throbber

`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`
`January 15, 2024
`
`
`
`
`Kimberly D. Bose, Secretary
`Federal Energy Regulatory Commission
`888 First Street, NE
`Washington, DC 20426
`
`RE: Milford (FERC No. 2534), Orono (FERC No. 2710), and Stillwater (FERC No. 2712) Projects;
`2023 Diadromous Fish Passage Study Report
`
`
`Dear Secretary Bose:
`
`On behalf of the licensees for the Projects listed below, Black Bear Hydro Partners, LLC is filing this
`2023 Diadromous Fish Passage Study Report for studies conducted at the Milford, Stillwater, and
`Orono hydroelectric projects, which are located on the Penobscot River in Maine:
`
`
`• Milford Project (FERC No. 2534), licensed to Black Bear Hydro Partners, LLC
`• Orono Project (FERC No. 2710), licensed to Black Bear Hydro Partners, LLC; Black Bear
`SO, LLC; and Black Bear Development Holdings, LLC
`• Stillwater Project (FERC No. 2712), licensed to Black Bear Hydro Partners, LLC; Black Bear
`SO, LLC; and Black Bear Development Holdings, LLC (collectively, “Black Bear”)
`
`
`Background
`
`Pursuant to Commission Orders “Amending License and Revising Annual Charges” for the Orono
`and Stillwater Projects (both dated September 14, 2012) and “Approving Fish Passage Design
`Drawings Under Articles 407 and 408” for the Milford Project (dated October 9, 2012), and consistent
`with the June 25, 2004 Lower Penobscot River Multiparty Settlement Agreement (Settlement
`Agreement), aspects of which were incorporated into the Orono Project license on December 8, 2005
`and the Milford and Stillwater Project licenses on April 18, 2005, the licensees constructed and
`installed upstream and downstream fish passage systems at the Milford, Orono, and Stillwater
`(downstream only) Projects in 2013 and 2014 to facilitate the passage of diadromous fish species on
`the Penobscot River. Articles 409, 411, and 408 of the Milford, Orono, and Stillwater Project licenses,
`respectively, also require evaluations of the constructed fishways to determine their effectiveness at
`passing alosines (collectively American shad, blueback herring, and sea run alewives) and American
`eels. The Commission-approved Species Protection Plan (SPP) and National Marine Fisheries
`Service’s (NMFS’s) 2012 Biological Opinion (BiOp) outline the passage effectiveness requirements
`for upstream and downstream-migrating Atlantic salmon adults and outmigrating juveniles (smolts).
`
` A
`
` summary of the quantitative monitoring studies conducted to date on the upstream and downstream
`Project fish passages are provided in Table 1 below. Additional diadromous fish passage studies
`conducted by the licensees at these Projects since 2014 for Atlantic salmon have been reported1
`separately to the Commission, as have the results of ongoing upstream eel monitoring efforts on the
`lower Penobscot River2.
`
`
`1 Annual Atlantic Salmon Species Protection Plan Report of Activities for Milford, Orono, Stillwater, West Enfield and
`Medway Projects are filed annually by March 30th.
`
` 2
`
` Annual Upstream Eel Fishway Operation, Monitoring, and Maintenance Report for Milford, Orono, Stillwater and
`West Enfield are filed with the Commission and the MDEP annually by March 31st.
`BLACK BEAR HYDRO PARTNERS, LLC
`1 Bridge Street, Milford, ME 04461
` T + 1 207.827.2247 F +1 207.827.4102 brookfieldrenewableUS.com
`
`
`
`

