throbber
The Merits of Open Bath Immersion Cooling of Datacom Equipment
`
`Phillip E. Tuma
`3M Company
`3M Center, 236-2B-01
`St. Paul, MN 55144-1000
`petuma@mmm.com
`
`Abstract
`This paper discusses the economic and environmental
`merits of passive 2-phase immersion in semi-open baths of
`dielectric fluid for cooling datacom equipment such as
`servers. The technique eliminates the need for hermetic
`connectors, pressure vessels, seals and clamshells typically
`associated with immersion cooling and the connectors,
`plumping, pumps and cold plates associated with more
`traditional liquid cooling techniques. A board level power
`density of 11.7W/cm2 can be sustained with 100cm3 of fluid
`per kW. The modular 80kW baths modeled can eject 130kW
`per m2 of floor space via water-cooled condensers. It is
`estimated that 28°C water at 15gpm could maintain average
`CPU junction temperatures, Tj<60°C and 62°C water at
`30gpm could maintain Tj<85°C, maximizing the availability
`of the heat for other purposes. Alternatively, the heat can be
`transferred directly to ambient air without water as an
`intermediate. The costs and greenhouse gas emissions
`associated with conservative annual fluid emission estimates
`are found to be less than those associated with the electrical
`power required for traditional chassis fans and liquid pumps.
`Since these fugitive losses occur at one point, more efficient
`capture techniques can be easily applied.
`Keywords
`data center, datacenter, datacom, cooling, immersion, open
`bath, fluoroketone, evaporative bath, passive, 2-phase.
`Nomenclature
`a
`constant
`C
`specific heat [J/kg-K]
`heat transfer coefficient [W/m2-K] or [W/cm2-K]
`h
`k
`thermal conductivity [W/m-K]
`K
`Henry’s Law constant [Pa-mol/mol]
`m
`mass flow rate [kg/s]
`n
`moles
`kinematic viscosity [cSt]
`
`P
`pressure [Pa]
`Q
`power or heat [W]
`heat flux [W/cm2]
`Q”
`R
`ideal gas constant = 8.314 J/mol-K or
`thermal resistance [°C/W], [°C-cm3/W]
`density [kg/m3]
`temperature [°C] or [K]
`volume [m3]
`
`
`T
`V
`
`Subscripts
`a
`ambient
`air
`air
`atm
`atmospheric
`b
`boiling or boiling point
`c
`chip
`cond
`condenser or condensation
`f
`fluid
`H
`headspace
`i
`initial or inlet
`j
`junction
`o
`final or outlet
`s
`sink
`sat
`fluid saturation
`t
`cold trap
`v
`vapor
`w
`water
`1. Introduction
`1.1. Air Cooling and its Limitations
`Among the causes of inefficiency in traditional data center
`air cooling schemes are: 2nd Law irreversibility resulting from
`multiple heat transfer processes; mixing of warm and cool
`airstreams; power consumption of cooling hardware such as
`chillers, computer room air conditioners (CRACs), fans,
`blowers and pumps; and the reliance on air as a heat transfer
`media. The technologies being implemented target one or
`more of the aforementioned causes of inefficiency.
`Water-cooled rear door heat exchangers [1], ducted rack
`exhaust plena and closed forced air racks, for example, limit
`the mixing of airstreams. Raising the facility air temperature
`can, in some instances, increase overall efficiency [2]. These
`and other technologies may enable a facility to operate
`without a chiller substituting cooling-tower-only operation
`with on-demand economizers when whether permits [3, 4]
`Facilities that use full-time economizers are simpler still and
`can achieve a Power Usage Effectiveness (PUE) <1.3 [5].
`This is limited by economizer blowers, air filters [6] and fans
`within the servers that draw power, particularly when
`temperatures are high. Furthermore, facilities like these must
`be located in relatively cool climates [7].
`There are other inherent economic and environmental
`impacts. Managing airflow at the chassis, rack or facility
`level adds
`significant engineering cost during
`the
`development of each new server, datacenter or datacenter
`expansion. The number of publications on the subject and the
`
`978-1-4244-6460-9/10/$25.00 ©2010 IEEE
`
`123
`
`26th IEEE SEMI-THERM Symposium
`
`Authorized licensed use limited to: Alexander Karl. Downloaded on June 16,2021 at 17:17:42 UTC from IEEE Xplore. Restrictions apply.
`
`Immersion Systems LLC – Ex. 1013
`PGR 2021-00104 (U.S. 10,820,446 B2)
`1 of 9
`
`

