internal quotation marks and citation omitted). With this steep
`standard, the Second Circuit advises that “jury verdicts should be
`disturbed with great infrequency.” Raedle, 670 F.3d at 418.
`Two facts are very important here: (1) the jury’s
`document requests and (2) the Court’s jury instructions. First,
`during deliberations, the jury requested no documents on Dr. Rao’s
`opinion. (See generally Court Exs. at 10–17; Pl.’s Ex. List,
`Docket Entry 537-1, at 12 (listing Dr. Rao’s admitted exhibits as
`exhibit numbers 1002 through 1008).) Instead, the jury requests
`documents only relating to Mr. Johnson. (Court Exs. at 10–17;
`Def.’s Ex. List, Docket Entry 537-2, at 1–2 (listing Mr. Johnson’s
`admitted exhibits as exhibit numbers EA, EB, EC, ED, and EE).) In
`fact, Mr. Johnson’s exhibits were the last ones the jury requested
`before reaching their verdict. (Courts Exs. at 10.)
`Second, the Court charged the jury to consider whether
`Scienton failed to mitigate its damages and whether only a portion
`of CA’s profits were attributable to Scienton’s idea:
`I also note that a party claiming damages as
`a result of an alleged wrongful act on the
`part of another has a duty under the law to
`mitigate those damages, that is, to take
`advantage of any reasonable opportunity the
`party may have had under the circumstances to
`reduce or minimize the damage. If you find
`that the defendant has proven that the
`plaintiff failed to seek out or take advantage
`of business or employment opportunities that
`were reasonably available, then you should
`reduce the amount of the plaintiff’s damages
`by the amount that the plaintiff could
`
`4
`
`

`

`Case 2:04-cv-02652-JS-ARL Document 589 Filed 09/29/17 Page 5 of 7 PageID #: 15287
`
`reasonably have realized if it had taken
`advantage of such opportunity.
`***
`If the idea accounts for only a portion of the
`profits earned by the defendant, you should
`only award that portion of the profits that
`are attributable to the idea. In other words,
`if the plaintiff has offered evidence that the
`defendant was unjustly enriched, the defendant
`may then introduce evidence of that the
`profits are attributable to other factors.
`(11/9/15 Tr., Docket Entry 576-8, 2373:22–2374:8, 2374:23–2375:4.)
`On the mitigation point, Scienton’s star witness, Predrag Zivic,
`testified that after its relationship with CA ended, Scienton made
`no effort to develop its idea despite options to do so. (10/22/15
`Tr., Docket Entry 562, 459:7–19.) On the profits point, the Court
`recalls that CA’s witnesses described their own work in developing
`the products. Patrick Lee, the developer of SCC, had no knowledge
`of Scienton, NI Group Inc., or Secure-IT Inc. before this lawsuit
`was filed. (11/2/15 Tr., Docket Entry 576-3, 1278:24–1279:3,
`1319:14–21.) The same is true of Howard Abrams, the developer of
`20/20, and Steve Firestone, the general manager of CA’s security
`business unit, who oversaw the development of both products.
`(11/4/15 Tr., Docket Entry 576-5, 1709:10–23, 1752:21–1753:11;
`1777:18–23, 1815:9–1818:2, 1819:1–16.) Putting all that together,
`it is a reasonable inference that the jury gave greater weight to
`Mr. Johnson’s calculation of $1.9 million and then reduced that
`figure based on the jury instructions. In other words, the jury’s
`
`5
`
`

`

`Case 2:04-cv-02652-JS-ARL Document 589 Filed 09/29/17 Page 6 of 7 PageID #: 15288
`
`verdict was not “seriously erroneous or a miscarriage of justice,”
`and the Court DENIES Scienton’s for a new-trial. See Raedle, 670
`F.3d at 417–18 (internal quotation marks and citation omitted).
`On two final points, the Second Circuit remanded only
`“for consideration of the motion for a new trial on damages,” (2d
`Cir. Mandate, Docket Entry 584, at 9), but CA had open issues in
`its motion for judgment as a matter of law--that is, arguments
`outside of the standing issue. Nevertheless, CA has requested
`that the Court decide the new-trial motion first, so “the parties
`may be in a better position to assess what portions, if any, of
`CA’s outstanding motions should be litigated further in light of
`the long-standing nature of the case and time and effort required
`by further litigation.” (Def.’s Aug. 2017 Ltr., Docket Entry 586,
`at 2 n.3.) Thus, the Court need not address whether it would
`violate the mandate rule by considering Rule 50(b) arguments not
`addressed on appeal.
`Moreover, Scienton previously filed a motion for
`prejudgment interest. Following this Memorandum and Order,
`Scienton states that it “will provide revised prejudgment interest
`calculations from Dr. Rao.” (Pl.’s Aug. 2017 Ltr. at 3 n.1.)
`
`6
`
`

`

`Case 2:04-cv-02652-JS-ARL Document 589 Filed 09/29/17 Page 7 of 7 PageID #: 15289
`
`CONCLUSION
`Plaintiff’s motion for a new trial on compensatory
`damages only is DENIED. (Docket Entry 551.) The Court invites
`Plaintiff to file a revised prejudgment interest calculation.
`
`
`
`
`
`
`
`
`
`
`
`SO ORDERED.
`
`
`
`
`
`
`
`
`
`
`
`September __29__, 2017
`Central Islip, New York
`
`Dated:
`
`
`
`/s/ JOANNA SEYBERT______
`Joanna Seybert, U.S.D.J.
`
`7
`
`

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket