`United States Court of Appeals
`FOR THE DISTRICT OF COLUMBIA CIRCUIT
`
`
`
`Argued May 5, 2022
`
`
`Decided August 23, 2022
`
`No. 20-1343
`
`CONSTELLATION MYSTIC POWER, LLC,
`PETITIONER
`
`v.
`
`FEDERAL ENERGY REGULATORY COMMISSION,
`RESPONDENT
`
`BRAINTREE ELECTRIC LIGHT DEPARTMENT, ET AL.,
`INTERVENORS
`
`
`
`Consolidated with 20-1361, 20-1362, 20-1365, 20-1368,
`21-1067, 21-1070
`
`
`On Petitions for Review of Orders
` of the Federal Energy Regulatory Commission
`
`
`
`
`
`Matthew A. Fitzgerald argued the cause for petitioner
`Constellation Mystic Power, LLC. With him on the briefs were
`Noel H. Symons and Katlyn A. Farrell.
`
`
`Jeffrey A. Schwarz argued that cause for State petitioners.
`With him on the briefs were Seth A. Hollander, Assistant
`
`
`
`
`
`2
`
`Attorney General - Special Litigation, Office of the Attorney
`General for the State of Connecticut, Scott H. Strauss, Amber
`L. Martin Stone, Kirsten S. P. Rigney, Robert Snook, Assistant
`Attorney General - Environment, Office of the Attorney
`General for the State of Connecticut, Andrew Minikowski and
`Julie Datres, Staff Attorneys, Ashley M. Bond, Maura Healy,
`Attorney General, Office of the Attorney General for the
`Commonwealth of Massachusetts, Christina Belew, Assistant
`Attorney General, Jason Marshall, and Phyllis G. Kimmel.
`
`
`Scott H. Strauss, Jeffrey A. Schwarz, Amber L. Martin
`Stone, and John P. Coyle were on the briefs for intervenors
`Braintree Electric Light Department, et al. in support of State
`petitioners.
`
`
`Robert M. Kennedy and Carol J. Banta, Senior Attorneys,
`Federal Energy Regulatory Commission, argued the causes for
`respondent. With them on the brief were Matthew R.
`Christiansen, General Counsel, and Robert H. Solomon,
`Solicitor.
`
`
`John P. Coyle argued the cause for intervenors Braintree
`Electric Light Department, et al. in support of respondent.
`With him on the brief were Scott H. Strauss, Jeffrey A.
`Schwarz, and Amber L. Martin Stone.
`
`
`Michael J. Thompson, Ryan J. Collins, and Maria Gulluni
`were on the brief for intervenor ISO New England, Inc. in
`support of respondent.
`
`
`Before: SRINIVASAN, Chief Judge, HENDERSON and RAO,
`Circuit Judges.
`
`
`Opinion for the Court filed PER CURIAM.
`
`
`
`
`
`3
`
`PER CURIAM: In March 2018, Constellation Mystic Power,
`LLC (Mystic)—a subsidiary of Exelon Generation Company,
`LLC (ExGen), which itself is a subsidiary of Exelon
`Corporation (Exelon)1—announced its intention to retire the
`Mystic Generating Station (Mystic Station), a natural gas-fired
`generator serving the greater Boston metropolitan area, after
`the facility’s existing capacity obligations expired in May
`2022. The region’s independent system operator, ISO New
`England, concluded
`that Mystic Station’s
`loss would
`exacerbate anticipated stresses on the region’s electricity
`network during winter months and increase the risk of rolling
`blackouts. ISO New England also found that Mystic Station’s
`retirement risked the closure of its sole fuel source, the Everett
`Marine Terminal (Everett)—a liquified natural gas (LNG)
`import and regasification facility currently owned and operated
`by an ExGen subsidiary—adding to the risk of blackouts in the
`region.
`
`In light of these findings, ISO New England entered into a
`cost-of-service agreement with Mystic and ExGen to keep two
`of Mystic Station’s generating units, referred to as Mystic 8 and
`9, in service between June 2022 and May 2024. The parties
`filed the proposed agreement (Mystic Agreement) with the
`Federal Energy Regulatory Commission (Commission or
`FERC). The Commission ultimately approved the terms of the
`Mystic Agreement, albeit with significant modifications.