`

`sensors,
`software,
`supplying
`companies
`in
`growth
`components and services aimed at refining air cooling are
`testament to its limitations. Air-cooled facilities are usually
`large buildings as required to accommodate airflow and
`evaporative cooling towers require a large volume of water [8].
`The fabrication of fans, heat sinks, CRACs, economizers,
`filters, etc. requires refined natural resources [9, 10] that may
`end up in landfills.
`Optimization of energy efficiency eventually leads beyond
`considerations of how best to eject a facility’s waste heat to
`how best to utilize it. However, the feasibility and cost of
`recovering its waste heat at any distance from an air-cooled
`datacenter are limited by the heat’s low thermodynamic
`availability or exergy and the large volumetric flow rate of
`air.
`1.2. Traditional Liquid Cooling and its Limitations
`Liquid cooling can reduce each of the aforementioned
`causes of inefficiency; facilitate waste heat recovery; and
`increase the thermodynamic availability of the heat removed
`[11]. Ellsworth and Iyengar [12] compared the facility level
`cooling performance of an air/liquid hybrid supercomputing
`cluster to its air-cooled equivalent with traditional chilled
`water and CRACs. They also predicted the efficiency gains
`achievable with an all-liquid technology and that same
`technology operating in a chiller-less or cooling-tower-only
`(water economizer) mode (Figure 1). The latter would result
`in a 90% reduction in cooling energy consumption versus the
`air-cooled cluster. While the efficiency of an all-liquid
`cluster was not shown to be dramatically higher than that of
`an air/liquid hybrid, the elimination of facility level air
`cooling
`infrastructure would
`likely
`reduce
`facility
`construction cost.
`However, implementation of traditional liquid cooling
`schemes, be they single- or two-phase, indirect-contact or
`immersion, is complicated by the number and variety of heat
`generating devices on a server and the requirement that each
`server within a rack be “hot swappable,” meaning that it can
`be removed and replaced without disturbing the operation of
`others. This makes it challenging to capture all of the heat
`generated on a printed circuit board (PCB) and move it to an
`external liquid stream. As a result, hybrid air-liquid systems
`bear inherent costs for design [13] and fabrication of cold
`plates, redundant pumps, plumbing, quick disconnects (QDs),
`controls, and heat exchangers [14] (Table 1). All-liquid
`systems (Table 2) are often more complicated, requiring
`additional or more complex cold plates, clamshells, or
`hermetic electrical connectors. Performance for many is
`limited by secondary even ternary thermal interfaces and fluid
`temperature
`glide. Hydrofluorocarbon
`(HFC)
`and
`perfluorocarbon (PFC) systems are prone to leakage and
`resultant global warming emissions at intractable sites like
`couplings.
`
`Cooling Tower
`Chiller
`Facility Pumps
`Rack Pumps
`CRAC
`
`1
`
`0.8
`
`0.6
`
`0.4
`
`0.2
`
`0
`
`Air Cooled
`
`All-Liquid All-Liquid with
`Air/Liquid
`Economizer
`Hybrid
`Figure 1: Normalized cooling power consumption of
`different components for various technologies [12]
`
`# Description
`224 Machined/brazed copper cold plates, clamps and TIMs
`168 Inter cold plate brazed copper manifold assemblies
`28 Brazed copper header assemblies
`28 Centrifugal blowers
`14 EMI gasket shield assemblies
`28 High performance quick disconnects (QDs)
`Rack Level
`2 Large brazed copper manifold assemblies
`1 Rear door heat exchanger
`2 Plate heat exchangers
`2 Reservoir tanks
`2 Proportional metering valves
`2 Pressure relief valves
`2 Check valves
`2 Solenoid isolation valves
`12 Temperature sensors
`6 Liquid level sensors
`2 Magnetically-coupled centrifugal pumps
`8 High performance large bore QDs
`1 Pressure relief valves
`TABLE 1: Partial list of cooling components in a 72kW
`air/liquid hybrid rack [14]
`
`See List
`a,b,c,d,
`(e),(f),g
`a,b,d2,
`(e)
`a,c,(e),
`(f),g
`
`Technology
`1. Pump water or HFC refrigerant onto each node and through
`cold plates12.
`2. Cold plates in contact with, not connected to server/node.
`Transfer heat to interface via heat pipes etc[15, 16]
`3. Pump dielectric fluid onto each server/node enclosed in
`direct immersion cooling clamshell [17].
`Shortcomings ()=depends on fluid technology
`a. Cost and environmental impact of cold plates, pumps, etc.
`b. Difficult to capture all heat without complex cold plate assemblies.
`c. QD leakage risk.
`d. Secondary thermal interface(s) (TIM2) impacts performance.
`e. Fluid glide effects performance (single-phase)
`f. Global warming emissions from fluid loss at intractable sites
`g. Risk of leakage at clamshell, QD or electrical vias.
`TABLE 2: Shortcomings of some commonly cited all-liquid
`cooling technologies
`
`Tuma, The Merits of Open Bath Immersion Cooling …
`
`26th IEEE SEMI-THERM Symposium
`
`Authorized licensed use limited to: Alexander Karl. Downloaded on June 16,2021 at 17:17:42 UTC from IEEE Xplore. Restrictions apply.
`
`Immersion Systems LLC – Ex. 1013
`PGR 2021-00104 (U.S. 10,820,446 B2)
`2 of 9
`
`