`

`
`
`
`
`
`
`
`
`
`Species Stillwater
`Upstream
`Salmon –
`NA
`juvenile
`Salmon -
`adult
`
`NA
`
`Shad -
`juvenile
`Shad -
`adult
`Herring -
`juvenile
`Herring -
`adult
`Eel - adult
`Eel -
`juvenile
`
`NA
`
`NA
`
`NA
`
`NA
`
`NA
`2014; 2016;
`2017; 2022
`
`Stillwater
`Downstream
`2014-2018
`10 yrs
`following smolt
`enhancements
`By proxy -
`2020 alosine
`study
`2017; 2018
`
`2020
`
`2018
`2016; 2021
`reanalysis
`NA
`
`Table 1 - Diadromous Fish Studies Conducted by Black Bear
`at the Stillwater, Orono and Milford Projects
`
`Orono
`Upstream
`NA
`
`Orono
`Downstream
`2014-2018
`10 yrs
`following smolt
`enhancements
`By proxy -
`2020 alosine
`study
`2017; 2018
`
`Milford
`Upstream
`NA
`
`2014; 2015
`
`NA
`
`2022
`
`2020
`
`2018
`2016; 2021
`reanalysis
`NA
`
`NA
`2015; 2019;
`2021
`NA
`2008 –
`2018
`
`Milford
`Downstream
`2014-2018
`10 yrs
`following smolt
`enhancements
`By proxy -
`2020 alosine
`study
`2017; 2018
`2020; 2021
`(sensor fish)
`2018
`2016; 2021
`reanalysis
`NA
`
`2014; 2015
`
`NA
`
`--
`
`NA
`
`2015; 2021
`
`NA
`2014; 2016;
`2022
`
`In addition, the licensees have conducted several years of qualitative fish passage evaluation and
`continued collaboration with the Maine Department of Marine Resources (MDMR) to collect upstream
`fish lift tallies of migratory fish at the Milford and Orono Projects in 2023 (see Table 2), including the
`trucking of river herring (collectively, alewife and blueback herring) upriver from Orono.
`
`Table 2 - Annual counts of American shad and river herring at the Milford and Orono Project
`fish lifts in the lower Penobscot River, Maine
`
`
`
`
`
`2014
`2015
`2016
`2017
`2018
`2019
`2020
`2021
`2022
`2023
`TOTAL
`
`Milford
`American
`River
`shad
`Herring
`812
`187,429
`1,806
`589,503
`7,862
`1,259,384
`3,868
`1,256,061
`3,958
`2,174,745
`2,522
`1,987,681
`11,276
`1,952,537
`11,581
`1,731,496
`7,582
`2,852,037
`4,154
`5,490,195
`55,421
`19,481,068
`
`
`
`
`Orono
`American
`River
`
`shad
`Herring
`
`0
`2,075
`
`1
`19,016
`
`6
`78,700
`
`0
`90,483
`
`6
`93,939
`
`9
`163,126
`
`2
`111,518
`
`2
`201,565
`
`2
`230,738
`
`2
`232,045
`1,223,205
`30
`
`BUSINESS GROUP NAME
`Street Address, City, State/Province, Zip/Postal Code
`T +1 123.456.7890 F +1 123.456.7890 brookfieldrenewableUS.com
`
`

`

`
`
`
`
`2023 Evaluations
`
`Upstream passage studies of the Milford fish lift for adult river herring (2019 and 2021) and American
`shad (2022) have demonstrated a significant number of failed passage attempts, many of which occur
`in the vicinity of the floor diffuser and V-gate as the fish pass through the entrance flume on their way
`to the lifting hopper. As a result of discussions with the resource agencies and Penobscot Indian
`Nation (PIN) at fish passage study planning meetings held in late 2022, an ad hoc work group
`comprised of fish passage engineers from the National Marine Fisheries Service (NMFS), U.S. Fish
`and Wildlife Service (USFWS), and biologists from the MDMR, PIN, and Black Bear, was established
`to explore options for modifying operational parameters of the Milford fish lift facility to potentially
`improve internal fish passage efficiency.
`
`Over the course of several virtual meetings held in early 2023, the ad hoc work group reviewed the
`Milford fish lift facility design and agreed that it is constructed and is being operated according to
`fishway engineering guidelines (USFWS 2019) and as intended. While the 180° turn in the fish lift
`entrance flume was an undesirable, but necessary, design feature, there is no evidence from the
`passage studies that the turn in the entrance flume is affecting fish passage at Milford. The work
`group considered laboratory and case studies focused on a variety of topics, including fish passage
`operations and reported passage results from other facilities with similar species, and they reviewed
`literature and best available science related to fish swimming abilities (burst, sustained, and long-
`term time periods). The group was not able to identify any other fish lifts with significantly or
`consistently higher passage results for alosine species of fish than what has been observed at Milford
`to date, including those with straight entrance flumes.
`
`Based on the results of the fish passage studies conducted at Milford for river herring and shad, and
`considering the extensive review and discussions, the work group came to consensus that using
`underwater cameras to qualitatively evaluate swimming behavior and responses of fish in the
`entrance flume of the Milford fish lift to various operating conditions (with a focus on injection of the
`supplemental auxiliary attraction flow upstream of the hopper and through the floor diffuser), including
`conditions outside of the recommended fishway operating guidelines, may provide valuable insight
`as to potential permanent changes in operating parameters of the lift to improve the overall
`effectiveness of the facility.
`
`As described in the study plan submitted to the Commission on March 8, 2023, an array of underwater
`cameras were installed in the entrance flume of the fish lift to monitor fish behavior in response to
`various attraction water, V-gate, and entrance gate settings. Real-time observations were made for
`each scenario, as well as reviews of recorded video. Based on observations from the 2023 study,
`Black Bear is recommending increases in the (1) maximum range of hopper flow to a velocity of 2.5
`ft/s, (2) the maximum range of flow and head differential at the entrance to 7 ft/s and 1.25 ft.,
`respectively, and (3) the width of the V-gate from 14.4 inches to 19.2 inches (i.e., changing the PLC
`setting for the V-gate from 6.0 to 8.0).
`
`The increased hopper velocity will provide for more attraction water flow injected upstream of the
`hopper, thus reducing the impact of flow emitted through the floor diffuser. The increased flow velocity
`at the entrance of the lift (from a range of 4-6 ft/s up to 5-7 ft/s), together with an increase in head
`differential at the entrance (from a range of 0.5-1.0 ft up to 0.75-1.25 ft.), were also found to improve
`fish passage conditions. And finally, Black Bear intends to change the V-gate setting from 6.0 to 8.0
`(from 14.4 to 19.2 inches) based upon the 2023 observations. However, Black Bear will defer to
`resource agency professional judgement if a different V-gate setting is preferred.
`
`
`
`BUSINESS GROUP NAME
`Street Address, City, State/Province, Zip/Postal Code
`T +1 123.456.7890 F +1 123.456.7890 brookfieldrenewableUS.com
`
`