`
`
`1 In February 2022, after the petitions for review here had been
`filed, Exelon consummated a spinoff transaction that placed
`ExGen—which was renamed Constellation Energy Generation,
`LLC—and Mystic under the corporate parentage of Constellation
`Energy Corporation. Despite this transaction, we will refer to
`Mystic’s parents as ExGen and Exelon, as the parties have done,
`unless context dictates otherwise.
`
`
`
`
`
`4
`
`At issue are six Commission orders related to its approval
`of the Mystic Agreement. See Constellation Mystic Power,
`LLC, 164 FERC ¶ 61,022 (July 13, 2018) (July 2018 Order);
`Constellation Mystic Power, LLC, 165 FERC ¶ 61,267 (Dec.
`20, 2018) (December 2018 Order); Constellation Mystic
`Power, LLC, 172 FERC ¶ 61,043 (July 17, 2020) (First July
`2020 Rehearing Order); Constellation Mystic Power, LLC, 172
`FERC ¶ 61,044 (July 17, 2020) (Second July 2020 Rehearing
`Order); Constellation Mystic Power, LLC, 172 FERC ¶ 61,045
`(July 17, 2020) (Compliance Order); Constellation Mystic
`Power, LLC, 173 FERC ¶ 61,261 (Dec. 21, 2020) (December
`2020 Rehearing Order). Two groups of petitioners now seek
`review of those orders: Mystic and a group of New England
`state regulators (State Petitioners).2 As detailed infra, we
`dismiss Mystic’s petition for review in part and deny it in part;
`we grant the State Petitioners’ petitions.
`
`I. BACKGROUND
`
`A. Statutory Background
`
`Section 201(b) of the Federal Power Act (FPA) grants the
`Commission jurisdiction of the transmission and wholesale
`sale of electric energy in interstate commerce. 16 U.S.C.
`§ 824(b); see New York v. FERC, 535 U.S. 1, 6–7 (2002). The
`FPA provides that “[a]ll rates for or in connection with
`jurisdictional sales and transmission service are subject to
`review by FERC to ensure that the rates are just and reasonable
`
`
`2 The State Petitioners include the Connecticut Public Utilities
`Regulatory Authority, the Connecticut Department of Energy and
`Environmental Protection, the Connecticut Office of Consumer
`Counsel (collectively, Connecticut Parties), the Attorney General of
`the Commonwealth of Massachusetts (Massachusetts AG) and the
`New England States Committee on Electricity, Inc. (States
`Committee).
`
`
`
`
`
`5
`
`and not unduly discriminatory or preferential.” New England
`Power Generators Ass’n v. FERC (NEPGA), 881 F.3d 202, 205
`(D.C. Cir. 2018)); see 16 U.S.C. §§ 824d(a), (e), 824e(a).
`Section 205 requires that all public utilities “file with the
`Commission . . . all rates and charges for any transmission or
`sale subject to the jurisdiction of the Commission,” 16 U.S.C.
`§ 824d(c), with the utility bearing the burden to show that its
`proposed rate is lawful, id. § 824d(e). See NEPGA, 881 F.3d at
`205. If the Commission determines that a rate is “unjust,
`unreasonable, unduly discriminatory or preferential,” it must
`set aside the rate and replace it with one that is just and
`reasonable. 16 U.S.C. § 824e(a)–(b). A negatively affected
`party may challenge a Commission-approved rate by filing a
`complaint with the Agency, and it carries the burden of
`demonstrating that the rate is unjust or unreasonable. See id.
`§ 824e(a)–(b). The reasonableness of a rate is assessed in light
`of the FPA’s goals of promoting reliable service at reasonable
`rates and developing plentiful energy supplies. See Consol.
`Edison Co. v. FERC, 510 F.3d 333, 342 (D.C. Cir. 2007); see
`also NAACP v. FPC, 425 U.S. 662, 669–70 (1976).