`

`immersed in the rinse sump where ultrasonics may be used to
`displace particulate (2). It is next moved from the rinse sump
`back to the vapor where clean condensing vapor again rinses
`the part (3). After a brief pause above the saturated vapor
`zone, during which solvent remaining on the part quickly
`evaporates (4), it leaves the machine dry.
`Vapor degreasers can clean thousands of parts per day
`with little fluid consumption despite the fact that they are
`open most of the time and only loosely lidded when not in
`use. Low loss rates are due in part to the secondary coils that
`often operate below 0°C. These set the solvent partial
`pressure that drives diffusion out of the bath through the
`freeboard region during use.
`
`Clearly a simple, compact, inexpensive liquid cooling
`technique
`is needed
`that minimizes natural
`resource
`consumption and global warming emissions. It must capture
`all heat while minimizing the junction-to-water temperature
`difference. It should be modular, scalable and should easily
`accommodate evolving hardware [18].
`1.3. Immersion Cooling History
`Passive 2-phase (evaporative) immersion cooling has been
`used for decades
`to cool high value electronics
`like
`transformers,
`traction
`inverters
`(Figure 2), specialized
`computers and klystrons. This technology is still in use
`today, being favored for its simplicity, reliability, power
`density and performance.
`These systems generally use sealed pressure vessels with
`hermetic electrical connections. They are evacuated and
`filled much like refrigeration systems and as such do not lend
`themselves to field service. It can be costly and complex to
`create
`such
`a hermetic
`enclosure
`for
`commodity
`computational electronics with their myriad of swappable
`components and electrical connections. For this reason, many
`people dismiss the idea of immersion in the context of
`datacom equipment. As will be shown, these measures are by
`no means necessary for static systems that remain at nearly
`constant temperature and power output.
`
`Figure 2: Immersion-cooled traction inverter from mining
`haul truck (photo courtesy of Siemens)
`1.4. The Open Bath Vapor Degreaser
`The management of fluid in vapor degreasers [19] is
`directly applicable to the concept discussed in this work.
`These ubiquitous machines are commonly used to clean parts
`ranging from screws and bearings to printed circuit boards,
`orthopedic implants and diesel engines. Degreasers comprise
`a tank, open at the top and fitted around its interior periphery
`with primary and secondary cooling coils (Figure 3). The
`tank is partitioned below a certain level to create two baths or
`“sumps” that are filled with a volatile solvent. The boil sump
`is heated from below causing the solvent within it to boil.
`Vapor rises to the height of the primary coils creating a
`saturated vapor zone beneath them. The condensed vapor
`flows back to the rinse sump, usually through a water
`separator. Because the sub-cooled solvent condensate is
`distilled, it is quite free of dissolved contaminants.
`The sequence of cleaning steps is also shown in Figure 3.
`The part to be cleaned is placed in a wire basket and lowered
`into the saturated vapor zone (1). Vapor condenses on the
`part beginning the cleaning process. The part is next
`Tuma, The Merits of Open Bath Immersion Cooling …
`
`Figure 3: Schematic of an open bath vapor degreaser.
`2. Open bath Immersion Cooling Concept
`The concept discussed in this work is based on the
`premise that electronics can be immersion cooled in semi-
`open baths similar in many ways to a vapor degreaser (Figure
`4). The term “semi” denotes a bath that is closed when access
`is not needed much like a chest-type food freezer. Like a
`freezer, it operates at atmospheric pressure and has no
`specialized hermetic connections for electrical inputs and
`outputs.
`In this concept, each server or node plugs into a backplane
`in the bottom of a tank (versus the back of a rack) that is
`partially filled with a volatile dielectric working fluid.
`Electrical connections from the backplane enter a conduit
`beneath the liquid level and exit the top of the tank. A vapor
`condenser integrated into the tank is cooled by tower water or
`water used at some distance for comfort heating. If desired,
`the vapor can flow passively to an outdoor natural draft
`cooling tower to transfer its heat passively to outdoor air
`without water as an intermediate. This open bath concept has
`a multitude of advantages over the other liquid cooling
`schemes that have been proposed.
`26th IEEE SEMI-THERM Symposium
`
`Authorized licensed use limited to: Alexander Karl. Downloaded on June 16,2021 at 17:17:42 UTC from IEEE Xplore. Restrictions apply.
`
`Immersion Systems LLC – Ex. 1013
`PGR 2021-00104 (U.S. 10,820,446 B2)
`3 of 9
`
`