`

`
`
`
`
`Please find attached a report covering the underwater video study conducted at the Milford Project
`in 2023. A draft of the report was distributed for agency and tribal review on November 14, 2023. A
`consultation meeting was then held virtually on December 13, 2023 with the resource agencies and
`PIN to present and review the study results and to answer questions. Responses to questions and
`comments received during the December 13th meeting are provided in Appendix B of the attached
`report, while correspondences associated with the agency reviews of the report and Black Bear’s
`responses are respectively provided in Appendices C and D. Finally, a copy of the PowerPoint slides
`prepared and presented by FishTec, Inc at the December 13th meeting are attached in Appendix E
`of the report. Where appropriate, the report has been revised based on the comments received.
`
`Please feel free to contact me by e-mail at Kevin.Bernier@brookfieldrenewable.com or by phone at
`(207) 951-5006 if you have any questions or comments.
`
`
`Sincerely,
`
`
`Kevin Bernier
`Senior Compliance Specialist
`
`Attachment:
`
`cc: S. Ledwin, M. Simpson, C. Clark, J. Valliere, L. Hammer; MDMR
`D. McCaw, C. Loring, Jr.; PIN
`H. Peterson, L. Rawlings; BIA
`B. Sojkowski, J. Rosset, A. Cross; USFWS
`J. Murphy, D. Dow; NMFS
`J. Perry, K. Dunham, K. Gallant; MDIFW
`L. Paye; MDEP
`S. Michaud, D. Bates, B. Brochu, C. Goodhart, R. Dill, R. Dorman, L. Macomber,
`D. Heidrich, S. Hill, R. Smith; Black Bear
`M. Sears, FishTec, LLC
`
`
`Black Bear Files:
`Black Bear/Licensing & Compliance/Milford 2534/01 Brookfield Corres
`Black Bear/Licensing & Compliance/Orono 2710/01 Brookfield Corres
`Black Bear/Licensing & Compliance/Stillwater 2712/01 Brookfield Corres
`
`
`
`
`
`BUSINESS GROUP NAME
`Street Address, City, State/Province, Zip/Postal Code
`T +1 123.456.7890 F +1 123.456.7890 brookfieldrenewableUS.com
`
`

`

`2023 Upstream Fish Passage Monitoring Study Report:
`Video monitoring of the entrance flume of the Milford fish li�.
`
`Milford Hydroelectric Project (FERC No. 2534)
`January 2024
`
`Prepared by FishTec, LLC
`
`Prepared for Black Bear Hydro Partners, LLC
`
`1
`
`