`
`B. The New England Electricity Market
`
`ISO New England is the independent system operator3 that
`operates the transmission facilities and administers the
`wholesale electricity markets across six states—Connecticut,
`Maine, Massachusetts, New Hampshire, Rhode Island and
`Vermont. The wholesale markets facilitate the sale of
`
`
`3 Independent system operators result from the unbundling of
`transmission and generation services—which were historically
`handled by a single, vertically integrated utility—and serve to
`coordinate, control and monitor the electricity transmission facilities
`owned by its member utilities in order to ensure nondiscriminatory
`access to all electricity generators. See Midwest Indep. Transmission
`Sys. Operator, Inc. v. FERC, 388 F.3d 903, 906 (D.C. Cir. 2004).
`
`
`
`
`
`6
`
`electricity by generators to electric utilities and electricity
`traders before its eventual sale to end-use consumers. The rates
`charged by ISO New England for access to its transmission
`system and the rules governing the wholesale markets under its
`purview are set out in a grid-wide tariff.
`
`In addition to ensuring adequate supply to meet present-
`day electricity demands, ISO New England must also ensure
`sufficient supplies to meet future needs. This is accomplished
`via a forward-capacity market, in which load serving entities—
`i.e., the utilities delivering electricity to end users—purchase
`capacity, which “is not electricity itself but the ability to
`produce it when necessary,” from generators. Pub. Citizen, Inc.
`v. FERC, 839 F.3d 1165, 1167–68 (D.C. Cir. 2016) (quoting
`Conn. Dep’t of Pub. Util. Control v. FERC, 569 F.3d 477, 479
`(D.C. Cir. 2009)). The forward-capacity market is conducted
`via an auction held three years in advance of a particular
`capacity commitment period. Generators submit bids reflecting
`the lowest price they will accept before exiting the market.
`During the “descending clock” auction, the capacity price is
`steadily lowered, causing bidding generators to exit. Once the
`amount of capacity offered reaches ISO New England’s
`projected capacity requirement for the commitment period, the
`auction stops, and those generators remaining in the market are
`paid the clearing price, regardless of their initial bids. See
`generally id. (explaining forward-capacity auction).
`
`Once a generator participates in a forward-capacity
`auction, it is automatically re-entered into every subsequent
`auction unless it affirmatively seeks to remove its capacity
`from the market for that commitment period or permanently,
`with the latter option constituting “retirement.” If a generator
`seeks to retire from the market, it must submit a Retirement De-
`List Bid eleven months before the auction corresponding to the
`period for which it intends to retire, which signals the
`
`
`
`
`
`7
`
`generator’s intent to exit the market if the clearing price falls
`below its bid price and gives ISO New England an opportunity
`to determine if the generator’s proposed retirement presents a
`service risk to the region. If ISO New England so concludes, it
`may ask the generator to remain in operation; if the generator
`accepts, it can then elect to receive either its initial bid price or
`a cost-of-service rate.
`
`C. Mystic 8 and 9
`
`Mystic 8 and 9 are combined-cycle natural gas-fired
`generating units with a combined summer capacity of about
`1,400 megawatts.4 The two units run on revaporized LNG
`imported via marine terminal, making them unique among
`other natural gas-fired units in the region, which run on vapor
`natural gas imported through regional pipelines.
`
`Following the restructuring of the Massachusetts energy
`market in the 1990s, Mystic Station was acquired from the
`Boston Edison Company by Sithe Energies, Inc. in 1999. Sithe
`shortly thereafter began construction of Mystic 8 and 9, with
`the two units beginning commercial operation as merchant
`generators in 2003; according to Mystic, the two units were
`constructed at a cost of just under $1 billion. In 2002, ExGen
`acquired Sithe but subsequently ran into financial troubles in
`connection with the construction of Mystic 8 and 9. In May
`2004, ExGen reached a settlement with its lenders, transferring
`Mystic Station to a special purpose entity owned by a
`consortium of lenders in exchange for the cancellation of debts.
`
`
`4 Mystic units 1 through 6 have been decommissioned, and the
`other units still in operation, Mystic 7 and Mystic Jet, are subject to
`Retirement De-List Bids but have not been designated as units
`necessary to meet reliability needs. None of these units is at issue
`here.
`
`
`
`
`
`8
`
`According to Mystic, as a result of this transaction, Mystic 8
`and 9 were valued at approximately $547 million.