`

`3. Thermal Performance
`The system thermal performance has two components.
`The first is at the board level and is device dependent. It is
`quantified by considering the junction-to-fluid temperature
`difference of the most difficult to cool component, the central
`processing unit (CPU). The second is the temperature
`difference from the fluid to the facility water. The fluid
`temperature, Tf, is the fluid’s atmospheric boiling point,
`
`(1)
`
`T
`
`
`
`
`
`)
`
`.
`
`P(T
`T
`sat
`atm
`b
`f
`3.1. Junction-to-Fluid Performance
`The performance capabilities of passive 2-phase heat
`transfer with dielectric coolants are well documented [20].
`Despite its simplicity and passive nature, it is not an inferior
`technology. Passive 2-phase immersion has been used to
`cool power semiconductors dissipating over Qc”=1100W/cm2
`with Tj-f=45°C, a performance level competitive with the
`best emerging pumped water technologies [21]. A typical CPU
`package configuration with its integrated heat spreader (IHS)
`is almost ideally suited for passive 2-phase immersion
`cooling. In most cases, it requires only the addition of a
`100m thick porous metallic boiling enhancement coating
`(BEC).
` These coatings produce boiling heat transfer
`coefficients, H>10 W/cm2-K at heat fluxes exceeding
`Q″=30W/cm2. Incorporating this technology directly onto the
`IHS during package assembly eliminates the secondary
`thermal interface common to many liquid cooling schemes
`without altering the package assembly process.
`
`Principal among them (Table 3) is the fact that most of the
`aforementioned air and
`liquid cooling hardware are
`eliminated as are considerations relating to their integration,
`reliability and power consumption. Power density and
`efficiency are very high and fire protection is intrinsic to the
`technology. Of course, there are other considerations, such as
`fugitive fluid emissions. Since these occur at one point rather
`than at countless seals and junctions, they are easily
`quantified and mitigated with simple techniques as will be
`discussed.
`
`Figure 4: Water-cooled open bath immersion concept
`
`Attribute
`1. No quick disconnects (QDs), clamshells, hermetic
`connectors.
`2. No pumps, fans, economizers, compressors
`3. No server/rack-level cold plates and plumbing
`4. Fluid losses at one point
`5. Intrinsic fire protection
`6 Tjf is low, no fluid glide
`7. High power density
`Advantage
`a. Less risk due to leakage
`b. Reduced power consumption
`c. Uses less natural resources
`d. Reduced cost and complexity
`
`e. Reduced greenhouse gas emission
`f. Uniform device temperatures
`g. More efficient capture of heat
`h. Reduced facility construction cost
`
`See list
`a,c,d,(e)
`
`b,c,d,e,h
`a,c,d
`a, e
`h
`g
`h
`
`Tc
`
`Ts
`
`BEC
`IHS
`Solder
`Silicon
`Junction
`
`Tf=Tsat(Patm)
`
`20x20mm chip
`Rj-c=0.008
`Rc-s=0.007
`Rs-f=0.030
`Rj-f=0.045°C/W
`
`+
`
`0
`
`10
`5
`Ac [cm2]
`
`15
`
`Tj
`
`0.15
`
`0.10
`
`0.05
`
`0.00
`
`Rs-f [°C/W]
`
`PCB
`
`TABLE 3: Advantages of open bath immersion cooling
`compared with other liquid and hybrid techniques
`
`Figure 5: Sink-to-fluid performance as a function of die size
`and
`total
`junction-to-fluid performance
`for
`20x20mm die in a hydrofluoroether (HFE) liquid
`
`Tuma, The Merits of Open Bath Immersion Cooling …
`
`26th IEEE SEMI-THERM Symposium
`
`Authorized licensed use limited to: Alexander Karl. Downloaded on June 16,2021 at 17:17:42 UTC from IEEE Xplore. Restrictions apply.
`
`Immersion Systems LLC – Ex. 1013
`PGR 2021-00104 (U.S. 10,820,446 B2)
`4 of 9
`
`