`

`
`
`Contents
`
`Introduc�on ...................................................................................................................................... 3
`1.0
`1.1.1
`Background ............................................................................................................................... 3
`1.1.2
`Milford Fish Li� Working Group ............................................................................................... 5
`1.1.3
`Milford Dam Fish Li� Descrip�on ............................................................................................. 6
`2.0
`Study Objec�ves ............................................................................................................................... 7
`3.0 Methodology ..................................................................................................................................... 8
`4.0
`Results ............................................................................................................................................. 14
`4.1
`Environmental Condi�ons ........................................................................................................... 14
`4.2
`Video Monitoring Observa�ons .................................................................................................. 16
`4.2.1
`High Hopper Flow Se�ng Observa�ons ................................................................................. 16
`4.2.2
`Even Flow Se�ng Observa�ons .............................................................................................. 18
`4.2.3
`Lower Hopper Flow Se�ng Observa�ons............................................................................... 19
`4.2.4
`V-Gate Se�ng Observa�ons ................................................................................................... 20
`5.0
`Discussion ........................................................................................................................................ 22
`6.0
`Reference Materials ........................................................................................................................ 23
`
`
`Appendices
`
`Appendix A – Milford Fish Li� Work Group Correspondence During the Spring 2023 Field Season
`
`Appendix B – Summary of Mee�ng Notes, Ques�ons and Responses from the December 13, 2023
`Consulta�on Mee�ng
`
`Appendix C – Correspondence Related to the Distribu�on of the Dra� 2023 Milford Entrance Flume
`Upstream Fish Passage Monitoring Study Report
`
`Appendix D – Responses to Writen Comments Received on the Dra� 2023 Milford Entrance Flume
`Upstream Fish Passage Monitoring Study Report
`
`Appendix E – Study Summary Presented by FishTec, LLC at the December 13, 2023 Study Report
`Consulta�on Mee�ng
`
`Appendix F – 2023 Observa�on Data Sheets and Fishway Inspec�on Forms
`
`
`
`
`
`2
`
`

`

`1.0
`
`Introduc�on
`
`Black Bear Hydro Partners, LLC (Black Bear or BBHP), an affiliate of Brookfield Renewable U.S.
`(Brookfield), is the licensee for the Milford Project (FERC No. 2534), which is located on the
`Penobscot River in Penobscot County, Maine, approximately 60 river kilometers upstream from
`Verona Island in Penobscot Bay. The Penobscot River provides habitat for several species of
`migratory (diadromous) fish, including Atlan�c salmon, alosines (i.e., blueback herring, alewives,
`and American shad), sea lamprey and American eels.
`
`Pursuant to the amended license for the Milford Project and a 2004 setlement agreement between
`the licensee, state and federal agencies, Penobscot Indian Na�on (PIN), and other stakeholders, the
`licensee developed a comprehensive upstream and downstream fish passage program to facilitate
`the passage of diadromous fish species on the Penobscot River. Since installa�on the Milford Dam
`fish li� facility has passed upstream nearly 9,300 Atlan�c salmon, an es�mated 19.5 million river
`herring, and over 55,000 adult American shad.
`
`By order dated April 18, 2005, FERC amended Ar�cle 409 of the Milford Project license to require
`the licensee to develop study plans to monitor the effec�veness of the fish passage facili�es.
`Subsequently the licensee has conducted qualita�ve and quan�ta�ve upstream passage efficiency
`studies for diadromous fish present at the facility since 2014. As explained in further detail in the
`sec�ons below, this study is a follow-up on previous studies and was designed to beter understand
`and improve upstream passage efficiency at the Milford Dam fish li�.
`
`
`1.1.1 Background
`Black Bear conducted radio telemetry studies in 2019 and 2021 to evaluate upstream passage
`effec�veness at Milford for adult river herring (alewife and blue back herring, combined), and for
`adult American shad in 2022 (NAI 2020, NAI 2022, NAI 2023). These studies indicated that the
`overall passage efficiency, efficiency at the entrance of the fish li�, and internal passage efficiency
`were all higher for river herring than for shad (Table 1).
`
`
`Table 1.
`
`Milford Fish Lift Passage Efficiencies and 95% CI Observed during Telemetry
`Studies.
`
`Passage Efficiency
`Nearfield
`Entrance
`Internal
`Overall
`
`River Herring
`2019
`94.5 (88.2-97.5)
`92.2 )85.1-96.0)
`74.7 (66.3-83.0)
`65.1 (56.9-73.8)
`
`River Herring
`2021
`
`--
`96.0 (89.9-98.5)
`89.9 (83.1-95.6)
`86.1 (79.0-92.8)
`
`Shad
`2022
`84.4 (73.4-91.4)
`71.6 (58.5-81.9)
`51.1 (34.9-66.6)
`30.9 (20.5-43.0)
`
`
`
`
`
`3
`
`