`
`In 2010, after the special purpose entity declared
`bankruptcy, subsidiaries of Constellation Energy Group, Inc.
`purchased Mystic Station, as well as a separate natural gas-
`fired facility unrelated to the proceedings at issue, for $1.1
`billion. In 2012, Constellation Energy Group merged with
`Exelon. According to Mystic, as part of the merger, Mystic 8
`and 9 were independently appraised at $925 million. As a result
`of the merger, Mystic, which traces its parentage through
`ExGen to Exelon, became the owner of Mystic 8 and 9.
`
`D. The Everett Marine Terminal
`
`Everett, located on a property near Mystic Station, is
`Mystic 8 and 9’s sole source of revaporized LNG, making the
`two units “the only natural gas-fired units in the United States
`that are directly connected to an LNG import regasification
`facility.” Joint Appendix (J.A.) 7. Everett, the longest-
`operating LNG import terminal in the United States, has a
`storage capacity of 3.4 billion cubic feet and connects to, aside
`from Mystic 8 and 9, two outbound interstate pipeline facilities
`and a local gas company’s distribution facility.
`
`When the Commission proceedings began, Everett was
`owned by Distrigas of Massachusetts, LLC, a subsidiary of
`Engie Gas & LNG Holdings LLC, although Exelon was
`already in the process of purchasing the Everett facility.
`According to William Berg, an Exelon executive, the company
`determined that acquisition of Everett “was the best and most
`reliable option for Mystic to meet its existing capacity supply
`obligations through May 2022 without significant risk of non-
`performance.” J.A. 197. In late 2018, while the Commission’s
`proceedings were ongoing, Exelon finalized its purchase of
`
`
`
`
`
`9
`
`Everett, which is now owned by Constellation LNG, LLC,
`another subsidiary of ExGen.
`
`E. The Mystic Agreement
`
`In 2018, Mystic concluded that Mystic Station was no
`longer economically viable, notified ISO New England of its
`intent to retire when its existing capacity supply obligations
`expired in May 2022 and submitted the required Retirement
`De-List Bid. Following Mystic’s announcement, ISO New
`England analyzed the impact of Mystic 8 and 9’s retirements
`on the region’s fuel security during the winter months, when
`natural gas-fired power plants have difficulties obtaining the
`necessary fuel through the region’s limited pipeline network
`due to priority demands for heating. See Belmont Mun. Light
`Dep’t v. FERC, 38 F.4th 173, 180–81 (D.C. Cir. 2022)
`(discussing ISO New England’s fuel security analysis). ISO
`New England concluded that the loss of Mystic 8 and 9, given
`their unique reliance on imported LNG rather than vapor
`natural gas distributed through regional pipelines, would likely
`result in multiple days of “load shedding”—i.e., rolling
`blackouts—during
`the 2022
`through 2024
`capacity
`commitment periods. ISO New England further determined
`that Mystic 8 and 9’s retirements could affect the financial
`viability of Everett, whose retirement could further exacerbate
`the length and severity of load shedding events.
`
`In light of these findings, ISO New England sought to
`retain Mystic 8 and 9 for two years beyond their planned
`retirements. In May 2018, Mystic, acting pursuant to section
`205 of the FPA, filed with the Commission an agreement, the
`Mystic Agreement, among itself, Exelon and ISO New
`England
`that would provide Mystic
`cost-of-service
`compensation for the continued operation of Mystic 8 and 9
`from June 1, 2022, until May 31, 2024. We go into greater
`
`
`
`
`
`10
`
`detail infra as to several of the cost inputs comprising Mystic’s
`cost-of-service rate under the agreement but, in simplified
`terms, the rate is derived from four primary cost inputs: (1) a
`return on Mystic 8 and 9’s “rate base,” meaning the value of
`the facilities used to provide service to ratepayers less
`depreciation; (2) operation and maintenance expenses;
`(3) depreciation expenses; and (4) taxes.