`

`The resultant sink-to-fluid resistance, Rs-f, is dependent on
`the chip size (Figure 5). For a typical 20x20mm chip, Rs-f
`=0.03°C/W. The additional resistances from sink-to-junction
`based on a 20x20mm thinned die and solder interface total
`0.015°C/W[23]. With Rj-f=0.045°C/W, a 200W processor has
`an average junction-to-fluid temperature difference,
`
`T
`
`
` 
`f
`
`j
`
`QR
`f
`j
`
`
`CPU
`
` ,
`
`(2)
`
`of about 9°C. It is likely this could be improved by
`optimizing a secondary heat transfer path through the package
`substrate.
`It is worth noting that although this passive technique
`requires a first level interface (TIM1), the resultant chip-to-
`fluid thermal resistance is lower than that achievable with
`direct-die-contact spray or jet impingement schemes based on
`dielectric coolants. These active techniques achieve heat
`transfer coefficients of H=1-3W/cm2-K [23,24] resulting in Rc-f
`>0.09°C/W, for the 20x20mm die discussed earlier.
`
`3.2. Fluid-to-Water Performance
`Previous research 21 has shown that a high density, water-
`cooled condenser can achieve a volume-specific, fluid-to-
`water inlet resistance,
`
`
`T
`cond
`Q
`
`V
`
`R
`
`
`wf
`
`
`
`T
`
`w
`
`f
`
` ,
`
`cond
`
`(3)
`
`However, it is worthwhile exploring what power density
`could be cooled. Previous research of immersion cooling of
`power electronics [21] suggests that power densities are limited
`more by the electrical bus than by the capabilities of
`immersion. The authors estimated that 100cc of fluid are
`required to cool a 1kW module if density limitations are
`exercised.
`Additional experiments were conducted with a form factor
`more consistent with a high density server. The simulated
`printed circuit board (PCB) shown in Figure 6 holds 20 heater
`assemblies comprised of 19x19mm 200W ceramic heaters
`epoxy bonded on one side to 30x30x3mm copper heat
`spreaders enhanced on the opposite side with a boiling
`enhancement coating (BEC). A thermocouple in the fluid, Tf,
`and one within each heat spreader, Ts, permit calculation of
`the individual thermal resistances and ensure that the heaters
`have not passed into the film boiling regime.
`The simulated PCB was immersed in a confined vertical
`channel of the same area as the board with 4 and 7mm gaps
`between the boiling surface and the adjacent wall. This
`assembly was able to dissipate 4kW (200W per heater
`assembly) for a 4mm gap at atmospheric pressure when the
`bath was filled with C3F7OCH3, a hydrofluoroether working
`fluid. Incipience overshoot did not exceed 7°C for any heater
`assembly. The average Rs-f are shown in Figure 6, bracketed
`by ½ standard deviation on each side. 4kW equates to a PCB
`level heat flux of Q”=11.7W/cm2 versus 1.7W/cm2 for the
`Cray X1E spray-cooled supercomputer [24]. These data
`suggest that 1kW/cm of bath normal to the PCB and 100cc of
`fluid per kW are certainly attainable, if only from a thermal
`point of view. Also, the potential for reduction of materials
`and waste associated with PCB manufacture is significant.
`
`of 1.4ºC-cm3/W under conditions of low water temperature
`glide. This number can be used in a log mean temperature
`difference (LMTD) analysis to predict condenser performance
`when the water temperature rises significantly:
`
`LMTD
`
`
`
`R
`
`Q
`cond
`V
`cond
`
`wf
`
`
`20X17X2.5cm BOARD
`
`(4)
`
`20 Heater
`Assemblies
`
`HEATER ASSEMBLY
`DETAIIL
`
`BEC
`
`Epoxy
`
`Ceramic
`Heater
`
`Copper Boiler
`30x30x3mm with
`Thermocouple
`
`Ts
`
`7mm gap
`4mm gap
`
`50
`
`25
`
`0
`
`1000xRs-f [°C/W]
`
`Bath
`
`4-7mm
`
`50
`
`100
`
`150
`
`200
`
`Q c [W]
`Figure 6: Experimental apparatus to demonstrate power
`density capabilities of immersion in a vertical PCB
`orientation
`
`Glide
`
`
`
`T
`w
`
`
`
`T
`i,w
`
`
`
`T
`o,w
`
`
`
`Q
`cond
`Cm
`
`
`w
`
`
`
`
`
`(5)
`
`The resultant inlet water temperature, Tw,i, is
`
`(6)
`
`(7)
`
`T
`i,w
`
`
`
`T
`
`f
`
`
`
`a
`
`
`1
`
`a
`
`
`
`glide
`
`.
`
`
`
`Glide
`LMTD
`
`
`
`a
`
`
`
`exp
`
`where
`
`4. Power Density
`By eliminating the heat sinks, fans and airspace normally
`required for air cooling, an immersion cooled server can, in
`principle, be quite compact. Current off-the-shelf air-cooled
`hardware, spread out as it is to facilitate air cooling, is not
`well suited for immersion. Determining how densely a server
`could be packaged is beyond the scope of this work.
`
`Tuma, The Merits of Open Bath Immersion Cooling …
`
`26th IEEE SEMI-THERM Symposium
`
`Authorized licensed use limited to: Alexander Karl. Downloaded on June 16,2021 at 17:17:42 UTC from IEEE Xplore. Restrictions apply.
`
`Immersion Systems LLC – Ex. 1013
`PGR 2021-00104 (U.S. 10,820,446 B2)
`5 of 9
`
`