`

`For the 2021 river herring and 2022 shad passage studies, a fine-scale detec�on telemetry array1
`was installed in the entrance flume of the fish li�, which allowed for the collec�on of highly
`accurate �ming informa�on needed to evaluate detec�ons at the various antenna loca�ons.
`
`A significant number of failed passage atempts were observed for both species, the majority of
`which occurred in the vicinity of the floor diffuser and at the V-gate. Totals of 63 and 80
`unsuccessful passage atempts to move through the entrance flume of the Milford fish li� were
`recorded for river herring and American shad, respec�vely, during the two study years. Figure 1
`provides a comparison of the percentage of unsuccessful upstream passage atempts that did not
`reach the next upstream monitoring sta�on. The percentages reported at each sta�on are based on
`the number of successful passage atempts recorded at the adjacent downstream sta�on (e.g., the
`3% failure rate at the third detec�on sta�on for American shad is based on the successful detec�on
`of 77 of the 79 passage atempts which were recorded at the second detec�on sta�on).
`
`When compared between species, a similar patern is observed with 25% to 57% (river herring and
`shad, respec�vely) of the failed passage atempts occurring in the area of the floor diffuser. It is
`recommended that as much supplemental flow as possible from the auxiliary water system (AWS)
`be injected upstream of li�ing hoppers, as flow provided via diffusers in the entrance flume
`downstream of li�ing hoppers can create confusing currents (Larinier and Travade 2002; USFWS
`2019). Other important fish passage criteria, such as velocity of flow through the hopper and the
`swimming abili�es of the fish species to be passed, must be taken into considera�on. In order to
`meet recommended fish passage guidelines (USFWS 2019), the AWS flow for the Milford fish li� has
`been injected at a rate of approximately 40% of the flow upstream of the hopper and 60% of the
`flow through the floor diffuser located downstream of the hopper. This reduces the likelihood of
`exceeding the flow velocity criteria of 1.5 �/s through the hopper established in the USFWS 2019
`primarily for blueback herring.
`
`Based upon the observa�ons of the adult river herring passage studies conducted in 2019 and 2021
`and the adult shad study conducted in 2022, the highest fallback rate for alosine species when
`moving between two adjacent monitoring sta�ons occurred from the V-gate to the hopper blocking
`screens (i.e., 69% of the failed river herring atempts and 95% of the failed shad passage atempts
`occurred in this area of the entrance flume). However, it should be noted that there is a gap in
`telemetry coverage for the area between the upstream side of the V-gate and roughly the middle of
`the hopper, so there is uncertainty as to the specific point in this area at which the fish are falling
`back (i.e., at the V-gate or immediately upstream of the V-gate).
`
`A number of factors could be contribu�ng to the fall back behavior by alosines in the entrance
`flume, including; (1) high density of fish in the entrance flume in the vicinity of the V-gate or V-gate
`opening; (2) the mechanical opera�on of the V-gate as it opens or closes during a li�ing cycle;
`
`
`1 A Hermes Coordinator, which u�lizes a GPS signal to synchronize the internal clocks within a series of Sigma Eight Orion receivers to allow for
`the collec�on of the highly accurate �ming informa�on needed to evaluate detec�ons at the various antenna loca�ons.
`
`
`
`4
`
`