`
`As part of its filing, Mystic attached a separate agreement
`between Mystic and Everett, referred to as the Everett
`Agreement. Per the Everett Agreement, over which the
`Commission disclaims jurisdiction, see Second July 2020
`Rehearing Order, at ¶ 43; FERC Br. 53, Mystic agreed to pay
`Everett a cost-based rate for the fuel used by Mystic 8 and 9
`alongside a monthly charge (Fuel Supply Charge) covering 100
`per cent of Everett’s fixed operating and maintenance costs as
`well as a return on investment tied to Everett’s rate base. As
`originally proposed, the Fuel Supply Charge would be offset
`by 50 per cent of the profits Everett earned on third-party sales
`over the course of the Everett Agreement.
`
`F. The Commission Proceedings
`
`This brings us to the Commission orders underlying this
`litigation. For clarity,
`rather
`than
`take
`the orders
`chronologically, we break up the orders according to the five
`disputed components of the Commission-approved Mystic
`Agreement.
`
`Mystic’s Rate Base: Under cost-of-service ratemaking
`principles, the starting point to calculate a generator’s return on
`capital is the generating facility’s rate base, or the value of the
`assets used to serve ratepayers. See NEPCO Mun. Rate Comm.
`v. FERC, 668 F.2d 1327, 1335 (D.C. Cir. 1981). Mystic
`initially proposed to set Mystic 8 and 9’s rate base according to
`the $925 million valuation it made in connection with the 2012
`
`
`
`
`
`11
`
`Constellation Energy Group-Exelon merger, before adding
`post-acquisition
`capital
`expenditures
`and
`subtracting
`depreciation. In its December 2018 Order, however, the
`Commission rejected Mystic’s approach as inconsistent with
`the Commission’s “original cost test,” which provides that a
`utility “may only earn a return on (and recovery of) the lesser
`of the net original cost of plant or, when plant assets change
`hands in arms-length transactions, the purchase price of the
`plant,” id. at ¶ 63; see infra Part III (explaining original cost
`test), and directed Mystic to reduce its valuation of Mystic 8
`and 9 to account for past sales of the units at prices lower than
`the 2012 valuation, see id. at ¶¶ 63–66.
`
`On rehearing, the Commission rejected Mystic’s claim
`that the original cost test, as applied by the Commission, was
`inappropriate to calculate its return on Mystic 8 and 9’s rate
`base, see generally Second July 2020 Rehearing Order, at
`¶¶ 105–111, and on compliance, rejected Mystic’s proposed
`rate base calculation for failing to account for the 2004 $547
`million transfer in lieu of foreclosure, see Compliance Order,
`at ¶ 45.
`
`Mystic’s Capital Structure: Alongside its rate base, a
`generator’s return on capital under a cost-of-service model is
`derived from its overall rate of return, which is dependent upon
`its capital structure—i.e., the relative amounts of debt and
`equity. See NEPCO, 668 F.2d at 1335. Mystic initially
`proposed using the capital structure of its immediate parent,
`ExGen: 67.28 per cent equity and 32.72 per cent debt. See
`December 2018 Order, at ¶ 35. The Commission rejected this
`proposal, finding the proposed structure too equity-heavy
`relative to the industry, see id. at ¶¶ 48–51, and instead directed
`Mystic to use the capital structure of ExGen’s parent, Exelon,
`which was 52.4 per cent debt and 47.6 per cent equity, id. at
`¶ 52. After Mystic sought rehearing,
`the Commission
`
`
`
`
`
`12
`
`reaffirmed its determination, again citing the anomalous nature
`of ExGen’s capital structure relative to the industry. See
`Second July 2020 Rehearing Order, at ¶¶ 132–34.
`
`After the petitions for review had been filed but before oral
`argument, the Commission issued an additional order that,
`although not subject to review in this proceeding, is
`nevertheless relevant. In February 2022, Exelon consummated
`a spinoff transaction that placed ExGen and Mystic under the
`corporate parentage of Constellation Energy Corporation. See
`Constellation Mystic Power, LLC, 179 FERC ¶ 61,081, at ¶ 6
`(May 2, 2022) (May 2022 Order). As a result, Mystic amended
`the Mystic Agreement to reflect the changes in corporate
`structure and, as relevant here, argued that Exelon’s capital
`structure was no longer relevant—as Exelon no longer had any
`relationship with Mystic—and again requested to use ExGen’s
`capital structure. Id. at ¶ 9. The Commission “agree[d] with
`Mystic that it would be inappropriate to continue basing its
`capital structure and cost of debt on those of Exelon
`Corporation,” id. at ¶ 25, but further explained that Mystic had
`not yet shown ExGen’s capital structure to be just and
`reasonable, id. at ¶ 24. The Commission accordingly set a
`hearing to determine the appropriate capital structure. Id. at
`¶¶ 24–25.