`

`
`
`5. Working Fluid
`Table 4 shows one hydrofluoroether (HFE) and two
`fluoroketone (FK) [25] working fluids possessing the requisite
`thermophysical, safety and material compatibility properties.
`The dielectric properties of the FK fluids are similar to those of
`C6F14, a PFC fluid commonly used in immersion systems,
`while the HFE has significantly higher dielectric constant and
`lower resistivity. This may limit the utility of HFEs in some
`applications. The Global Warming Potential (GWP) of the
`HFE fluid is less than 60. The FK fluids have a GWP of 1,
`among the lowest of man-made compounds. The first of these
`FK fluids is already widely used globally as a Halon
`replacement for fire protection. Both of the FK fluids shown
`are being field tested in immersion applications at this time.
`
`
`Propertya
`C6F14
`Molecular Formula
`PFC
`Fluid Type
`56
`Tb [°C]
`<-100
`Tfreeze [°C]
`None
`Tflash [°C]
`12.0
` [mN/m]
`0.057
`k [W/m-K]
`1050
`C of liquid [J/kg-K]
`1680
` [kg/m3]
`0.40
` [cSt]
`88
`L. Heat @ Tb [kJ/kg]
`30.9
`Psat at 25ºC [kPa]
`350
`Psat at 100ºC [kPa]
`Resistivity [Gohm-cm] 1,000,000
`Dielect. Const.
`1.76
`DS [kV@2.54mm]
`~40
`GWPb
`9300
`EGc [ppmv]
`NA
`a. Properties at 25°C unless noted
`b. GWP based on 100 year integration time horizon
`c. 8-hour time weighted average (TWA) Exposure Guideline
`
`Working Fluid
`C6F9OH5
`C6F12O
`HFE
`FK
`76
`49
`<-100
`<-100
`None
`None
`13.6
`10.8
`0.068
`0.059
`1220
`1103
`1420
`1600
`0.41
`0.4
`119
`88
`15.7
`40.4
`206
`441
`0.1
`10,000
`7.3
`1.84
`~40
`~40
`55
`1
`200
`150
`
`C7F14O
`FK
`74
`<-100
`None
`12.3
`~0.06
`1130
`1670
`0.52
`90
`15.7
`228
`10,000
`1.85
`~40
`1
`150
`
`TABLE 4: Possible Working Fluids
`
`
`
`
`6. Fluid Losses
`The viability of open bath immersion technology depends
`primarily on the rate of fluid loss. It affects the cost of
`ownership but also the greenhouse gas emissions and the
`likely human exposure in the datacenter. The fluid loss
`mechanisms associated with purging air from low pressure
`sealed systems are well understood as are techniques for
`mitigating them [21] One simple technique is to pass the
`exiting
`air/vapor
`stream
`through
`an
`on-demand,
`thermoelectrically-cooled condenser or “trap” that condenses
`the vapor allowing it to return to the system. Similar
`techniques can be applied for open bath immersion. There are
`different loss mechanisms associated with each stage of
`operation.
`
`
`
`P
`atm
`
`
`
`
`)T(P
`a
`sat
`
`Kn
`
`l
`
`n
`v
`
`
`
`(11)
`
`The saturated vapor zone will rise until it contacts
`sufficient condenser surface area to condense the vapor being
`generated. This results in reduced headspace volume above
`the vapor zone, displacement of the air/vapor mixture within
`it and losses of
`
`
`)T(P
`t
`sat
`)T(P
`
`t
`sat
`
`P
`atm
`
`.
`
`
`
`
`
`P
`atm
`
`
`
`n
`v
`
`
`
`
`V)T(P
`a
`sat
`RT
`a
`
`
`
`V
`
`f,H
`
`i,H
`
`
`
`)T(P
`t
`sat
`)T(P
`
`t
`sat
`
`P
`atm
`
`.
`
`(12)
`
`
`
`The headspace will saturate to Tw. This too displaces air
`and results in fluid loss of
`
`
`n
`v
`
`
`
`
`
`
`V)T(P)T(P
`
`sat
`w
`sat
`a
`RT
`w
`
`f,H
`
`)T(P
`t
`sat
`)T(P
`
`sat
`t
`
`P
`atm
`
`.
`
`
`
`(13)
`
`Tuma, The Merits of Open Bath Immersion Cooling …
`
`
`
`
`
`
`26th IEEE SEMI-THERM Symposium
`
`Authorized licensed use limited to: Alexander Karl. Downloaded on June 16,2021 at 17:17:42 UTC from IEEE Xplore. Restrictions apply.
`
`
`
`6.1. During Filling
`If the liquid is added slowly from the bottom of the tank,
`the amount of vapor in the displaced air is negligible (Figure
`7a). Fluid will then evaporate until the headspace volume,
`VH,i, above it is saturated with vapor at ambient temperature,
`Ta, which is here assumed to be lower than the water
`temperature, Tw. As this occurs, air is displaced. The
`maximum amount of vapor carried with that air can be
`calculated as
`
`
`n
`v
`
`
`
`2
`
`)T(PV
`a
`sat
`i,H
`PRT
`2
`atm
`a
`
`.
`
`
`
`
`
`
`
`
`
`(8)
`
`
`The resultant losses can be mitigated by passing the
`exiting airstream through a cold trap operating at Tt so that
`
`
`.
`
`
`
`(9)
`
`
`
`)T(P
`sat
`t
`
`2
`
`21
`
`)T(P)T(P
`sat
`t
`sat
`a
`
`
`
`
`
`V
`i,H
`PRT
`atm
`a
`
`n
`v
`
`
`
`
`This analysis assumes that the headspace is well mixed as the
`fluid evaporates.
`6.2. During Start Up
`When the servers are turned on (Figure 7b), the fluid
`begins to boil. Air that was dissolved in the fluid,
`
`
`Kn
`
`l
`
`n
`
`air
`
`
`
`
`
`P
`atm
`
`
`
`)T(P
`a
`sat
`
`,
`
`
`
`
`
`
`
`(10)
`
`is first liberated, pushing some of the saturated air/vapor
`mixture through the trap. The resultant losses are
`
`
`Immersion Systems LLC – Ex. 1013
`PGR 2021-00104 (U.S. 10,820,446 B2)
`6 of 9
`
`