`

`and/or (3) the mechanical opera�on of the li�ing hopper (the frequency of li�s ranges from a li�
`every 10 minutes to every 25 minutes in the spring, depending on fish density).
`It is also possible that adult alosines in the Milford entrance flume may merely be responding to the
`behavior of other fish in the flume (i.e., following other fish that are backing downstream). Or that
`the presence of predatory species of fish (e.g., black bass or striped bass) within the entrance flume
`could be at �mes influencing adult alewives or shad, as well.
`
`There was consensus to establish an ad hoc work group to further evaluate poten�al causes for
`unsuccessful upstream passage, and if there are any opera�onal adjustments, op�mized se�ngs, or
`other modifica�ons that may improve the internal passage efficiency in the lower flume of the
`Milford fish li� facility.
`
`
`
`
`Note: Percentages are based on the number of unsuccessful passage attempts confirmed at the adjacent downstream station (NAI 2023).
`Figure 1:
`Species Comparison of Upstream Passage Attempts at the Milford Fish Lift.
`
`1.1.2 Milford Fish Li� Working Group
`An ad hoc work group (work group) comprised of fish passage engineers from the Na�onal Marine
`Fisheries Service (NMFS), U.S. Fish and Wildlife Service (USFWS), and biologists from the Maine
`Department of Marine Resources (MDMR), PIN, and BBHP, was established in December 2022 to
`explore op�ons for modifying opera�onal parameters of the Milford fish li� facility to poten�ally
`improve internal fish passage efficiency. This group met virtually four �mes between December 22,
`2022, and January 26, 2023, as well as corresponded on a regular basis via e-mail and met one-on-
`one, as needed.
`
`
`
`5
`
`

`

`The work group reviewed the Milford fish li� facility design and agreed that it is constructed and is
`being operated as intended and according to fishway engineering guidelines (USFWS 2019). While
`the 180° turn in the fish li� entrance flume was an undesirable but necessary design feature due to
`limita�ons of space, there is no evidence from the past passage studies that the turn is affec�ng fish
`passage at Milford.
`
`The work group reviewed laboratory and case studies focused on a variety of topics, including fish
`passage opera�onal parameters and reported passage results from other facili�es with similar
`species, and reviewed literature and best available science related to fish swimming abili�es (burst,
`sustained, and long-term �me periods). The work group was not able to iden�fy any other fish li�s
`with significantly or consistently higher passage results for alosine species of fish than what has
`been observed at Milford to date, including those with straight entrance flumes.
`
`The work group came to consensus that using underwater cameras to qualita�vely evaluate
`swimming behavior and responses of fish in the entrance flume of the fish li� to various opera�ng
`condi�ons, including condi�ons outside of the recommended fishway opera�ng guidelines, may
`provide valuable insight as to poten�al permanent changes in opera�ng parameters of the li� to
`improve the overall effec�veness of the facility.
`
`BBHP distributed a dra� a study plan developed by the work group for agency review on February
`7, 2023. Several mee�ngs were held to finalize the study plan, and the study commenced in April of
`2023. Appendix A includes the study plan and work group correspondence before and throughout
`the study.
`
`
`1.1.3 Milford Dam Fish Li� Descrip�on
`Upstream fish passage at Milford Dam is provided via a single entrance fish li� located immediately
`downstream from the powerhouse on the east side of the tailrace. A target of 190-210 cubic feet
`per second (cfs) is provided at the entrance of the fish li� through a combina�on of conveyance
`flow from the upper flume and the auxiliary water supply system, which adds supplemental flow in
`two areas: 1) upstream of the hopper, and 2) downstream of the hopper via a floor diffuser. The
`hopper can be operated manually or automa�cally (normal opera�ng condi�on) using a
`programmable logic controller (PLC). The entrance consists of a manually adjusted “overshot”
`atrac�on flow gate (also referred to as the “flap gate”), an adjustable V-gate, and a
`blocking/diffusion screen upstream of the li�ing hopper. The entrance flume is 10-feet-wide with a
`180 degree turn leading to a 12-�-wide by 17-�-long, 4,600 gallon li�ing hopper. The li�ing hopper
`rises using a mechanical hoist approximately 20 feet, and then it discharges into a 10-foot-wide by
`300-foot-long exit flume, which passes through the east end of the powerhouse to the headpond
`upstream of the outer trashracks. The opera�onal parameters for the Milford fish li� align with
`USFWS and NMFS engineering guidelines for fish li�s that pass diadromous fish, taking into
`considera�on the presence of alewife and blueback herring (river herring), including:
`
`
`
`6
`
`