`
`Everett’s Costs: The Commission rejected Mystic’s
`proposal to recover 100 per cent of Everett’s fixed operating
`and maintenance costs via the Fuel Supply Charge, instead
`adopting its Trial Staff’s proposal that would allocate 91 per
`cent of Everett’s costs—the historical ratio of Everett’s vapor
`sales, as opposed to its LNG sales, to its total sales—and the
`Staff’s related revenue crediting mechanism, whereby Everett
`would retain up to 50 per cent of the margin on third-party
`forward sales, meaning those made at least three months in
`
`
`
`
`
`13
`
`advance.5 See December 2018 Order, at ¶¶ 133–35. The
`Commission also rejected Mystic’s proposal to include the
`Everett acquisition cost as part of Everett’s rate base, which is
`used to calculate the return-on-investment component of the
`Fuel Supply Charge. See id. at ¶¶ 148–49.
`
`rejected Mystic’s
`the Commission
`rehearing,
`On
`arguments regarding the exclusion of Everett’s acquisition cost
`from its rate base. See Second July 2020 Rehearing Order, at
`¶¶ 113, 118–20. Further, the Commission rejected arguments
`by the Massachusetts AG, one of the State Petitioners, that the
`Commission lacked jurisdiction to review and approve the
`inclusion of Everett’s fixed operating costs as a component of
`Mystic’s proposed cost-of-service rate, asserting that “[t]he
`Fuel Supply Charge is a component of Mystic’s cost-of-service
`rate and, as a result, is subject to Commission review and
`approval.” First July 2020 Rehearing Order, at ¶¶ 16–18, 26–
`31. Despite comments from several State Petitioners objecting
`to the Commission’s allocation of Everett-related costs, see
`Second July 2020 Rehearing Order, at ¶¶ 57–60, 62, the
`Commission reaffirmed the appropriateness of its 91 per cent
`allocation, see id. at ¶¶ 64–65. In response to comments noting
`that vapor sales are made to parties other than Mystic, the
`Commission reasoned that those sales nevertheless benefit
`Mystic “by helping to manage Everett’s tank.” Id. at ¶ 64. But
`the Commission did decide to eliminate revenue crediting,
`finding that “proper cost allocation based on cost-causation
`principles obviate[d] the need” for the revenue crediting and
`
`
`5 Under the revenue crediting mechanism, “the first 10 million
`MMBtus are credited 90 percent to Mystic (i.e., back to ratepayers)
`and 10 percent to Constellation LNG, revenue from the next 30
`million MMBtus are credited 80 percent to Mystic and 20 percent to
`Constellation LNG, and so on until all deliveries above 60 million
`MMBtus are credited 50/50 as initially proposed by Mystic.”
`December 2018 Order, at ¶ 134.
`
`
`
`
`
`14
`
`questioning its own jurisdiction to approve an incentive
`mechanism that “focuses directly on Everett’s conduct rather
`than Mystic’s.” Id. at ¶ 66. The Connecticut Parties, a subset of
`the State Petitioners, sought rehearing on the elimination of
`revenue crediting, arguing that “unless or until Mystic’s share
`of Everett costs is reduced to correspond to its use of the
`facilities,” the Commission should “restore the crediting
`mechanism.” J.A. 1664. The Commission denied their request.
`
`On this issue, then-Commissioner (now Chairman) Glick
`dissented from all of the orders at issue, asserting that the
`Commission overstepped its jurisdictional boundaries by
`reviewing and approving recovery of Everett-related costs that,
`in his view, bore little relationship to Mystic’s jurisdictional
`rate. See, e.g., December 2018 Order (Glick, C., dissenting);
`First July 2020 Rehearing Order (Glick, C., dissenting).