`

`
`
`
`Figure 7: Bath upon and after filling a.), during and after start up b.) and during load fluctuations in operation c.)
`
`
`
`
`
`
`6.3. During Steady State Operation
`During operation (Figure 7c) there are losses associated
`with fluctuating power levels that cause the vapor volume to
`rise and fall by VH. These are
`
`
`
`
`P
`atm
`
`
`
`n
`v
`
`
`
`
`V)T(P
`
`sat
`w
`RT
`w
`
`H
`
`)T(P
`t
`sat
`)T(P
`
`t
`sat
`
`P
`atm
`
`.
`
`
`
`(14)
`
`7. Results
`Table 5 summarizes results of the thermal performance
`calculations for the modular 80kW bath shown in Figure 8.
`If a commercially available fluoroketone fluid is used (FK1,
`Tf=49°C) in the bath, a 15gpm water flow rate could produce
`average Tj<60°C with a water inlet temperature, Tw,i=28°C. If
`the average Tj and the water flow rate are allowed to rise to
`83°C and 30gpm, respectively, a very useful Tw,i=62°C water
`temperature may be possible with a higher boiling fluid. The
`tank footprint power density is 130kW/m2, higher than the
`52kW/m2 level typical of air-cooled or hybrid air-liquid racks
`and beyond most long term industry projections [26] of what
`may be achievable with other air and liquid cooling
`technologies. With no real estate area and construction
`volume devoted to housing air handlers, plena, hot/cold aisles,
`etc., an all-liquid facility (Figure 9) might achieve 25kW/m2
`(2300W/ft2) versus 2.2kW/m2 (200W/ft2)[26] for most air
`cooled facilities.
`
`Processor Power [W]
`T j-f for 20x20mm CPU [°C]
`Power per node [kW]
`Number Nodes per Tank
`Total Tank Power [kW]
`Condenser Volume [cc]
`Log Mean Temp. Difference [°C]
`FK1
`Working Fluid
`T b =T sat (P atm )=T f [°C]
`49
`Resultant T j [°C]
`58.0
`30
`15
`30
`15
`10
`Water Flow [gpm]
`113.6
`56.8
`113.6
`56.8
`37.9
`Water Flow [liter/min]
`Water glide =T w [°C]
`10.1
`20.1
`10.1
`20.1
`30.2
`T w,i [°C]
`62.0
`53.4
`37.0
`28.4
`18.7
`Table 5: Water temperature calculations for 1 tank
`
`FK2
`74
`83.0
`
`
`
`200
`
`92
`
`40
`80
`22,000
`5.5
`
`
`
`
`26th IEEE SEMI-THERM Symposium
`
`
`In the calculations to follow, it was assumed that the power
`level and hence the vapor height underwent a single cycle per
`day of 25%.
`Finally, fluid will diffuse through the conduit housing the
`electrical IO. Experiments indicate that the diffusion rate is
`on the order of 100g-cm/cm2-day. If the cross sectional area
`of the diffusion path (conduit area minus wire conductors,
`etc.) is kept below 2cm2 and the length 2 meters, diffusion
`rates are near 1 g/day.
`
`
`Figure 8: Modular 80kW tank dimensions
`
`Tuma, The Merits of Open Bath Immersion Cooling …
`
`
`
`
`
`
`
`
`
`
`Authorized licensed use limited to: Alexander Karl. Downloaded on June 16,2021 at 17:17:42 UTC from IEEE Xplore. Restrictions apply.
`
`Immersion Systems LLC – Ex. 1013
`PGR 2021-00104 (U.S. 10,820,446 B2)
`7 of 9
`
`