`

`• 4.0 - 6.0 �/s flow velocity at the entrance while maintaining a differen�al of 0.5 – 1.0 �
`• 1.5 - 4.0 �/s entrance flume flow velocity
`• 1.0 - 1.5 �/s hopper flow velocity
`• 1.0 - 1.5 �/s exit flume flow velocity
`• 14.4-inch-wide V-gate se�ng (determined previously in consulta�on with the agencies)
`
`
`
`
`2.0 Study Objec�ves
`
`In the study plan, the work group proposed that the following fish li� parameters will be the ini�al
`focus of the 2023 evalua�ons:
`
`1. AWS flow distribu�on (hopper vs. floor diffuser)
`a. The majority of the AWS flow will be injected upstream of the hopper to
`reduce/eliminate undesirable flow characteris�cs in the area of the floor diffuser
`that may be confusing fish.
`b. The group will atempt to evaluate fish behavior across a range of AWS scenarios,
`star�ng with the baseline scenario (40% hopper / 60% floor diffuser).
`c. The velocity of flow through the hopper will be calculated for each scenario and
`recorded.
`
`2. Velocity at the Entrance
`a. The range of acceptable velocity of flow at the fishway entrance will be increased to
`5.0 – 7.0 �/s (vs. recommended 4.0-6.0 �/s for river herring) in an atempt to
`improve the fish li�’s entrance efficiency.
`b. A minimum water depth of 3.0 � over the flap gate will be targeted for all scenarios
`tested.
`
`Addi�onally, the work group agreed that other secondary parameters/condi�ons may also be
`assessed during the 2023 fish passage season including, but not limited to:
`
`a. Unit 6 being turned down or off
`b. V-gate se�ng
`c. Li� frequency
`
`
`
`
`7
`
`

`

`3.0 Methodology
`
`Run �ming data for river herring and shad since 2014 were used to determine the �ming for this
`study (Table 2). The following outlines the general underwater video monitoring strategy/schedule
`agreed upon by working groups members in the study plan:
`
`1. April 15th (or when river condi�ons allow) – the fish li� will be put into opera�on for the
`season.
`a. Opera�ng parameters – start with baseline (status quo)
`b. Conduct ini�al ocular assessment for a range of AWS and entrance flow se�ngs
`
`2. By May 1 (prior to fish arrival) - cameras installed/wired/tested
`a. Conduct range of AWS and entrance flow assessments via the cameras
`
`3. First week of river herring passage season
`a. Conduct video assessments of fish behavior across the range of AWS and entrance
`flow scenarios.
`b. Effort = the amount of �me spent observing per day/week is as long as is needed to
`understand what is going on
`c. Report back to the work group for discussion and consensus on approach going
`forward
`d. Adapt approach (and poten�al fish li� se�ngs) and conduct more video monitoring
`and assessments
`e. Second week of river herring passage season
`i. Implement work group sugges�ons/ make observa�ons / report back/ adapt
`
`4. Con�nue monitoring/assessments through the peak river herring and shad upstream
`passage periods.
`
`
`Table 2.
`
`Median Run Dates for River Herring and Shad at Milford since 2014.
`
`Year
`2014
`2015
`2016
`2017
`2018
`2019
`2020
`2021
`2022
`2023
`
`Median Run Date
`River Herring
`Shad
`Comments
`27-May
`16-Jun AWS - No bulkheads
`27-May
`18-Jun AWS - No bulkheads
`27-May
`15-Jun AWS - Bulkheads in place, but not effective
`23-May
`18-Jun AWS - Bulkheads in place and effective
`24-May
`15-Jun
`1-Jun
`20-Jun
`28-May
`5-Jun
`21-May
`1-Jun Very early spring - fish lift operating April 15
`21-May
`5-Jun Another early spring - fish lift operating April 15
`29-May
`22-Jun High water throughout passage season
`
`
`
`
`
`8
`
`

`

`A total of six Barlus-IP68 Underwater IP Cameras (Model: T5MP-1-1) with a 2.8mm lens, a 100°
`horizontal field of view and an image resolu�on of 5-megapixels were used for this study. The
`cameras were connected to the IP68 CCTV Underwater Security System Network Video Recorder
`(NVR) via power over ethernet (POE) cables.
`
`The cameras were installed during the first several weeks of April, and ini�al tes�ng was conducted
`on April 13th and April 20th, before the fish li� was opera�onal on April 24th. Further tes�ng and
`camera adjustments were conducted April 27th and April 28th, during the beginning of the river
`herring run. Tes�ng included visual inspec�on of the live video feed to verify that an adequate
`por�on of the water column was within view horizontally and ver�cally, as well an assessment of
`the viewing distance from the camera loca�on. The cameras were mounted to aluminum poles with
`custom made brackets, and the poles were mounted to the guardrails in a manner to allow for
`camera adjustments to be made as tailwater eleva�ons changed.
`
`Cameras were installed at the following loca�ons to observe fish behavior as they entered and
`passed through the lower flume, through the V-Gate and into the hopper.
`
`1. Camera 1 – located outside of the lower flume entrance, aimed slightly upstream.
`2. Camera 2 – located inside of the lower flume entrance, aimed slightly downstream.
`3. Camera 3 – located near the floor diffuser, aimed downstream.
`4. Camera 4 – located upstream of the floor diffuser, aimed across the flume.
`5. Camera 5 – located downstream of the V-gate, aimed slightly downstream.
`6. Camera 6 – located downstream of the V-Gate, aimed upstream.
`
`Figure 2 below shows these camera loca�ons and orienta�ons within the lower flume, with the
`floor diffuser loca�on depicted by the green-dashed area. Figure 3 through Figure 6 show
`photographs of all camera loca�ons. All six cameras were connected to a central temporary video
`viewing sta�on established on the walkway of the lower flume, which allowed for the viewing of
`live video feed from all six cameras simultaneously (Figure 7). The viewing sta�on (Figure 8) was
`protected from weather and housed a large monitor, the NVR, and an external hard drive that
`backed up the video data recorded onto the NVR during observa�ons throughout the study.
`
`
`
`
`
`9
`
`

`

`
`Camera Locations and Orientation in the Milford Fish Lift Lower Flume.
`
`
`Camera Location 1: Outside of the entrance looking across the flap gate.
`
`Figure 2.
`
`
`Figure 3.
`
`
`
`
`10
`
`

`

`
`Camera Location 2: Inside of the lower flume entrance looking downstream to
`the flap gate.
`
`Figure 4.
`
`
`
`
`Camera Locations 3 and 4: Looking across the floor diffuser.
`
`Figure 5.
`
`
`
`
`11
`
`

`

`
`Camera Locations 5 and 6: looking across and upstream at the V-Gate entrance
`
`Figure 6.
`
`
`
`
`View of the Live Feed Monitor in the Temporary Viewing Station
`
`
`
`Figure 7.
`
`
`
`
`12
`
`

`

`
`View of the Temporary Viewing Station Located at the Lower Flume.
`
`Figure 8.
`
`Observa�on efforts began once the first river herring began to show up in early May. This included
`ten total days spent observing anadromous fish between May 4th and June 15th over twenty-six flow
`combina�ons. Table 3 details the flow se�ngs tested on each day.
`
`
`
`Table 3.
`
`Lower Flume Flow Settings Testing during Study Period.
`
`Date
`4-May
`9-M

This document is available on Docket Alarm but you must sign up to view it.


Or .

Accessing this document will incur an additional charge of $.

After purchase, you can access this document again without charge.

Accept $ Charge
throbber

Still Working On It

This document is taking longer than usual to download. This can happen if we need to contact the court directly to obtain the document and their servers are running slowly.

Give it another minute or two to complete, and then try the refresh button.

throbber

A few More Minutes ... Still Working

It can take up to 5 minutes for us to download a document if the court servers are running slowly.

Thank you for your continued patience.

This document could not be displayed.

We could not find this document within its docket. Please go back to the docket page and check the link. If that does not work, go back to the docket and refresh it to pull the newest information.

Your account does not support viewing this document.

You need a Paid Account to view this document. Click here to change your account type.

Your account does not support viewing this document.

Set your membership status to view this document.

With a Docket Alarm membership, you'll get a whole lot more, including:

  • Up-to-date information for this case.
  • Email alerts whenever there is an update.
  • Full text search for other cases.
  • Get email alerts whenever a new case matches your search.

Become a Member

One Moment Please

The filing “” is large (MB) and is being downloaded.

Please refresh this page in a few minutes to see if the filing has been downloaded. The filing will also be emailed to you when the download completes.

Your document is on its way!

If you do not receive the document in five minutes, contact support at support@docketalarm.com.

Sealed Document

We are unable to display this document, it may be under a court ordered seal.

If you have proper credentials to access the file, you may proceed directly to the court's system using your government issued username and password.


Access Government Site

We are redirecting you
to a mobile optimized page.





Document Unreadable or Corrupt

Refresh this Document
Go to the Docket

We are unable to display this document.

Refresh this Document
Go to the Docket