`
`True-Up Mechanism: Recognizing that many of the
`components of Mystic’s cost-of-service rate were based, at
`least in part, on Mystic’s projections of future costs, the
`Commission directed Mystic to include a “true-up” mechanism
`in the Mystic Agreement, which would allow parties to
`reconcile cost projections with actual expenditures via
`surcharges and refunds as necessary. See July 2018 Order, at
`¶ 20. Mystic initially proposed a true-up mechanism that would
`have applied only to specific subsets of rate inputs, see
`December 2018 Order, at ¶ 165, but the Commission rejected
`this approach, instead “direct[ing] that the true-up mechanism
`apply to the entire [Mystic] Agreement, with the exception of
`the [return on equity],” id. at ¶ 177. The Commission
`emphasized that the true-up process included Mystic’s
`revenues. Id. at ¶ 179. The Commission also noted that the
`reasonableness of tank congestion charges passed along to
`ratepayers “is more appropriately reviewed during the true-up
`process,” id. at ¶ 164, but later determined that review of tank
`
`
`
`
`
`15
`
`congestion charges was “no longer required” given its
`elimination of the revenue crediting mechanism, see Second
`July 2020 Rehearing Order, at ¶ 73.
`
`Mystic sought rehearing on the breadth of the true-up
`mechanism as it applied to pre-2018 costs related to Mystic 8
`and 9 that, in Mystic’s view, had already been fully litigated.
`See Second July 2020 Rehearing Order, at ¶ 79. The
`Commission denied rehearing, finding that those historic
`numbers had not yet been fully litigated and were thus
`appropriately “subject to true-up.” Id. at ¶ 86. Mystic also
`objected to the inclusion of revenues as part of the true-up
`process. Id. at ¶ 80. The Commission agreed with this argument
`and “set aside” its earlier requirement that Mystic “true-up
`revenues.” Id. at ¶ 88.
`
`The States Committee, another of the State Petitioners,
`sought clarification, or rehearing in the alternative, as to
`whether interested parties could still challenge the calculation
`of revenue credits despite the Commission’s decision to omit
`revenues from the true-up process. See J.A. 1716. As they see
`it, the Commission acknowledged their request, see December
`2020 Rehearing Order, at ¶ 25, but failed to address it
`adequately. See infra Part VI.B.1. With regard to the tank
`congestion charges,
`the States Committee also sought
`rehearing, arguing that if the costs of third-party sales are being
`passed on to ratepayers, ratepayers should have some
`mechanism to review and challenge the reasonableness of those
`sales, see J.A. 1712–13, arguments that the Commission
`addressed in its final rehearing order, see December 2020
`Rehearing Order, at ¶¶ 26–28.
`
`Clawback Provision: In its December 2018 Order, the
`Commission determined that the Mystic Agreement was not
`just and reasonable without a “clawback” provision—which
`
`
`
`
`
`16
`
`would require Mystic to reimburse ratepayers for certain
`capital and repair expenditures made over the course of the
`Mystic Agreement if Mystic 8 and 9 were to re-enter the New
`England energy market after the Agreement expires. See
`December 2018 Order, at ¶ 208. In essence, a clawback
`provision disincentivizes a generating facility from switching
`between cost-of-service and market-based rates so that
`ratepayers finance investments during the term of a cost-of-
`service agreement that benefit the facility beyond the term of
`the agreement. Id.; see also Midcontinent Indep. Sys. Operator,
`Inc., 161 FERC ¶ 61,059, at ¶ 55 (2017). The Commission
`accordingly directed Mystic to revise the Mystic Agreement to
`include a clawback provision. See December 2018 Order, at
`¶ 208. The States Committee sought clarification as to whether
`the required clawback provision would apply to consumer-
`funded investments and repairs in connection with both Mystic
`8 and 9 and Everett. See J.A. 1374.
`
`On compliance, Mystic proposed a clawback provision
`applicable to certain repairs and capital expenditures made by
`Mystic. See J.A. 1506 (proposed clawback
`language);
`Compliance Order, at ¶ 16. The States Committee and
`Connecticut Parties protested
`the omission of Everett
`expenditures from Mystic’s proposed clawback provision,
`pointing to the affiliate relationship between Mystic and
`Everett. See J.A. 1509–11 (States Committee); J.A. 1512–15
`(Connecticut Parties).
`
`The Commission ultimately approved Mystic’s proposed
`clawback provision. See Compliance Order, at ¶ 25. In the
`Second July 2020 Rehearing Order, the Commission rejected
`the request that the provision encompass Everett’s costs, noting
`that neither Everett nor the Everett Agreement falls within the
`Commission’s jurisdiction and concluding that it “lack[ed]
`jurisdiction to require a clawback, true-up, and/or refund of
`
`
`
`
`
`17
`
`Everett’s costs.” See Second July 2020 Rehearing Order, at
`¶ 43. The Commission further explained that, if Mystic 8 and 9
`retired while Everett remained
`in service,
`the Mystic
`Agreement would terminate, leaving “no rate within the
`jurisdiction of the Commission through which to order a
`refund.” Id. In the Compliance Order, the Commission denied
`the States Committee’s and Connecticut Parties’ related
`protests, referring back to the Second July 2020 Rehearing
`Order. See Compliance Order, at ¶ 28. The Commission also
`denied the Connecticut Parties’ subsequent request for
`rehearing for the same reasons it outlined in the July 2020
`orders. See December 2020 Rehearing Order, at ¶ 39.
`
`G. Petitions for Review
`
`Mystic and the State Petitioners petitioned for review of
`the various Commission orders modifying and ultimately
`approving the Mystic Agreement. Mystic objects to the
`Commission’s application of
`the original cost
`test
`in
`determining Mystic 8 and 9’s rate base; the selection of
`Exelon’s capital structure instead of ExGen’s; the exclusion of
`Everett’s acquisition cost from the Fuel Supply Charge
`calculation; and the inclusion of Mystic 8 and 9’s rate base
`components as part of the true-up process. The State
`Petitioners, for their part, object to the Commission’s exercise
`of jurisdiction of and allocation of Everett’s costs as part of the
`Fuel Supply Charge; the exclusion of Everett’s costs from the
`clawback provision; the failure to address the request to allow
`revenue credit calculations to be reviewed during the true-up
`process; the confusion over who can review the reasonableness
`of tank congestion charges during that process; and the failure
`
`
`
`
`
`18
`
`to address the incentives created by the Mystic Agreement’s
`treatment of delayed capital projects.
`
`We dismiss Mystic’s petition for review in part and deny
`it in part, and we grant the State Petitioners’ petitions. The
`opinion proceeds as follows: In Part III, we hold that the
`Commission’s application of the original cost test to determine
`Mystic 8 and 9’s rate base was not arbitrary and capricious. In
`Part IV, we dismiss Mystic’s objection to the Commission’s
`selection of capital structure as moot in light of the
`Commission’s May 2022 Order. In Part V, we find that the
`Commission acted arbitrarily and capriciously in allocating
`Everett’s operating costs but otherwise acted lawfully in
`excluding Everett’s acquisition cost from the Fuel Supply
`Charge calculation. In Part VI, we conclude that the
`Commission properly included historical rate base components
`in the true-up mechanism but also find that the Commission
`failed to respond to the State Petitioners’ request for
`clarification as to whether interested parties may challenge the
`calculation of Mystic’s revenue credits and that the December
`2020 Rehearing Order created confusion over who can review
`the tank congestion charges during the true-up process. Finally,
`in Part VII, we hold that the Commission’s jurisdictional
`rationale for excluding costs related to Everett from the
`clawback process does not constitute reasoned decisionmaking
`and that the Commission failed to address related arguments
`raised by the State Petitioners.
`
`II. STANDARD OF REVIEW
`
`We begin by setting forth the standard of review common
`to all of the objections brought by the petitioners. This Court
`will set aside a Commission order found to be “arbitrary,
`capricious, an abuse of discretion, or otherwise not in
`accordance with law.” 5 U.S.C. § 706(2)(A); see Del. Div. of
`
`
`
`
`
`19
`
`Pub. Advoc. v. FERC, 3 F.4th 461, 465 (D.C. Cir. 2021). Our
`role is not to ascertain “whether a regulatory decision is the best
`