`

`Figure 9: Conceptual aerial view and interior cross sections
`of air and water cooled immersion concepts
`
`Table 6 summarizes results of the fluid loss calculations
`for the modular 80kW bath shown in Figure 8 as a function of
`the vapor trap operating temperature, Tt, assuming a single
`25% load fluctuation per day. With Tt=10°C, annual fluid
`consumption cost at $123/yr compares favorably with the
`$184/yr cost of operating rack level pumps[12] at $0.05/kWh
`and the $2,800/yr cost of operating just the server fans in a
`typical air-cooled rack assuming they use 80W per kW of
`server power [2]. If the fluid GWP=1, the greenhouse gas
`emissions resulting from annual fluid loss are 0.2% of those
`associated with operating
`the aforementioned pumps
`assuming 7.18x10-4 metric tons CO2/kWh [27]. Use of an HFE
`with GWP=55 would raise this to 5%.
`
`Loss
`
`Tt [°C]
`Saturate empty tank [g]
`Beginning boil [g]
`Rise of vapor [g]
`Saturate headpace to P sat (T w ) [g]
`
`10
`45.9
`83.3
`59.8
`30.3
`219
`9.65
`6.7
`1
`2794
`123.0
`2.8E-03
`0.154
`
`20
`57.7
`152.6
`109.5
`55.5
`375
`16.5
`12.2
`1
`4815
`212
`4.8E-03
`0.265
`
`Eqn.
`5
`0
`-
`38.8
`32.1
`9
`62.4
`46.9
`11
`44.8
`33.6
`12
`22.7
`17.0
`13
`169
`130
`Total startup [g]
`7.42
`5.70
`Total Startup Fluid Cost at $0.044/g [$]
`5.0
`3.7
`Due to load cycle of 25% [g/day]
`10
`1
`1
`Diffusion through conduit [g/day]
`-
`2183
`1732
`Fluid lost [g/yr]
`96.0
`76.2
`Resultant cost [$/yr]
`2.2E-03
`FK fluid Metric Tons CO2 Equivalent (MTCE) 1.7E-03
`0.120
`HFE fluid MTCE
`0.095
`MTCE comparison for pumped water and air cooled
`Water pumps 5.8W/kW for 1 yr
`2.9
`Rack fans at 80W/kW for 1 yr
`40.3
`
`However, commonly cited all-liquid technologies are
`costly. They require significant engineering and hardware
`such as cold plates, pumps, plumbing, couplings, valves, and
`clamshells that consume natural resources and are prone to
`mechanical failure.
`Passive 2-phase immersion cooling has unique attributes:
`• All of the aforementioned node level and most of the rack
`level liquid cooling hardware are eliminated reducing
`environmental impact and simplifying design.
`• Low Tj-w increases the availability of heat and the ability
`to use full-time and even dry (non evaporative) cooling
`tower water.
` Alternatively, an outdoor-air-cooled
`condenser can be employed and water eliminated.
`• The tank (rack) and facility footprint power densities are
`estimated to be 2.5 and 10 times, respectively, those
`achievable with traditional air cooling.
`• A PCB level power density of ~12W/cm2 was demonstrated
`that
`only
`electronic
`and
`not
`thermal
`implying
`considerations limit node level power density
`• All devices are at same temperature (no glide).
`• The fluid cost is estimated to be $8 (100cc) per kW, less
`than the cost of copper used in two 2U heat sinks.
`• Fluid consumption on startup is estimated to be <25¢/kW.
`Annual consumption is estimated to be 1-3$/kW-year, less
`than 4% of the cost of running the server chassis fans in an
`equivalent air-cooled system at 5¢/kW-hr.
`• The resultant greenhouse gas emissions are 0.004-0.7% and
`0.1-5% (depending on fluid chemistry) those associated
`with the power draw of the server chassis fans in an air-
`cooled system and the rack pumps in a pumped water
`system, respectively.
`• Unlike most pumped r

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket